Minutes of the Previous Meeting
Held on 2 November 2010
What the committee will consider, in order, with every paper attached to its item. Sutton in Partnership - Working Together is the main business.
Held on 2 November 2010
To consider the financial position at month 7
Decision: To note the current spending against the original estimates, and the issues arising and impacting on the 2010/11 budget. Decision page
To report the financial position at month 7
Decision: ( i ) To note the latest position on capital expenditure and resources; (ii) To note the intention to report less frequently in future, but a least four times a year; (iii) To amend capital estimates for 2010/11 and release financial provision for additional expenditure related to Contaminated Land Grant and Agresso Upgrade, as identified in paragraphs 2.6, 2.7 and 2.8 of the report. Decision page
To consider proposals to meet the further increase in demand for primary school places for September 2012 and beyond
To endorse the Sutton Partnership Agreement A colour copy of the Sutton Partnership map is being circulated to Executive members only. The document is viewable on the council’s website at www.sutton.gov.uk
Decision: ( i ) To thank [name removed] for attending and for his comments on the report; (ii) To approve the “Sutton in Partnership” document, now submitted. Decision page
To report the outcome of the consultation and consider policy recommendations
Decision: To note the outcome of the consultation on the proposed changes to the charging policy for Adult Social Services and agree: ( i ) the new contributions policy now submitted be implemented with effect from 1 January 2011; (ii) contributions be assessed against the full value (100%) of a service user’s personal budget, as described in paragraph 3.3 of the report: (iii) charges against the personal budget be based on the actual costs of services used (paragraph 3.4 of the report); (iv)... Decision page
Confirmation of statutory duties under the Flood & Water Management Act 2010 and Sutton’s response
Decision: ( i ) To note the statutory duties and powers implemented under the Flood & Water Management Act 2010; (ii) To note the progress on local action to reduce flood risk and that Sutton’s interim Surface Water Management Plan is being used as an exemplar for other boroughs to use; (iii) To agree that a detailed report be presented when the Surface Water Management Plan is in final draft form, including proposals for public consultation; (iv) To agree that a further report be presented on use of any... Decision page
Report on the impact of the government cancelling the waste PFI credits and the South London Waste Partnership’s proposed response
Decision: To agree to continue to support the South London Waste Partnership’s procurement process to achieve the best financial and environmental solution for the management of waste for the sub-region. Decision page
To agree to make a CPO for the land required for the construction of the access road for the new Stanley Park High School A colour plan is being circulated to Executive Members only. The document is viewable on the council’s website at www.sutton.gov.uk
Decision: ( i ) To make The London Borough of Sutton (Orchard Hill Woodmansterne Road Access Land) Compulsory Purchase Order 2010 (the “2010 Order”) under s226 (1)(a) of the Town and Country Planning Act 1990 and section 13 of the Local Government (Miscellaneous ... view the full minutes text for item 942. Decision page
To agree new letting arrangements for Community Associations that manage community centres
Decision: To agree: ( i ) the continuation of current policy to charge market rents for use of buildings, but to adopt a circular grant funding method for the charging and payment of rent demands for rack-rented community centres; (ii) that, in return for this funding arrangement, community associations become responsible for all repairs and maintenance of the community centres up to a value of £50k, to be reviewed initially after 2 years and, thereafter, every 5 years; (iii) that arrangements for... Decision page
To recommend the Council Tax Base for 2001/12 to full Council for approval
An update on the One Planet Action Plan and the next steps
Decision: Resolved : ( i ) To congratulate the Executive Head of Environmental Sustainability and his team on recently being awarded ‘Best Public Sector Organisation for Environmental Innovation’ by the Environment Agency; (ii) To note the key achievements under both One Planet Living and the Eco Management and Audit Scheme and the extent to which these initiatives contributed to the Green Flag award in 2010; (iii) To note the external resources that have been secured to deliver environmental... Decision page
Decision: To approve: ( i ) the mechanism now submitted by which interest rates are fixed for discretionary and mandatory loans to enable Sutton Housing Partnership to enter into deferred payment agreements with Sutton leaseholders who have incurred charges for major works; (ii) the revised minimum value of £5k for loans that are for a term of 3 to 10 years; (iii) the payment plan options for non-resident leaseholders, as set out in section 3 of the report to the 7 October 2010 meeting of the Housing... Decision page
Item 938 is where most of this meeting's papers sit: 3 papers, about 469 KB.
To endorse the Sutton Partnership Agreement A colour copy of the Sutton Partnership map is being circulated to Executive members only. The document is viewable on the council’s website at www.sutton.gov.uk
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 29 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 2 November 2010. 6 of its items lead into this meeting; 8 items are new. Point at any item to follow a thread. Procedural items are left out.
Business and Financial Planning 2011/12 to 2014/15, Regeneration of Elizabeth House Sheltered Housing Scheme- Outcome of Tender Process for Design, Building & Management, Sutton Life Centre Business & Operations Plan (2010/11), Promoting Customer Self-Service and 4 more do not return this time.
See the 2 November meetingEvery The Executive meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Sutton, The Executive
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the The Executive, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.