Item793
Resolved
To agree: (i) the appointment of the selected contractor: Erith Group Ltd; (ii) to amend capital estimates for £898k for the Defra grant awarded to carry out the remediation works, and an additional £20k to be allocated from the capital budget set aside for general contaminated land; and (iii) to release financial provision of £918k so that work can proceed in September 2008. To agree: (i) the appointment of the selected contractor: Erith Group Ltd; (ii) to amend capital estimates for £898k for the DEFRA grant awarded to carry out the remediation works, and an additional £20k to be allocated from the capital budget set aside for general contaminated land; and (iii) to release financial provision of £918k so that work can proceed in September 2008.
Word for word from the decision Sutton published for this meeting.
Source: moderngov.sutton.gov.uk