Resolved : i ) To note progress made on current Public Realm schemes ii) To note the current financial position of Public Realm schemes iii) To increase the unallocated balance by £11,396 from the net under spend indentified under Appendix B iv) To allocate an additional £2,000 of Public Realm Capital expenditure from 2013/14 for musical instrument and trampoline at Cheam Park v) To allocate £70,000 of Public realm Capital expenditure, 2013/14 towards play equipment at Overton Park
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Sutton South, Cheam and Belmont Local Committee
Summary
This report sets out information on the following three areas: The current progress on Public Realm schemes The financial position of the CRPPLWWHH¶VPublic Realm schemes The options for future work, subject to the consideration and agreement of the allocation of funding Agenda Item 10 Page 40
Recommendations
It is recommended that the South Sutton, Cheam and Belmont Local Committee: 1. Agree to note progress made on current Public Realm schemes 2. Agree to note the current financial position of Public Realm schemes 3. Agree to increase the unallocated balance by £11,396 from the net under spend indentified under Appendix B
Signed: Mary Morrissey Strategic Director of Environment and Neighbourhoods
Date: 26 September 2013 Page 41 Agenda Item 10
Background
1.1Since 2008, this Committee has been allocated Public Realm funding to invest in area improvements and from 2010 has also had an allocation for transport related schemes. Appendix A lists the current Public Realm schemes for this Committee and the progress to date and Appendix B shows the completed Public Realm schemes in this period. There are currently no unfunded schemes.
2. Progress and issues with agreed schemes (see Appendix A)
2.1A number of schemes have progressed since May 2013. In particular;
Nonsuch and Cheam Park Track
2.2This Committee awarded an amount of £1,700 towards the cost of laying a new path between Cheam Park and Nonsuch Park. The Nonsuch Park Joint Management Committee supported the proposal and agreed to joint fund the project. The project was due to commence over the summer but was delayed due to concerns from Nonsuch Watch about the bird nesting season. However, the equipment has now arrived on site and it is estimated that work will be completed by the time of this committee. A verbal update will be provided at this meeting.
Cheam Park Wheel Chair Swing
2.3On the 5 July 2012, this Local Committee agreed to allocate £2,000 towards the cost of a wheelchair swing in Cheam Recreation Ground to assist with community fundraising by Cheam Park Farm Junior School and the local community toward the £11,000 target. 2.4 The wheelchair swing scheme was initially proposed to the committee as a suitable inclusive and accessible item of play equipment for wheelchair users of all abilities, to be installed at Cheam Recreation Ground playground. 2.5 Since then there have been a number of site visits and discussions between Council Officers, local Ward Councillors and with a local family of a child who would benefit from the additional equipment. Council officers have also worked with a range of engineering and outdoor play equipment suppliers to determine the options available for this particular location. 2.6 Council officers¶ advice in the early stages was that the item is unsuitable in its earlier configuration as it was designed specifically for specialist supervised playgrounds. The manufacturers advised that due to the weight of the swing in motion, it was unsuitable for open access unsupervised play areas, as it could seriously injure a child running in front or behind it. Additionally, the wheelchair needs to be locked into place each time it is used and there is the issue of who would look after the keys in an unsupervised park playground. 2.7 Over the last year the wheelchair swing has been further developed by the manufacturers to address some of these concerns so it now offers an enclosed Agenda Item 10 Page 42
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Sutton South, Cheam and Belmont Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingthat the minutes of the meeting held on 5 February 2026 be agreed as an accurate record. On behalf of the Committee, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.