( i ) To note the position of the projects identified for each ward and to agree the following: a) fund new fencing at Cuddington Park Local Nature Reserve in the sum of £8,000 from Public Realm 2010/11; b) match-fund contributions to street tree replacements made by residents associations in the area with public realm funding; c) a contribution of up £1,000 for new benches in Cheam Park from the 2010/11 allocation; (ii) That Ian Kershaw include the Section 106 funding available to this Committee in his letter to members, agreed under the preceding agenda item.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Sutton South, Cheam and Belmont Local Committee
Page 11 Agenda Item 8
Urgent item brought forward at the direction of the Chair so that the Committee’s public realm programme can be progressed without delay
Sutton South, Cheam and Belmont Local Committee 18 November 2010
Report of the Locality Lead Officer
Public Realm Projects update
Ward location: Sutton South, Cheam Report author: Ian Kershaw, Locality and Belmont Lead Officer. 020 8649 0684
Area Served: Cheam, Sutton South Lead Councillor: Ruth Dombey and Belmont
Summary This report sets out the latest position on public realm projects in the area and S106 funding for particular schemes.
Recommendations The Committee is asked to note:
Agree to fund new fencing at Cuddington Park Local Nature Reserve in the sum of £8,000 from Public Realm funding.
Agree to match fund contributions to street tree replacements made by residents associations in the area with public realm funding.
Agree any S106 fund contributions to substitute for public realm projects and adjust the available sums from Public Realm budgets as appropriate.
Note the position of the remaining projects identified for each ward and agree any revisions.
1. Background 1.1 The Committee on 30 September received an update on public realm projects. A separate report on the agenda gives details of S106 agreement funds that could be allocated to this Committee’s pubic realm projects.
2. Issues
2.1Belmont pastures Work will start by the end of November to re-profile the site to make the benches accessible for people with walking difficulties. The benches will be installed straight after, followed by reseeding the area. The Biiodversity Team and the Sutton Nature Conservation Volunteers will install the benches to keep costs down. These works are estimated at £5,300. In addition, the team will cut back some of the trees from
1 Agenda Item 8 Page 12
the street lighting. This will be done in January/ February at an estimated cost of £2,500. Estimates are also being sought to remove some of the railings to tidy the entrance, though spending money on a gate is not felt to be good value for money,
2.2Nonsuch Park A working group of officers and members from Sutton and Epsom met with representatives of the BMX club. The club is being formalised and the Nonsuch Park Joint Management Committee has been asked to endorse plans to formalise the “Jumps”. New fencing is expected to be needed and would be installed in the new year.
2.3The Lodge, Cheam Park Works to the interior of the building have been completed and steps are being taken to let the tenancy.
2.4Allotments Belmont and Cotswold Road allotments have been put forward for improvement under Community Payback.
2.5S106 funding S106 refers to funding made over to the Council to offset the impact of development. A separate report on this agenda gives details of S106 funding that is available to this Committee for specific reasons. The Committee may wish to allocate some of these funds (where possible) to existing public realm projects and offset or increase that expenditure. Possible areas are:
o £4,771 of 10,121 available toward Eaton Road parking (S106 re 8550). o £2,000 toward Belmont pastures improvements (S106 ref 8506) o £9,618 toward street tree replacement (S106 ref 8527)
3. Financial implications 3.1 The 2008/09 and 2009/10 Capital Estimates contain a total of £2m for the Public Realm project which has been allocated to the Local Committees on the basis of population.
3.2The South Sutton, Cheam and Belmont Local Committee have been allocated £314k from the Public Realm Project Fund for 2008/09 and 2009/10. There is a further allocation for 2010/11 of £118k (of which £16k relates to transport schemes) and £38k s106 funding was available for works in Cheam Park. Projects totalling £446k have already been agreed for period 2008/09 to 2010/11 leaving a balance of £24k for projects in 2010/11 (by Del 112/10) and further potential allocations of 95K (including transport related schemes of £16k) in 2011/12.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Sutton South, Cheam and Belmont Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingthat the minutes of the meeting held on 5 February 2026 be agreed as an accurate record. On behalf of the Committee, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.