Environment and Neighbourhood Committee noted this item on Thursday 14 June 2012. Below is the council's own wording, with the papers it was decided on.
( i ) To note the list of reserve schemes in Appendix A to the report. (ii) To agree the proposed process for prioritising substitute schemes should it become necessary to make a variation to the transport programme. (iii) That, subject to the views of the Chair of the relevant Local Committee, to delegate authority to the Executive Head of Planning and Transportation, in consultation with the Chair of the Environment and Neighbourhood Committee to make variations to the Local Implementation Plan transport programme. (iv) To delegate authority to the Executive Head of Planning and Transportation to make adjustments to allocations with Transport for London’s agreement to meet scheme budgets. (v) To receive an annual report setting out progress on the Local Implementation Plan Programme.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to: Environment and Neighbourhood Committee
Date: 14 June 2012
Report of: The Executive Head of Planning and Transportation
Ward Location: Not Applicable Author(s) and Contact Phone Number(s): Paul Blunt Tel: 0208 770 6445
Area Served: Borough Wide Chair of the Committee: Jill Whitehead
Report title: VARIATIONS TO THE LOCAL IMPLEMENTATION PLAN
Summary This report outlines the method of choosing a substitute transport scheme should a scheme in the current years Local Implementation Plan (LIP) transport programme be abandoned for whatever reason. A scheme could be abandoned for a number of reasons including, rejection by the local committee, as a result of the consultation process or because of insufficient funds for its implementation. The process for selecting substitute schemes is described in the report and the current reserve list of schemes is attached in Appendix A (This includes reserve schemes reported previously to The Executive, unfunded schemes and schemes recently suggested by Councillors). Agenda Item 7 Page 42
Recommendations I recommend the Committee to: a) Note the list of reserve schemes in Appendix A. b) Agree the proposed process for prioritising substitute schemes should it become necessary to make a variation to the transport programme. c) Subject to the views of the Chair of the relevant Local Committee, delegate authority to the Executive Head of Planning and Transportation, in consultation with the Chair of the Environment and Neighbourhoods Committee to make variations to the Local Implementation Plan transport programme. d) Delegate authority to the Executive Head of Planning and Transportation to make adjustments to allocations with TfL’s agreement to meet scheme budgets. e) A report be submitted annually to the Committee setting out progress on the LIP Programme.
Background Documents and Previous Decisions
Signed:
Peter O’Connell Acting Strategic Director
Date: 1 June 2012
1. Background 1.1 Each year the Council submits its programme of transport proposals for the following financial year to Transport for London (TfL) for approval and an allocation of funding. The submission and list of schemes is approved by the relevant Committee. In recent years this has been The Executive.
1.2Local Committee approval is obtained as necessary to implement schemes in a particular Local Committee area.
1.3During the course of the year it has become common practice for officers to make minor alterations to the programme and allocations in order to ensure full Page 43 Agenda Item 7
spend of the funding provided by TfL. TfL have a process for requesting these alterations and all changes have to be agreed by them.
1.4A scheme may not be implemented for various reasons. Often this is a result of public consultation. Rather than return the unused funding to TfL, officers look at alternative ways to use the surplus funding which could, for example, be to extend the scope of another scheme in the programme.
1.5The Council maintains a reserve list of schemes amounting in value to 20% of the current Corridors and Neighbourhoods programme as requested by TfL. There is a further list of unfunded schemes that could not be included in the reserve list as it would take the value beyond the 20%. These two lists were reported to the Executive in September 2011. There are various other lists that have been produced of potential schemes for future bids, such as Appendix B to the Sutton Transport Plan 2011-31.
1.6This report supports Sutton’s plan to be a ‘One Planet Borough’ – living with itss fair share of the Earth’s resources. The schemes proposed in the appendix will encourage more sustainable travel.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.