Beddington and Wallington Local Committee noted this item on Tuesday 11 October 2011. Below is the council's own wording, with the papers it was decided on.
( i ) That the public realm spending up to October 2011, the potential projects for 2011/12 and the feedback on the progress made to date on the outstanding public realm and TfL funded projects, be confirmed. (ii) Unanimously to not spend up to £1,000 on getting a quote for the redevelopment of the dried pond next to Manor’s Cottage, Wallington North, to be funded from revenue, but instead plant a tree in its place with associated drainage. (iii) Unanimously to fund the completion of Beddington Park cycle path which would be funded from public realm resources for which only option 3 was affordable within the balance remaining in 2011/12, subject to legal implications. (iv) Unanimously to release an additional £300 required to remove the old Beddington Notice Board and replace it with a new board. (v) Unanimously to release £689 plus VAT to fund the anti vandal bench and pot at the Sensory Gardens, Wallington and £699 extra funding needed for the wheels and ramps. (vi) To note the progress on current public realm projects. (vii) To note to add The Meads and Onslow Gardens yellow lines to Peter Ashley’s list and that Julie Young obtain a breakdown of costs. (viii) That an update on the heritage plaques be provided at the next meeting. (iv) That an update on the Festoon lights be sent to Councillor Hall before the next meeting. (x) To investigate Wallington Public Hall for public realm funding, in particular the kitchens and frontage.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Beddington and Wallington Local Committee
Summary
This report confirms:
i) The public realm spending up to October 2011 ii) Potential projects for 2011/12 iii) Feedback on the progress made to date on the outstanding public realm and TfL funded projects
I recommend that the Committee consider the report and;
i) Agree whether to spend up to £1,000 on getting a quote for the redevelopment of the dried pond next to Manor’s Cottage, Wallington North, to be funded from revenue. ii) Agree whether to fund the completion of Beddington Park cycle path which would be funded from public realm resources for which only option 3 is affordable within the balance remaining in 2011/12. iii) Agree to release an additional £300 required to remove the old Beddington Notice Board and replace it with a new board iv) Note progress on current public realm projects.
Background
1.1The public realm funding for 2011/12 stands at £55,544, and an unallocated sum of £31,742 remained from 2010/11 which slipped to 2011/12 by Del 18/11 providing a total allocation of £87,286. This is supplemented by transport related funding of £22,218 (plus £3,691 under spend from 2010/11).
1.2Of the funds available for public realm in 2011/12 a sum of £24,000 has been released for the enhancements to the wheels and ramps at Roundshaw park, £5,800 has been released for outdoor gym equipment at both Beddington Park and Roundshaw Park, £1,500 to replace damaged fencing on Wallington Green, £900 for a new Beddington notice board, £1,000 for a new signpost for Wallington Green, £1,000 for a plaque to commemorate Gary Mason, £3,000 to replace litter bins on Manor Road and £3,225 for two additional benches and five additional bins at Beddington Park. A further £25,000 has been set aside for the staging area at the Old Town Hall in Wallington. £30,000 has been returned from the EcoLocal bike project. This leaves £46,061 unallocated funding. Agenda Item 11 Page 18
1.3With regard to the available transport related funding, £3,691 will be spent on further consultation around Butter Hill, £13,909 will fund outstanding yellow line schemes across the committee area and £5,000 will fund improvements to the existing cycle lane at Boundary Road / Park Lane. This leaves £3,309 of funding currently unallocated.
1.4The public realm money is supplemented by £10,000 revenue funding for 2011/12 which can be spent on the ongoing maintenance and repair of public realm projects. £3,500 has been released for maintenance of the wheels and ramps at Roundshaw Park and £1,508 for maintenance of outdoor gym equipment in Beddington and Roundshaw Parks. The leaves £4,992 unallocated revenue funding.
2. Potential projects for 2011/12 funding
Public Realm 2.1 Dried pond next to Manor’s Cottage – a request was submitted to either reline or redevelop the pond. The Parks Service has advised it will cost money (anticipated up to £1,000 maximum revenue funding) to get a quote if the Committee wishes to progress with it. A final design to reline the pond and get it back into circulation could cost upwards of £20k.
2.2Completion of Beddington Park cycle lane – there are three options to consider, presented below and with drawings in Appendix A, B and C. As this would be funded from public realm, only option iii. is possible with the balance available in 2011/12:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Beddington and Wallington Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.