Resolved
That planning permission be granted for application No. C2012/66328/3FR, subject to the conditions, reasons and informatives set out in the Appendix to these Minutes.
Development Control Committee decided this item on Wednesday 19 September 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That planning permission be granted for application No. C2012/66328/3FR, subject to the conditions, reasons and informatives set out in the Appendix to these Minutes.
1.1Site and surroundings:
1.2The application site comprises a two storey mid terrace single family dwelling house faced in yellow brick with reddish brown tiled pitched roof, located on the south western side of Quarr Road. The house had an existing single storey rear extension, comprising a bathroom and WC, which would be replaced by the proposed extension.
1.3The site is located in the St Helier Estate, which is characterised by inter-war two storey terraced housing, mostly faced in either red brick, brown or yellow brick, although some have been faced in painted timber or pebble dashed.
1.4Site specific LDF designation:
x St Helier Area of Special Local Character
1.5Relevant Planning History:
1.6None relevant.
2.0APPLICATION PROPOSALS Agenda Item 25 Page 150
2.1Background to Proposals:
2.2Timber box bathrooms were installed during the 1960s’ to terraced and semi- detached houses built during the 1930s’ in order to provide a separate bathroom. Those existing pod units installed in the 1960s’ are now far beyond their economic life. Typical problems relate to moisture ingress such as decayed timber elements, leaking roofs and structural distortions. Between 2004 and 2007 some 200 of these units were replaced with a larger 4m deep pre-fabricated pod incorporating a bathroom and utility room. However, this type of pod had disadvantages as it took 3 or 4 days to install, as it involves assembly of pre-fabricated parts within the rear gardens once the existing pod had been removed. Also, at the time because the pods were permitted development and built in pre-cast ‘pebbledash’ style panels they did not harmonise with the brick built houses.
2.3The current retrospective application, submitted by Sutton Housing Partnership forms part of the Council’s decent homes programme which affects 750 dwellings across St Helier and aims to replace all remaining box bathrooms over the next 5 years. The benefit of the new box bathrooms are that they improve access for disabled users, having wider doors, provide more room for users (including a utility room), are faced in external materials that better match the existing house and can be installed more quickly as they are craned into position fully assembled. The removal of the existing pod and the provision of the replacement bathroom takes around 3-5 hours. The new pod bathrooms are installed in the same position as the existing units, although they are about 0.6m deeper and 0.25m higher. The design and layout of the new bathrooms was drawn up with the residents and local Councillors.
2.4Details of Proposal:
2.5Planning permission is sought to erect a single storey rear extension comprising a bathroom and utility room. The extension would have a depth of 3.98m, a width of 2.1m and a height of 2.9m. It would be faced with yellow Noverbrick external cladding hung tile, have a flat black membrane finish roof and have a semi glazed door and obscure glazed window on its north western side.
2.6Significant amendments to application since submitted:
2.7None.
3.0PUBLICITY
3.1Adjoining Occupiers Notified
3.2Method of Notification:
3.3Letters were sent to two adjoining occupiers in Quarr Road on 24 August 2012.
3.4Number of Letters Received: None. Page 151 Agenda Item 25
3.5Official Consultation:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
24: 20 Quarr Road: REPORTReport | 47 KB | DownloadRead as text |
Follow Development Control Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2014 | Election of chairThat Councillor Hamish Pollock be elected Chair of the Committee for the duration of the meeting. | Decided | Open |
| 23 Apr 2014 | Felnex trading estate, 190 london road, hackbridge - application no. c2014/68760/fulThat planning permission be granted for application No. C2014/68760/FUL, subject to (a) the written conclusion of a ‘... | Agreed | Open |
| 23 Apr 2014 | Tauranga, the wood end, wallington - application no. d2014/68776/hhaThat planning permission be granted for application No. D2014/68776/HHA, subject to the conditions, reasons and infor... | Decided | Open |
| 23 Apr 2014 | Thomas wall park pavilion, green lane, morden - application no. c2014/69143/nmaThat planning permission be granted for application No. C2014/69143/NMA, subject to the conditions, reasons and infor... | Decided | Open |
| 23 Apr 2014 | Land at margaret's pool, corner of pound street and west street, carshalton - application no. c2014/68989/advThat planning permission be granted for application No. C2014/68989/ADV, subject to the conditions, reasons and infor... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.