Resolved
To note the latest position on capital expenditure and resources.
The Executive noted this item on Monday 3 December 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the latest position on capital expenditure and resources.
Appendix LONDON BOROUGH OF SUTTON Page 23 Agenda Item 4 THE EXECUTIVE 3/12/07
Capital Budget 2007/08 - Progress Report Adult Social Services and Housing
1 2 3 4 5 6 7 8 Cap Total Line Previous Latest Profiled Prog Cost of Schemes Payments to No Estimate Estimate Estimate to Ref Scheme 2007/08 2007/08 31-Dec-07 31-Oct-07 £'000 £000's £000's £000's £000's
HOUSING SCHEMES:
GENERAL FUND COMMITTED
SCHEMES CALLING ON GENERAL LBS RESOURCES 1 C003 N/A Temporary Accommodation 916 916 800 577 2 C019 2,756 Accommodation at Sutton Gate 0 0 0 8 3 C032 300 Loans for Boiler Replacement at Roundshaw 300 150 30
3,056 1,216 1,066 830 585 ROUNDSHAW REGENERATION 4 C005 8,354 Roundshaw - LBS Spend 52 52 20 11 5 C009 6,391 Phoenix Centre (LBS/SRB/PSA/Lottery/Priv Dev) 31 31 31 43
14,745 83 83 51 54
SCHEMES ATTRACTING SPECIFIC FUNDING 6 C004 8,712 Durand Close Development / Feasibility (LBS/Grant/S106) 1,676 1,676 1,276 676 7 C033 45 Travellers Sites - The Patures (Grant/LBS) 45 45 0
8,757 1,721 1,721 1,276 676
UNCOMMITTED SCHEMES CALLING ON GENERAL LBS RESOURCES 8 C027 25 Homechoice Premises Improvements 25 25 0
25 25 25 0
26,583 SUB TOTAL HOUSING GENERAL FUND 3,045 2,895 2,157 1,314
HRA COMMITTED SCHEMES CALLING ON GENERAL HRA RESOURCES 9 C001 339 Sheltered Housing 22 7 5 2 10 C025 145 Extension to 67 Brinkley Road 37 37 25 1 11 C028 465 Sheltered Housing Improvements 350 140 64 12 C029 100 Sheltered Housing - Asset Management Strategy 50 5 0
1,049 459 189 94 3
CAPITAL WORKS TO HRA DWELLINGS 13 C010 3,878 Roofing Works 470 470 439 186 14 C011 9,224 Window Replacement 2,301 2,301 1,803 1,707 15 C012 7,565 Mechanical & Electrical works 383 383 217 102 16 C013 5,621 Heating Works 579 579 511 290 17 C014 1,402 Communal Areas 17 17 8 8 18 C015 13,363 Miscellaneous Works 2,334 2,334 1,896 1,421 19 C016 11,653 Fees & Variations in Tender Costs 3 3 0 237
52,706 Total Major Repairs Programme 6,087 6,087 4,874 3,950
SCHEMES ATTRACTING SPECIFIC FUNDING
20 C034 50 Extensions and Deconversions (Grant) 50 10 0
50 50 10 0
UNCOMMITTED
21 C026 35 DDA Improvements to Estate Surgeries 35 35 16
35 35 35 16
53,840 SUB TOTAL HOUSING HRA 6,631 6,321 4,984 3,953
80,423 TOTAL HOUSING 9,676 9,216 7,141 5,267 Appendix Agenda Item 4 1 2 3 Page 4 24 5 6 7 8 Cap Total Line Previous Latest Profiled Prog Cost of Schemes Payments to No Estimate Estimate Estimate to Ref Scheme 2007/08 2007/08 31-Dec-07 31-Oct-07 £'000 £000's £000's £000's £000's
ADULT SOCIAL SERVICES SCHEMES:
COMMITTED
SCHEMES CALLING ON GENERAL CAPITAL RESOURCES 22 C502 N/A Minor Works - Other * 30 30 20 8 23 C512 3,700 Modernisation of Learning Disabilities Day Services 150 150 20 6 24 C516 855 Package of Improvements - Residential Care Homes 688 688 400 357
4,555 868 868 440 371
SCHEMES ATTRACTING SPECIFIC FUNDING 25 C515 392 Mental Health Project of the Social Exclusion Unit (SCE-R) 46 46 46 36 26 C518 170 Improve the Care Home Environment 170 170 100 27 C509 0 Target 5 - Increasing Adoption Rates for Looked After Children (PSA) 0 0 0 3
562 216 216 146 39
UNCOMMITTED
28 C517 80 Sutton Town Centre - Adult Changing Rooms for Disabled 40 0 0
80 40 0 0
5,197 TOTAL SOCIAL SERVICES 1,124 1,084 586 410
85,620 TOTAL COMMUNITY SERVICES 10,800 10,300 7,727 5,677
Payments as % of Latest estimate 55% Payments as % of Profiled estimate 73%
* = Rolling Programme
E:\moderngov\Data\AgendaItemDocs\5\4\4\AI00007445\[CapMonASSH0.XLS]Strat
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cap Mon ASSHReport | 55 KB | DownloadRead as text |
PDF |
Cap Mon CYPLSReport | 54 KB | Download |
PDF |
Cap Mon E&LReport | 57 KB | Download |
PDF |
Cap Mon ReportReport | 61 KB | Download |
PDF |
Cap Mon Res&CEReport | 55 KB | Download |
Follow The Executive at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 May 2012 | Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... | Noted | Open |
| 8 May 2012 | Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... | Agreed | Open |
| 8 May 2012 | Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... | Approved | Open |
| 8 May 2012 | Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. | Approved | Open |
| 8 May 2012 | Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.