Cheam North and Worcester Park Local Committee agreed this item on Thursday 3 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved : i ) To develop a three year ‘Local Transport funded’ rolling plan of schemes for the Committee area ii) To include the following schemes in the Highways, Transport and Smarter Travel delivery programme for 2014/15: o Cuddington Rec – new path for pedestrians and cyclists o Browning Avenue – traffic calming features review and implementation of speed reduction measures o Cycleway-North Cheam to Worcester Park – upgrade the existing footpath o Malden Road, Cheam – pelican crossing. [name removed] hoped that the agreed cycleway would not be subject to flooding and [name removed] undertook to see that was the case.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Cheam North and Worcester Park Local Committee
Page 13 Agenda Item 12
Report to: Cheam North and Worcester Park Local Committee 3 April 2014
Report of: The Executive Head of Commissioning
Ward Location: Author and Contact Phone Number: Not Applicable Brendon Hills 0208 770 6455 Area Served: Chair of the Committee: Cheam North and Worcester Park Adrian Davey
Report title: LOCAL IMPLEMENTATION PLAN FUNDING 2014/2015 TRANSPORT SETTLEMENT
Summary 7KHUHSRUWRXWOLQHV7UDQVSRUWIRU/RQGRQ¶V 7I/¶V DOORFDWLRQWRWKH&RXQFLOof Local Implementation Plan (LIP) funding for 2014/15 and how it will impact on the Cheam North and Worcester Park locality.
Recommendations a) Agree to develop a three year µ/RFDO 7UDQVSRUW)XQGHG¶rolling plan of schemes for the committee area.
b) Note that the schemes and measures detailed in this report will become part of the Highways, Transport and Smarter Travel delivery programme for 2014/15.
Background Documents and Previous Decisions LIP report to E&N 23/1/14
Signed:
Strategic Director Date: 6 March 2014 Agenda Item 12 Page 14
1. Background 1.1 6XWWRQ¶V7UDQVSRUW3ODQ(LIP) 2011 - 2031 has recently been updated to cover detailed transport proposals for the three financial years 2014/15 to 2016/17. This report advises this committee on how the LIP programme will impact the Cheam North and Worcester Park locality and explains how the Highways and Transport Service will engage in delivering schemes within the programme.
2. Funding Submission Consultation and Assessment Process 2.1 All Ward Councillors were invited to put forward schemes for inclusion in the 2014/15 spending submission. New proposals were selected following site visits and an initial assessment was undertaken to ensure the proposals were practicable, that they would meet WKH0D\RU¶V7UDQVSRUW6WUDWHJ\ goals and the borough¶s transport objectives, represent value for money and would be likely to be acceptable to the public.
3. 2014/15 LIP Submission 3.1 TfL announced the LIP funding allocations for London Boroughs on 16 December 2013 and the Environment and Neighbourhood Committee, as the Highways Authority, approved the programme of works for 2014/15 on 23 January 2014.
3.2The Council receives money from TfL for Corridor and Neighbourhood Measures and Principal Road Maintenance. Details of the Cheam North and Worcester Park schemes are listed in Appendix A. The London Borough of Sutton also receives, at a borough wide level, funding for Major Schemes and Cycling initiatives.
3.3Schemes that involve changes on the public highway will be referred to Local Committees as a part of the consultation process. Update reports will be provided on non-controversial schemes that do not involve changes on the public highway e.g. schemes in parks.
4. LIP Local Transport Funding 4.1 The Environment & Neighbourhood Committee has agreed to allocate TfL local transport funding of £16,889 per annum to the Cheam North and Worcester Park Local Committee.
4.2To improve forward planning the Committee is asked to commence preparing a three-year rolling programme of local transport funded schemes. It is proposed to undertake informal consultations with all Councillors in June 2014 with a view to bringing back a draft programme to the September Local Committee. Page 15 Agenda Item 12
5. Public Engagement, Quality Assurance and Programme Management Arrangements 5.1 Within the LIP programme TfL have allowed a limited budget for fees to pay for design work and consultation. Going forward a Gateway Project Management approach will be used to help assure quality and achieve value for money. The Gateway Process will allow members to systematically examine a project at critical stages in its lifecycle providing them with the assurance that it can progress successfully (in financial and technical terms, in particular) to the next stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cheam North and Worcester Park Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.