Resolved
( i ) To agree the scoping paper for social care IT replacement.
Scrutiny Overview Committee agreed this item on Tuesday 20 July 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
( i ) To agree the scoping paper for social care IT replacement.
Page 7 Agenda Item 4
Scrutiny Overview Committee
20 July 2010
DRAFT TERMS OF REFERENCE: Social Care IT Systems Replacement
1. Description of topic (pinning down exactly what is to be scrutinised and what would not be included) At their meeting of 7 June 2010 The Executive requested that a scrutiny review of the business case and of the future provision of social care IT systems be undertaken in parallel with the procurement exercise.
Sutton implemented the PARIS system in 2002 and has subsequently provided subsequent systems to address the needs of the service which PARIS could not provide i.e. Abacus for financial management, the Support Portal for personalisation, and Delia to manage interfaces between systems.
A business case has been put forward for the replacement of the current PARIS/Abacus systems which will minimise the need for a further in house portal and interface programming.
This investigation will focus on the timing, reasons, benefits and outcomes of replacing this system as outlined in the Business Case.
It will not focus on procurement exercise.
2. Aims of the investigation (brief description of the required outcomes e.g. improved service performance, better procedures for customers, increased value for money) • To review the future implementation and development of social care IT systems and to ensure that it provides a cost effective efficient process. • To review the management arrangements for effective implementation and development of future social care IT system, and to compare them with other authorities. • To seek assurances that the development of any new IT system procured will be met on time, within budget and to agreed functionality.
Suggested areas for investigation
To see whether the Social Care IT Systems Replacement: 1. Meets the services’ and Council’s needs for financial management and planning. 2. Provides accurate, timely and user-friendly data and collated information for the effective commissioning and provision of services, and submission of reports to central government 3. Provides adequate flexibility to ensure required changes of Transforming Social Care are taken into account.
9th July 2010 Agenda Item 4 Page 8
Also: 4. To review the management arrangements for the effective implementation and development any new system including staffing of the support team, training staff and budget, and contracts. 5. To receive further information on services’ needs, database requirements and training, and how any new system will satisfy the needs of service managers from social services, IT and finance. 6. To receive information on system links between management, administration and users. 7. To receive further information regarding expected efficiencies – are they realistic or sustainable.
3. Background information (based on existing information including plans and strategies, recent committee reports, comparative performance data, consultation information, general trends from complaints, councillors’ casework, media clips). This information should help provide the evidence base for the scrutiny investigation. PARIS is one of a number of IT systems available to local authority social services for recording and collating the extensive data required for the commissioning and management of social care services, submission of performance reports (for the adult and children’s services and as major components of local authority performance), and government inspections.
The system was first implemented in 2002 following the standard tendering and procurement process. The firm providing PARIS – In4Tek – was selected from a choice of a number of bids. No software met all of Sutton’s requirements.
The lessons learnt were: • There was insufficient recognition of additional costs, and the need for a permanent support team.
• There was insufficient recognition of the amount and costs of training needed.
• There was limited recognition of the impact of high turnover of project managers.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Scoping PaperReport | 89 KB | DownloadRead as text |
Follow Scrutiny Overview Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Nov 2011 | Welfare reform( i ) the Terms of Reference were agreed with no amendments (ii) the guests for the next meeting were confirmed (iii)... | Agreed | Open |
| 20 Sep 2011 | Complaints report 2010/11( i ) to thank Gill Bull for her input to the discussion. (ii) For further information as noted to be provided to the... | Noted | Open |
| 20 Sep 2011 | Date of next meetingto note that the next meeting of this committee would be held on Wednesday 5 October 2011. There will be a single iss... | Noted | Open |
| 7 Jun 2011 | Capacity of the Voluntary SectorIt was agreed that the report should be amended to include the need for benchmarking, Key Performance Indicators (KPI... | Agreed | Open |
| 7 Jun 2011 | Smarter Services Sutton Customer Services( i ) To thank Gill Bull and Janette Garlick for their input to the discussion. (ii) To agree the draft Terms of Refe... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.