( i ) To note the update on agreed schemes for 2010/11; (ii) That the public realm schemes for 2011/12 be progressed as per the report, the minor corrections and need for further discussions being noted; (iii) That the proposed funding of transport schemes for 2011/12 be agreed as set out above.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
a) To note the update on agreed schemes for 2010/11.
b) To agree which schemes to progress for 2011/12.
Background
1.1Public Realm is defined to include shared, open civic spaces not including highway improvements. It does not include any areas inside buildings that would be considered to be public space.
1.2The local Committee has been allocated at total of £329,103 of Public Realm funding to invest in area improvements for 2008-10. Seven improvement projects valued at approximately £330,000 were completed by the end of March 2010.
1 Agenda Item 7 Page 2 1.3 The committee had a further £122,892 to allocate for 2010/11 to public realm projects, including transport related schemes (£16,505). It was agreed on March 18th at the Local Committee to split this equally between the 3 wards. 1.4 For 2011/12 this local committee has been allocated £41,263 for Public Realm schemes and £16,505 for Transport schemes. In addition this allocation it was agreed at the May committee pool the unspent funds form 2010/11 of £17,987 and the £6,000 set aside for Collingwood Rec, giving an over all total of £65,250. It was agreed that this sum would be split in the following way:
Each ward receives £8,000, totalling 24,000 Larger schemes across the locality allocated 41,250 Total £65,250
2 Issues
2.1The status of the agreed Public Realm schemes for 2010/11 can be found in Appendix 1 of this report. The entire £16,505 allocated for transport schemes was released in August 2010, the current schemes agreed can be found at Appendix 2 of this report.
2.2The scheme for Chaucer Estate was revised and the cost will now be in the region of £10,000 instead of the previously allocated £20,000. The balance of £10,000 has been rolled over to 2011/12 and can be utilised for other schemes on the Chaucer Estate. Further ideas are required with in Chaucer Estate for the utilisation of this funding.
2.3A number of schemes have already been identified for Public Realm (Appendix 3) and Transport Schemes (Appendix 4) and have been reviewed and subsequently prices by the appropriate sections. In order to progress these schemes the committee is required to agree schemes that should be implemented.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.