(i) To note the increased cost of the Library and Civic Offices project and the impact of this on the Capital Replacement Programme (CRP) in 2008/09; (ii) To agree that funding of £2.045m from 2009/10 and 2010/11 be brought forward to meet essential compliance and health and safety work, existing project commitments at both Cheam and Westcroft Leisure Centres and a number of other high profile schemes (as shown in Appendix 3 to the report); (iii) To amend capital estimates to reflect the revised profile of spending for the CRP over the period 2008/11 and release financial provision for the 2008/09 CRP of £3.7m along with schemes funded from the main capital programme for Westcroft Leisure Centre changing rooms (£100k scheme E154) and Cheam Leisure Centre roof (£170k scheme E117); (iv) To agree that the total revenue loss of £380k from the closure of both Cheam and Westcroft Leisure Centres be met from ... view the full minutes text for item 430.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report of the Executive Head Of Construction & Property
Impact of Cost of Civic Offices and Central Library Project on Capital Replacement Programme 2008/9 including Westcroft and Cheam Leisure Centres Ward Location: Borough Wide Author(s) and Contact Phone Numbers: Ade Adebayo ext. 6109 Claire De Vos ext. 4926 Area Served: Borough Wide Executive Councillor(s): John Drage and Graham Tope
Executive Decision Report
Summary This report summarises the progress made to the essential remedial works being undertaken to the Civic offices and Sutton Central Library; additional and unforeseen works which have been identified during the project and their associated costs; and the impact these costs have on the programmed projects within the Capital Replacement Programme in 2008/9 and future years. The report also summarises proposed works at both Cheam and Westcroft leisure centres and advises on required closure periods. Recommendations The Executive is recommended to: 1. Note the increased cost of the Library and Civic Offices Project and the impact of this on the Capital Replacement Programme (CRP) in 2008/9. 2. Agree that funding of £2.045m from 2009/10 & 2010/11 is brought forward to meet essential compliance and health and safety work, existing project commitments at both Cheam and Westcroft Leisure Centres and a number of other high profile schemes. 3. Amend capital estimates to reflect the revised profile of spending for the CRP over the period 2008/11. Release financial provision for the 2008/09 CRP of £3.7m along with schemes funded from the main capital programme for Westcroft changing rooms (£100k scheme E154) and Cheam roof (£170k scheme E117). 4. Approve meeting the total revenue loss of £380k from the closure of both Cheam and Westcroft leisure centres from the central contingency.
1. Background 1.1 Essential Maintenance at the Civic Centre and Central Library commenced in January 2008, following investigations into the condition of and hygiene within ventilation duct work which revealed that not only the system was in a very poor state, but also that the fire dampers were not functioning. 1.2 The failure of the fire dampers to work has meant that the buildings have an increased risk of fire spread through ducts to other floors in the case of a fire. Agenda Item 15 Page 8
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.