Beddington and Wallington Local Committee noted this item on Tuesday 1 October 2013. Below is the council's own wording, with the papers it was decided on.
Resolved : ( i ) To note the progress made on current Public Realm schemes; (ii) To note the current financial position of the Public Realm schemes; (iii) To agree to an “in principle” allocation of £2,000 from Public Realm funds for the design, production and installation of a heritage board for Croydon Airport and (iv) To reduce the unallocated balance by £1,779 from the net over spend identified under Appendix B.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Beddington and Wallington Local Committee
Page 75 Agenda Item 9
Report to: Beddington and Wallington Local Committee
Date: 1 October 2013
Report of: Strategic Director, Environment and Neighbourhoods Ward Location: Not Applicable Author(s) and Contact Phone Number(s): Roberta Fusco (4849) Locality Lead Officer Area Served: Beddington North Chair of the Committee: Beddington South Cllr Joyce Melican Wallington North Wallington South Report title: Progress Report: Area Improvements and Public Realm Schemes and Neighbourhood Grants
Summary This report contains information on the following three areas: - Public Realm spending up to September 2013 - Feedback on progress made to date on the outstanding public realm projects - Options for potential projects for consideration, subject to the consideration and agreement of the allocation of funding Recommendations It is recommended that the Committee consider the report and agree:
a) Agree to note the progress made on current Public Realm schemes
b) Agree to note the current financial position of the Public Realm schemes
c) $JUHHWRDQµLQSULQFLSOH¶DOORFDWLRQRI ,000 from Public Realm funds for the design, production and installation of a heritage board for Croydon Airport
d) Reduce the unallocated balance by £1,779 from the net over spend identified under Appendix B
Background Documents and Previous Decisions Minutes of the Local Committee meeting held on 25 June 2013 Agenda Item 9 Page 76
Signed:
_____________________________________ Strategic Director
Date: 20th September 2013-09-20
1. Background 1.1 In 2008 and subsequent years this Committee was allocated Public Realm funding to invest in area improvements. Since 2010, funding has also been received for transport related schemes. 1.2 Set out in this report is the following information: - Appendix A Public Realm schemes and progress to date
- Appendix B Current traffic and parking schemes and progress made to date
- Appendix C Completed Public Realm schemes
- Appendix D Unfunded public Realm schemes for future consideration
- Appendix E Notes of meeting of Councillors and Community Representatives held on 23 July 2013 to discuss security measures at Roundshaw Downs
2. Progress and Issues arising with agreed schemes (Appendix A)
2.1The Bandstand in Wallington Library Gardens ± The Local Committee originally approved to fund the installation of a bandstand in Wallington Library Gardens in January 2011. Planning permission was obtained in January 2013. The project will EHPDQDJHGE\WKH&RXQFLO¶V/LEUDU\DQG+HULWDJH6HUYLFH7KHWHQGHUSURFHVVZDV undertaken in July 2013 and a contractor has been appointed. Works are expected to commence in late Autumn. £25,000 has been allocated to this project by the Local Committee.
2.2The replacement Skate Ramp in Beddington Park ± It was agreed at the Local Committee meeting in December 2012 to replace the skate ramp in Beddington Page 77 Agenda Item 9
Park. After consultation with local schools, it was agreed in June 2013 to progress ZLWKSURFXUHPHQWDQGLQVWDOODWLRQRIDUHSODFHPHQW³KDOISLSH´UDPS,WZDVKRSHG that a new Borough wide skate facility contractor would be in place over the summer; however the process to appoint a Framework contractor is still ongoing. In the meantime, a tender exercise will need to be carried out. Officers in the Parks Service propose the following project timescales: w/c 16.09.13: Finalise Specification for supply and installation w/c 23.09.13: Publish Request for quotes w/c 14.10.13: Tenders evaluated w/c 21.10.13: Contract award Standard lead times for supply & installation is 8-12 weeks. Delivery and installation should take place w/c 13.01.14, dependant on weather conditions. This may slip considerably if there is exceptionally wet or snowy weather.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Beddington and Wallington Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.