Council Housing - Major Works Programme - Procurement of Contractors and Consultants

Approved Executive 1 paper

The Executive approved this item on Monday 15 March 2010. Below is the council's own wording, with the papers it was decided on.

Item243

Resolved

To approve the appointment of the following in relation to the Council’s five-year ‘decent homes’ major works programme:- (i) Mullaly & Co and Lakehouse Contracts Ltd as external works contractors (ii) Apollo Housing and Lakehouse Contracts Ltd as internal works contractors (iii) Amey and Bailey Garner to manage the external works contracts.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to The Executive

Page 49 Agenda Item 6b

London Borough of Sutton

Executive - 15 March 2010

Report of the Executive Head of Community Living

COUNCIL HOUSING MAJOR WORKS PROGRAMME -PROCUREMENT OF CONTRACTORS AND CONSULTANTS Ward Location: Not Applicable Author and Contact Phone Number: Trevor Hart (x5844) Area Served: Borough-wide Executive Councillor: Colin Stears

Executive Decision Report Summary This report sets out for Member approval a number of contractors and consultants to be appointed to undertake the programme of major works to the Council’s housing over the coming years with the aim of bringing all the stock up to the decent homes standard. Recommendations I recommend the Executive to: (i) approve the appointment of Tenderers A and B as external works contractors in relation to the five year ‘decent homes’ programme of major works; (ii) approve the appointment of Tenderers G and H as internal works contractors in relation to the five year ‘decent homes’ programme of major works; (iii) approve the appointment of Tenderers L and M as consultants to manage the external works contracts.

1. Background 1.1 Under the management agreement between the Council and Sutton Housing Partnership (SHP) contracts for major repair and improvement works are let in the name of the Council. However, SHP as the Authority’s housing management provider, is responsible for the procurement (tendering) process. 1.2 In light of our anticipated ALMO funding award of £112.5m becoming available once SHP had achieved a ‘2-star’ rating at its reinspection last October, earlier in 2009 the ALMO began the process of procuring a number of contractors and consultants who would become responsible for the major works programme (often referred to as the ‘decent homes’ programme) over the coming five years. 1.3 In the past, Council approval to the appointment of contractors and consultants has generally been sought via Delegated Decision Notices, based on recommendations put forward by SHP. However, in light of the potential level of expenditure involved and the intention to appoint a number of firms to see through the whole five-year decent homes programme, it was considered appropriate that The Executive should be asked to approve SHP’s recommendations. Agenda Item 6b Page 50

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of major works contractors etcReport 94 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
SB
Councillor Sean BrennanChair, present
RD
Councillor Ruth DombeyVice-Chair, present
TB
Councillor Tony Brett YoungExecutive Councillor, present
JD
Councillor John DrageExecutive Councillor, present
LG
Councillor Lyn GleesonExecutive Councillor, apologies
CH
Councillor Colin HallExecutive Councillor, present
CS
Councillor Colin StearsExecutive Councillor, present
GT
Councillor Graham TopeExecutive Councillor, present

On this subject at Sutton

Search all
  1. Council Housing - Major Works Programme - Procurement of Contractors and ConsultantsThis decision
  2. Housing Revenue Account (HRA) Major Works - Fire SafetyApproved
  3. Housing Revenue Account Major Works Contracts Approval (Rosehill Court and Social Housing Decarbonisation Fund Wave 2)Approved
  4. Sutton Housing Partnership Major Works Programme - Kitchens and Bathrooms Contract UpdateApproved
  5. Sutton Housing Partnership Major Works and Whole Block RetrofitDecided
  6. Sutton Housing Partnership - Major Works ProgrammeApproved

More from Sutton The Executive

All decisions
MeetingDecisionOutcome
8 May 2012 Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... Noted Open
8 May 2012 Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... Agreed Open
8 May 2012 Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... Approved Open
8 May 2012 Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. Approved Open
8 May 2012 Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies