(i) To note the progress of the project; (ii) To release the balance of £4.106m financial provision, of which £2.606m is the council’s commitment for this scheme, so the main building works can commence, subject to Sutton & Merton PCT and the council entering into a Capital Grant Agreement for the transfer of £1.5m to the council (paragraph 3.1 of the report); (iii) To agree that capital estimates are amended to reflect the latest profile set out in paragraph 3.2 of the report. Councillor John Drage declared a personal interest, as he is a non-executive director of the PCT.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
London Borough of Sutton The Executive – 9th March 2009 Report of the Executive Head of Service – Learning Disabilities The New Resource Centre at Anton Crescent Ward Location: Author(s) and Contact Phone No: Not applicable Shaun O’Leary – Executive Head of Service Learning Disabilities and Mental Health 020 8770 4505 Mike Miles - Project Manager Construction & Property Services Environment & Leisure Group 0208 770 6308 Adrienne Stathakis – Senior Consultant in Project Management and Modernisation 020 8770 6827 Area Served: Borough wide Executive Councillor: Colin Stears
Key Decision Report Summary This report provides an overview and update on the provision of the new Resource Centre for Adults with Learning disabilities at Anton Crescent.
A number of options were considered; the preferred position agreed was to locate the facility on the old transport site adjacent to the current Hallmead day centre.
Recommendations We recommend The Executive to:
1. To note the progress of this project;
2. Release the balance of £4.106 million financial provision,of which £2.606 million being the Council’s commitment for this scheme so the main building works can commence, subject to Sutton and Merton Primary Care Trust and the Council entering into a Capital Grant Agreement for the transfer of £1.5 million to the Council (See paragraph 3.1.); and
3. To agree that capital estimates are amended to reflect the latest profile set out under 3.2.
1. Background 1.1 The existing Hallmead Special Care Unit (15 user capacity) and Hallmead Day Centre (200 user capacity) have reached the end of their useful and economic life. The Day Centre is a converted industrial building dating from the 1970’s and the Special Care Unit, built in the 1980’s, is now cramped and in need of substantial updating and refurbishment. Agenda Item 6 Page 40
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.