Resolved
That the Carbon Management Plan be adopted subject to potential future projects identified in the plan being tested for policy and business viability and specifically approved for implementation.
The Executive approved this item on Monday 26 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Carbon Management Plan be adopted subject to potential future projects identified in the plan being tested for policy and business viability and specifically approved for implementation.
Page 1 Agenda Item 6
Working with
London Borough of Sutton Carbon Management Plan: Plan 2012-2017
Sutton Life Centre (BREAM “Excellent” Building) Agenda Item 6 Page 2 Working with
Contents Foreword from Councillor Colin Hall – Executive Member for Environment and Climate Change .......... 3
Foreword from the Carbon Trust ..................................................................................................................... 4
Executive Summary........................................................................................................................................... 5
1 Introduction................................................................................................................................................. 8 1.1 Our low carbon vision and target ............................................................................................................................................... 8 1.2 Our drivers and priorities for reducing our carbon emissions ..................................................................................................... 8 1.3 The context for our Carbon Management Programme............................................................................................................. 10
2 Emissions baseline and projections ...................................................................................................... 11 2.1 Scope ..................................................................................................................................................................................... 11 2.2 Baseline .................................................................................................................................................................................. 11 2.3 Projections and Value at Stake ............................................................................................................................................... 13 2.4 Display Energy Certificates ..................................................................................................................................................... 14
3 Carbon Management Projects ................................................................................................................. 16 3.1 Existing projects ...................................................................................................................................................................... 18 3.2 Planned / funded projects........................................................................................................................................................ 19 3.3 Planned projects requiring funding .......................................................................................................................................... 20 3.4 Potential future projects .......................................................................................................................................................... 20 3.5 Projected achievement towards target .................................................................................................................................... 22
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Carbon Management Plan_final_v1_cleanReport | 5.1 MB | DownloadRead as text |
PDF |
Carbon Report for Executive_29 March_finalReport | 105 KB | Download |
Follow The Executive at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 May 2012 | Advocacy Commissioning(i) To note the contents of the report and progress made to date in reviewing and realigning advocacy services to mee... | Noted | Open |
| 8 May 2012 | Domestic Violence - Strategic Options(i) That the proposals set out in paragraphs 4 to 6 in the report be endorsed; (ii) To agree to forward the report to... | Agreed | Open |
| 8 May 2012 | Review of Housing Allocations Policy and Development of a Tenancy Strategy( i ) That the draft revised housing allocations policy, as set out in Appendix 1 to the report, be approved and adop... | Approved | Open |
| 8 May 2012 | Sutton Housing Partnership Delivery Plan 2012/13To approve the Sutton Housing Partnership Delivery Plan for 2012/13. | Approved | Open |
| 8 May 2012 | Epsom and Ewell Borough Council Insurance Arrangements(i) To agree to the principle of the provision of insurance services to Epsom and Ewell Borough Council and to author... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.