CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Sutton

Mayor's Big Green Fund Bid

Agreed Committee 2 papers

St. Helier, The Wrythe and Wandle Valley Local Committee agreed this item on Thursday 25 April 2013. Below is the council's own wording, with the papers it was decided on.

Item421

Resolved

( i ) To support in principle the Big Green Fund project proposals (ii) To provide feedback, as appropriate, on the London Borough of Sutton becoming the accountable body for the Big Green Fund project should the bid to the Mayor be successful. (iii) To agree in principle to provide £20,000 public realm funding, subject to change, towards the Big Green Fund project, should the bid to the Mayor be successful and should some funding be secured from the London Borough of Merton
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to St. Helier, The Wrythe and Wandle Valley Local Committee

Summary

The Mayor’s Big Green Fund has the potential to bring significant investment, approximately £450,000, to Sutton’s green infrastructure should the Wandle Valley bid be successful. The capital works need to be delivered over a period of 18 months, by March 2015, resulting in positive outcomes relating to biodiversity, access to green space, physical activity, community cohesion and skills development.

It is recommended that the Committee:-

1. support in principle the Big Green Fund project proposals that will bring significant capital investment to green infrastructure in Sutton, and as well as facilitate community engagement, physical activity and skills development; 2. provide feedback, as appropriate, on the London Borough of Sutton becoming accountable body for the Big Green Fund project should the bid to the Mayor be successful; 3. agree in principle to provide £20,000 public realm funding towards the Big Green Fund project, should the bid to the Mayor be successful.

1. Purpose:

The purpose of this report is to brief the Committee on the bid to the Mayor’s Big Green Fund covering green infrastructure in Sutton and Merton, and seek their in principle support for the project.

Background

2.1Wandle Valley Regional Park Trust:

Following completion of a Governance Study led by Sutton in April 2011, the Wandle partners established the Wandle Valley Regional Park Trust to deliver a regional park over the next decade - in line with adopted policy in the London Plan and Borough Core Strategies/Local Plans. The mission for the Trust is ‘to provide leadership, coordination, innovation and resources – working towards the ultimate aim of benefiting from the repatriation of the Lee Valley Regional Park precept to the London Boroughs - to enable the longer-term vision of a high quality, multi functional and attractive regional park to be achieved’.

The Trust was constituted as a Limited Company in July 2012 and is now negotiating with the Charity Commission regarding its application for charitable status. The Trust’s Board comprises 16 directors (and future Trustees), with nominations from 11 different organisations that are the Members of the company – with Jayne McCoy and Graham Tope the directors nominated by Sutton (see Appendix 1). The Regional Park Board meets in public on a quarterly basis.

1 Agenda Item 8 Page 46

2.2The Mayor’s Big Green Fund:

The All London Green Grid (ALGG) is the Green Infrastructure Strategy for London that was adopted as Supplementary Planning Guidance by the Mayor in March 2012. On 10th December 2012, GLA announced the launch of the Mayor's Big Green Fund (BGF) at an ALGG event at City Hall. This fund will provide grants of up to £500,000 — from a total fund of £2 million — to support the delivery of up to eight Big Green projects across London by March 2015. The fund aims to bolster the delivery of the ALGG Area Frameworks by providing funding to deliver projects already identified as priorities - including Area Framework 8 covering the Wandle Valley that the Wandle partners adopted in 2011.

GLA has stated that applications should come from ALGG Area Groups, or similar strategic partnerships operating within the framework areas - so in the case of Area Framework 8 the process needed to be led by the Regional Park Board. The GLA asked that the applications should result from a collaborative approach to select the best Area Framework projects that meet the fund criteria, with all applications to be received by noon on 1st March 2013 (the deadline was subsequently put back to 15th March). A maximum of two bids could be made per partnership, but it was made clear that only one project from an area stood a chance of being approved.

3. Proposals:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
StHelierTheWrythe&WandleValleyLC_BGFproposal_vfinal_25.04.13Report 104 KB DownloadRead as text
PDF
Wandle Valley_BGFbid_LBSLocalCommittee_appendix2projectarea_25.04.13[1]Appendix 11 MB Download

At this meeting

Whole meeting

Who was there

10 of 11 attended
SA
Councillor Sheila AndrewsCommittee Member, present
AC
Councillor Anisha CallaghanChair, present
DC
Councillor Dave CallaghanCommittee Member, present
MC
Councillor Margaret CourtCommittee Member, present
JD
Councillor John DrageCommittee Member, present
PK
Councillor Paddy KaneCommittee Member, present
PM
Patrick MurphyNon-elected, non-voting, absent
CS
Councillor Colin StearsVice-Chair, present
SS
Councillor Sue StearsCommittee Member, present
TT
Tamary TabeniSecretary, present
RT
Councillor Roger ThistleCommittee Member, present

More from Sutton St. Helier, The Wrythe and Wandle Valley Local Committee

All decisions
MeetingDecisionOutcome
16 Mar 2022 Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 13 January 2022 be agreed as an accurate record. Agreed Open
13 Jan 2022 Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 21 October 2021 be agreed as an accurate record. Agreed Open
13 Jan 2022 Petition Regarding Measures to Reduce Antisocial Behaviour in the Rose Hill AreaTo note the petition. 2. To agree that Sutton Council’s Community Safety Team will review CCTV coverage in the area a... Noted Open
21 Oct 2021 Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 17 June 2021 be agreed as an accurate record. Agreed Open
21 Oct 2021 Community Investment ProgrammeIt was agreed that an update on outcomes would be provided at a future meeting of the committee. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies