LOCAL IMPLEMENTATION PLAN

Agreed Committee 2 papers

Cheam North and Worcester Park Local Committee agreed this item on Thursday 3 April 2014. Below is the council's own wording, with the papers it was decided on.

Item451

Resolved

Resolved : i ) To develop a three year ‘Local Transport funded’ rolling plan of schemes for the Committee area ii) To include the following schemes in the Highways, Transport and Smarter Travel delivery programme for 2014/15: o Cuddington Rec – new path for pedestrians and cyclists o Browning Avenue – traffic calming features review and implementation of speed reduction measures o Cycleway-North Cheam to Worcester Park – upgrade the existing footpath o Malden Road, Cheam – pelican crossing. [name removed] hoped that the agreed cycleway would not be subject to flooding and [name removed] undertook to see that was the case.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Cheam North and Worcester Park Local Committee

Page 13 Agenda Item 12

Report to: Cheam North and Worcester Park Local Committee 3 April 2014

Report of: The Executive Head of Commissioning

Ward Location: Author and Contact Phone Number: Not Applicable Brendon Hills 0208 770 6455 Area Served: Chair of the Committee: Cheam North and Worcester Park Adrian Davey

Report title: LOCAL IMPLEMENTATION PLAN FUNDING 2014/2015 TRANSPORT SETTLEMENT

Summary 7KHUHSRUWRXWOLQHV7UDQVSRUWIRU/RQGRQ¶V 7I/¶V DOORFDWLRQWRWKH&RXQFLOof Local Implementation Plan (LIP) funding for 2014/15 and how it will impact on the Cheam North and Worcester Park locality.

Recommendations a) Agree to develop a three year µ/RFDO 7UDQVSRUW)XQGHG¶rolling plan of schemes for the committee area.

b) Note that the schemes and measures detailed in this report will become part of the Highways, Transport and Smarter Travel delivery programme for 2014/15.

Background Documents and Previous Decisions LIP report to E&N 23/1/14

Signed:

Strategic Director Date: 6 March 2014 Agenda Item 12 Page 14

1. Background 1.1 6XWWRQ¶V7UDQVSRUW3ODQ(LIP) 2011 - 2031 has recently been updated to cover detailed transport proposals for the three financial years 2014/15 to 2016/17. This report advises this committee on how the LIP programme will impact the Cheam North and Worcester Park locality and explains how the Highways and Transport Service will engage in delivering schemes within the programme.

2. Funding Submission Consultation and Assessment Process 2.1 All Ward Councillors were invited to put forward schemes for inclusion in the 2014/15 spending submission. New proposals were selected following site visits and an initial assessment was undertaken to ensure the proposals were practicable, that they would meet WKH0D\RU¶V7UDQVSRUW6WUDWHJ\ goals and the borough¶s transport objectives, represent value for money and would be likely to be acceptable to the public.

3. 2014/15 LIP Submission 3.1 TfL announced the LIP funding allocations for London Boroughs on 16 December 2013 and the Environment and Neighbourhood Committee, as the Highways Authority, approved the programme of works for 2014/15 on 23 January 2014.

3.2The Council receives money from TfL for Corridor and Neighbourhood Measures and Principal Road Maintenance. Details of the Cheam North and Worcester Park schemes are listed in Appendix A. The London Borough of Sutton also receives, at a borough wide level, funding for Major Schemes and Cycling initiatives.

3.3Schemes that involve changes on the public highway will be referred to Local Committees as a part of the consultation process. Update reports will be provided on non-controversial schemes that do not involve changes on the public highway e.g. schemes in parks.

4. LIP Local Transport Funding 4.1 The Environment & Neighbourhood Committee has agreed to allocate TfL local transport funding of £16,889 per annum to the Cheam North and Worcester Park Local Committee.

4.2To improve forward planning the Committee is asked to commence preparing a three-year rolling programme of local transport funded schemes. It is proposed to undertake informal consultations with all Councillors in June 2014 with a view to bringing back a draft programme to the September Local Committee. Page 15 Agenda Item 12

5. Public Engagement, Quality Assurance and Programme Management Arrangements 5.1 Within the LIP programme TfL have allowed a limited budget for fees to pay for design work and consultation. Going forward a Gateway Project Management approach will be used to help assure quality and achieve value for money. The Gateway Process will allow members to systematically examine a project at critical stages in its lifecycle providing them with the assurance that it can progress successfully (in financial and technical terms, in particular) to the next stage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LIP Allocation Report to CNWP Local Committee 3 Apr 14 FINAL VERSIONReport 84 KB DownloadRead as text
PDF
LIP ref to all local ctteesReport 59 KB Download

At this meeting

Whole meeting

Who was there

14 of 18 attended
EA
Councillor Eric AllenCommittee Member, present
GA
Gerald AlmerothCouncil Staff, present
HB
Hugh ByrneNon-elected, non-voting, present
AD
Councillor Adrian DaveyChair, present
SD
Simon DensleyNon-elected, non-voting, present
NE
Councillor Nick EmmersonCommittee Member, apologies
SF
Councillor Stephen FenwickCommittee Member, apologies
MF
Michael FreterNon-elected, non-voting, present
SG
Councillor Stuart Gordon-BullockCommittee Member, present
KH
Ken HaagmanNon-elected, non-voting, present
MJ
Councillor Miguel JavelotCommittee Member, apologies
GJ
Councillor Gerry JeromeCommittee Member, present

All 18 on the meeting page

On this subject at Sutton

Search all
  1. LOCAL IMPLEMENTATION PLANThis decision
  2. Local Implementation Plan Allocation 20/21Noted
  3. Local Implementation Plan Schemes 2020/21Agreed
  4. 2020/21 Local Implementation Plan SchemesAgreed
  5. Local Implementation Plan (LIP)Agreed
  6. Local Implementation Plan (LIP)Agreed

More from Sutton Cheam North and Worcester Park Local Committee

All decisions
MeetingDecisionOutcome
30 Jun 2022 Minutes of the previous meetingthat the minutes of the meeting held on 27 January 2022 be agreed as an accurate record. Agreed Open
30 Jun 2022 Election of a Vice ChairRESOLVED 1. that Councillor Param Nandha be appointed as Vice Chair of the Cheam North and Worcester Park Local Commi... Decided Open
30 Jun 2022 Progress Report – Area Improvements and Public Realm ProgrammeRESOLVED that: 1. The report be noted. Noted Open
27 Jan 2022 Minutes of the previous meetingthat the minutes of the meeting held on 4 November 2021 be agreed as an accurate record. Agreed Open
27 Jan 2022 Public realm projects and neighbourhood grantsResolved that: 1. A sum of £1,277 for capital from the following schemes from closing 2020-21: Community Noticeboards... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies