Resolved
To note the latest position on capital expenditure and resources.
The Executive noted this item on Tuesday 6 November 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the latest position on capital expenditure and resources.
Appendix LONDON BOROUGH OF SUTTON Page 19 Agenda Item 4 THE EXECUTIVE 6/11/07
Capital Budget 2007/08 - Progress Report: Adult Social Services and Housing
1 2 3 4 5 6 7 8 Cap Total Line Previous Latest Profiled Prog Cost of Schemes Payments to No Estimate Estimate Estimate to Ref Scheme 2007/08 2007/08 30-Sep-07 30-Sep-07 £'000 £000's £000's £000's £000's
HOUSING SCHEMES:
GENERAL FUND COMMITTED
SCHEMES CALLING ON GENERAL LBS RESOURCES 1 C003 N/A Temporary Accommodation 916 916 495 512 2 C019 2,831 Accommodation at Sutton Gate 0 0 0 8 3 C032 300 Loans for Boiler Replacement at Roundshaw 300 300 0
3,131 1,216 1,216 495 520 ROUNDSHAW REGENERATION 4 C005 8,354 Roundshaw - LBS Spend 52 52 10 10 5 C009 6,391 Phoenix Centre (LBS/SRB/PSA/Lottery/Priv Dev) 31 31 31 43
14,745 83 83 41 53
SCHEMES ATTRACTING SPECIFIC FUNDING 6 C004 8,712 Durand Close Development / Feasibility (LBS/Grant/S106) 1,676 1,676 600 662 7 C033 45 Travellers Sites - The Patures (Grant/LBS) 45 45 0
8,757 1,721 1,721 600 662
UNCOMMITTED SCHEMES CALLING ON GENERAL LBS RESOURCES 8 C027 25 Homechoice Premises Improvements 25 25 10
25 25 25 10
26,658 SUB TOTAL HOUSING GENERAL FUND 3,045 3,045 1,146 1,235
HRA COMMITTED SCHEMES CALLING ON GENERAL HRA RESOURCES 9 C001 285 Sheltered Housing 22 22 0 10 C025 145 Extension to 67 Brinkley Road 37 37 25 1 11 C028 450 Sheltered Housing Improvements 350 350 64
880 409 409 89 1
CAPITAL WORKS TO HRA DWELLINGS 12 C010 3,878 Roofing Works 470 470 269 186 13 C011 9,224 Window Replacement 2,301 2,301 1,672 1,676 14 C012 7,565 Mechanical & Electrical works 383 383 73 94 15 C013 5,621 Heating Works 579 579 332 279 16 C014 1,402 Communal Areas 17 17 0 8 17 C015 13,363 Miscellaneous Works 2,384 2,334 1,433 1,339 18 C016 11,653 Fees & Variations in Tender Costs 3 3 0 237
52,706 Total Major Repairs Programme 6,137 6,087 3,779 3,819
SCHEMES ATTRACTING SPECIFIC FUNDING
19 C034 50 Extensions and Deconversions (Grant) 0 50 0
50 0 50 0
UNCOMMITTED
20 C026 35 DDA Improvements to Estate Surgeries 35 35 16 21 C029 100 Sheltered Housing - Asset Management Strategy 50 50 0
135 85 85 16
53,771 SUB TOTAL HOUSING HRA 6,631 6,631 3,884 3,820
80,429 TOTAL HOUSING 9,676 9,676 5,030 5,055 Appendix Agenda Item 4 1 2 3 Page 4 20 5 6 7 8 Cap Total Line Previous Latest Profiled Prog Cost of Schemes Payments to No Estimate Estimate Estimate to Ref Scheme 2007/08 2007/08 30-Sep-07 30-Sep-07 £'000 £000's £000's £000's £000's
ADULT SOCIAL SERVICES SCHEMES:
COMMITTED
SCHEMES CALLING ON GENERAL CAPITAL RESOURCES 22 C502 N/A Minor Works - Other * 30 30 15 8 23 C512 3,200 Modernisation of Learning Disabilities Day Services 2,230 150 0 3 24 C516 855 Package of Improvements - Residential Care Homes 688 688 250 357
4,055 2,948 868 265 368
SCHEMES ATTRACTING SPECIFIC FUNDING 25 C515 392 Mental Health Project of the Social Exclusion Unit (SCE-R) 46 46 40 36 26 C518 170 Improve the Care Home Environment 170 170 0 27 C509 0 Target 5 - Increasing Adoption Rates for Looked After Children (PSA) 0 0 0 3
562 216 216 40 39
UNCOMMITTED
28 C517 80 Sutton Town Centre - Adult Changing Rooms for Disabled 40 40 0
80 40 40 0
4,697 TOTAL SOCIAL SERVICES 3,204 1,124 305 407
85,126 TOTAL COMMUNITY SERVICES 12,880 10,800 5,335 5,462
Payments as % of Latest estimate 51% Payments as % of Profiled estimate 102%
* = Rolling Programme
E:\moderngov\Data\AgendaItemDocs\3\4\0\AI00006043\[CapMonASSH0.XLS]Strat
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CapMon ASS&HReport | 55 KB | DownloadRead as text |
PDF |
CapMon CYP&LSReport | 54 KB | Download |
PDF |
CapMon E&LReport | 57 KB | Download |
PDF |
CapMon Res&CEReport | 55 KB | Download |
PDF |
CapMon reportReport | 62 KB | Download |
Follow The Executive at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 May 2012 | Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... | Noted | Open |
| 8 May 2012 | Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... | Agreed | Open |
| 8 May 2012 | Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... | Approved | Open |
| 8 May 2012 | Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. | Approved | Open |
| 8 May 2012 | Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.