Reducing Flood Risk

Approved Executive 6 papers

The Executive approved this item on Monday 6 June 2011. Below is the council's own wording, with the papers it was decided on.

Item528

Resolved

(i) That The Preliminary Flood Risk Assessment document be adopted; (ii) That the Flood & Water Management Act 2010 and associated regulations be added to the scheme of delegations for the Strategic Director of Environment & Leisure and Executive Heads within the Environment and Leisure Group; (iii) That a sum of £75,000 be allocated from available grant funding towards the Environment Agency scheme, supported by the North Cheam and Worcester Park Local Committee, to reduce flood risk from the Beverley Brook; (iv) That the current joint working across South West London Boroughs on flood prevention be noted and that the benefits of further formal joint working arrangements including the boroughs of Merton and Wandsworth as far as the River Wandle was concerned and a further report be submitted in the autumn; (v) To thank Chris Reid and his team and their colleagues at the Environment Agency for all their hard work in connection with this matter.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to The Executive

Summary

This report seeks the approval of Sutton’s Preliminary Flood Risk Assessment (PFRA) required under EU directive and implemented in the UK by the Flood Risk Regulations 2009. The PFRA has been prepared through the GLA/London Council’s Drain London programme. It is an overview document to be submitted to the Department for Environment and Rural Affairs to demonstrate that the local authority has preliminary information on flood issues.

Within the UK there has been significant progress in tackling flood issues following the Pitt Review in 2007/8. UK authorities are therefore, in addition, preparing more detailed Surface Water Management Plans as part of flood risk management. This report also summarises the main statutory requirements for local authorities as Lead Local Flood Authorities and recommends that the Flood & Water Management Act 2010 and associated regulations are added to the delegated powers of the Strategic Director of Environment & Leisure and Executive Heads within that Group.

Funds to assist in carrying out the new responsibilities have been awarded for both this and the next financial year. It is recommended that £75k from this funding be allocated to the Beverley Brook scheme as match funding to the contribution agreed by the by the Local Area Committee on 19th May. This will enable a £1,709m scheme to reduce flood risk to 90 Sutton properties severely affected by flooding in 2007. The major funding will come from the Thames Area Regional Flood Defence Committee budget.

Work already completed under a pilot project to protect 43 properties from flood risk, funded by the Environment Agency, is summarised at appendix A.

Finally, the report gives an update on proposals for joint working across South West London, building on the excellent work prompted by the Greater London Authority/London Councils through the Drain London Project. Detailed proposals for joint working will be submitted in the autumn.

1 Agenda Item 6 Page 16

Recommendations

It is recommended that

(a) The Preliminary Flood Risk Assessment be adopted; (b) The Flood & Water Management Act 2010 and associated regulations be added to the scheme of delegations for the Strategic Director of Environment & Leisure and Executive Heads within the Environment and Leisure Group; (c ) A sum of £75,000 is allocated from available grant funding towards the Environment Agency scheme, supported by the North Cheam and Worcester Park Local Committee, to reduce flood risk from the Beverley Brook; (d) The joint working across South West London Boroughs be noted, including the intention to explore the benefits of formal joint working arrangements and report bac in the autumn.

Background

An update on activity in Sutton to reduce flood risk through Sutton’s Flood Group and duties under the Flood & Water Management Act 2010 was presented at The Executive meeting on 30th November 2010. The new statutory duties on local authorities to manage flood risk are largely based on EU requirements and the findings of the Pitt Review following the major flood events for 2007. It is recommended that The Flood & Water Management Act 2010 and associated regulations be added to the scheme of delegations for the Strategic Director of Environment & Leisure and Executive Heads within the Environment and Leisure Group.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Flood Resistance and Resilience Scheme 040511 App AAppendix 49 KB Download
PDF
Flood Risk Management: Preliminary Flood Risk Assessment: Final 27 May 2011Report 73 KB DownloadRead as text
PDF
Flood Risk PIRA reportn DLT2-GP8-PFRA-Sutton-Report-V05Report 866 KB Download
PDF
PIRA 1 DLT2-GP8-PFRA-Sutton-Annex1-3_V02Appendix 56 KB Download
PDF
PIRA 2 DLT2-GP8-PFRA-Sutton-Annex1-3_V02Appendix 59 KB Download
PDF
PIRA 3 DLT2-GP8-PFRA-Sutton-Annex1-3_V02Appendix 74 KB Download

At this meeting

Whole meeting

Who was there

9 of 12 attended
JP
Julia PenfoundCouncil Staff, expected
SB
Councillor Sean BrennanChair, present
RD
Councillor Ruth DombeyVice-Chair, present
DC
Councillor Dave CallaghanExecutive Councillor, present
JD
Councillor John DrageExecutive Councillor, present
CH
Councillor Colin HallExecutive Councillor, present
KJ
Councillor Kirsty JeromeExecutive Councillor, present
JM
Councillor Jayne McCoyExecutive Councillor, present
CS
Councillor Colin StearsExecutive Councillor, present
GT
Councillor Graham TopeExecutive Councillor, apologies
SW
Councillor Simon WalesExecutive Councillor, present
RS
Richard ShortmanSecretary, expected

On this subject at Sutton

Search all
  1. Reducing Flood RiskThis decision
  2. Reducing Flood Risk in Sutton - Update on the activities of the Sutton Flood Group and Implications of the Flood and Water Management Act 2010Noted

More from Sutton The Executive

All decisions
MeetingDecisionOutcome
8 May 2012 Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... Noted Open
8 May 2012 Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... Agreed Open
8 May 2012 Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... Approved Open
8 May 2012 Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. Approved Open
8 May 2012 Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... Agreed Open