Sutton South, Cheam and Belmont Local Committee noted this item on Thursday 12 February 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the item re-circulated with the agenda.
Page 37 Agenda Item 12
RE-CIRCULATED ITEM
London Borough of Sutton
Sutton South, Cheam and Belmont Local Committee
4th December 2008
Cheam Leisure Centre – Update Report
1.0Introduction
1.1The overall programme of work included the replacement of the lead main; the relining of the swimming pool; provision of safe access ways and lighting to the main roof void; proprietary coating to the main pitch of the swimming pool hall roof; repointing of brickwork; repairs to the gables, parapet walls and rain water goods; major repairs to the flat roof areas above the gym; replacement of the roof covering to the link corridor leading to the squash courts and provision of edge protection to various areas.
1.2The main contractor for the project is Willmot Dixon Sustain, who is the Council’s appointed contractor for undertaking works of repairs and maintenance to the fabric of our buildings.
2.0Swimming Pool Works and Replacement Main
2.1The relining of the pool is satisfactorily complete. As part of the works, the original under water pool windows have been blocked up to eliminate the risk of leakage into the pool side corridors, and to enable the safe completion of the replacement main.
2.2The replacement of the original lead main has been successfully replaced.
3.0Roofing Works
3.1The provision of safe access ways and lighting to the main roof void is complete, and this now permits the servicing of air handling plant within the main roof void.
3.2Approximately 85% of the coating to the main pitched asbestos corrugated sheet roof serving the main pool hall is complete. The Marley system is applied across the sheet material and the inset Georgian lay lights.
3.3Works to the flat roof areas above the gym have commenced.
3.4The flat roof to the link walkway to the squash courts has been stripped and revealed that additional works, including replacement of roof lights will be required. The extent of the repair could only be fully established when the roof was stripped.
1 Agenda Item 12 Page 38
4.0Contractors’ Performance and Programme Issues
4.1The swimming pool liner has been installed to a high standard. There was a delay of one week to ensure an appropriate quality of finish was achieved.
4.3The roofing works were very slow to start fully on site, and as a consequence the works will not complete on programme on 4th December 2008.
4.4There still remains work to be carried out to parapets and to the main roof. The target now is to complete the remainder of works that requires safe access by scaffold to be completed by the 19 December so that the scaffolding can be taken down and removed to ensure security of the building over the Christmas holiday.
4.5The pointing to the parapet walls will therefore not be completed, and arrangements will be made to undertake this as a separate exercise in the early New Year.
Claire De Vos Interim Head of Property Care Construction and Property. LBS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cheam leisure centreReport | 61 KB | DownloadRead as text |
Follow Sutton South, Cheam and Belmont Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Minutes of the previous meetingthat the minutes of the meeting held on 5 February 2026 be agreed as an accurate record. On behalf of the Committee, ... | Agreed | Open |
| 5 Feb 2026 | Minutes of the previous meetingthat the minutes of the meeting held on 18 September 2025 be agreed as an accurate record. | Agreed | Open |
| 18 Sep 2025 | Minutes of the previous meetingRESOLVED : That the minutes of the meeting held on 3 July 2025 be agreed as an accurate record. | Agreed | Open |
| 3 Jul 2025 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 3 April be agreed as an accurate record. | Agreed | Open |
| 3 Apr 2025 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 6 February 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.