Major Works Procurement Strategy

Approved Committee 1 paper

Housing, Economy and Business Committee approved this item on Tuesday 1 July 2014. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

( i ) To approve the approach to the future procurement of planned internal major works to the Council’s housing stock, using the London Housing Consortium Whole House Refurbishment framework as set out in paragraphs 3.10 to 3.13 of the report. (ii) That a further report will be brought to the Committee in one year to provide monitoring information on the framework strategy. (iii) That a further report will be brought to the Committee in 2015/16 in relation to external works and contract administration consultancy support.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Housing, Economy and Business Committee

Page 55 Agenda Item 7

Report to: Housing, Economy and Business Committee

Date: 1 July 2014

Report of: Executive Head of Community Living and Strategic Commissioning

Ward Location: All Author(s) and Contact Phone Number(s): Trevor Hart, Housing Strategy and Commissioning Manager (020 8770 5844) Area Served: Borough-wide Chair of the Committee: Cllr Jayne McCoy

Report title:

MAJOR WORKS PROCUREMENT STRATEGY

Summary To provide for approval a strategy for procuring major works to the Council's housing stock from 2015 when existing contractual arrangements begin to come to an end. Recommendations The Committee is recommended to: 1. approve the approach to the future procurement of planned internal major works to the Council’s housing stock, using the London Housing Consortium Whole House Refurbishment framework as set out in paras. 3.10 to 3.13 of the report; and

2. agree that a further report will be brought to the Committee in 2015/16 in relation to external works and contract administration consultancy support.

Background Documents and Previous Decisions Review of Decent Homes Programme - report to Housing, Economy and Business Committee, Nov 2012

1 Agenda Item 7 Page 56

Signed:

Strategic Director, Adult Social Services, Housing and Health Date: 19th June 2014

1 Background 1.1 The management of the Council’s housing stock, comprising nearly 7,500 rented and leasehold homes, is carried out on its behalf by an arms length management organisation or ALMO - Sutton Housing Partnership (SHP). In addition to providing day to day management and responsive repairs services, SHP is responsible for undertaking planned major repairs and improvements to the stock. Such works can include replacement kitchens and bathrooms, new heating systems, electrical rewiring, replacement windows and doors and new roof coverings as well as a variety of repairs and improvements to estates and the communal parts of flatted blocks. The contracts for these works, unlike others that SHP manages, are legally held by the Council, ( i.e the Council is the contracting party not SHP), although they are procured and managed by SHP. 1.2 The current contracting arrangements for delivering major works to the Council’s housing stock, derived from a combination of individual tendering exercises and the use of framework agreements, are centred on a number of ‘works packages’, the principal ones being: internal works, external works, heating, contract administration and cost consultancy. For both internal works and external works SHP uses two contractors - respectively Lakehouse and Keepmoat and Lakehouse and Mulalley - while for heating works there is a single contractor - T Brown. Contract administration is shared between two firms - Pellings and Baily Garner - while cost consultancy is provided by Procom. 1.3 Since all of our current contracts are due to end in either 2015 or 2016, SHP has been developing, in liaison with the Council, a new procurement strategy for the coming years. This was approved by the SHP board of management at its meeting on 4 June 2014 for recommendation on to the Council.

2. Issues 2.1 Work to develop a new procurement strategy began last year, overseen by a steering group comprising key SHP staff and board members, resident representatives and the Council’s senior client officer, and supported by a specialist housing procurement consultancy. The group considered a range of issues including types of contract, how works might best be packaged, procurement options and various customer care related issues. They came up with a number of key principles to be followed, and these were duly approved by SHP’s board of management. Included in these were that: • contractors should be made responsible for all stages of the works process from initial contact with the resident through to completion and sign-off; 2 Page 57 Agenda Item 7

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Major works procurement strategy: report to 1 July HEB Ctte final withReport 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 22 attended
JM
Councillor Jayne McCoyChair, present
NE
Councillor Nick EmmersonVice-Chair, present
SB
Councillor Samantha BourneCommittee Member, apologies, sent representative
JC
Councillor Jean CrossbyCommittee Member, present
TF
Councillor Trish FiveyCommittee Member, present
NG
Councillor Neil GarrattCommittee Member, present
DH
Councillor David HicksCommittee Member, present
NM
Councillor Nick MatteyCommittee Member, present
JM
Councillor Joyce MelicanCommittee Member, present
DS
Councillor Daniel SangsterCommittee Member, present
DH
Councillor Doug HuntSubstitute, present as substitute
RD
Councillor Ruth DombeyEx Officio, present

All 22 on the meeting page

On this subject at Sutton

Search all
  1. Major Works Procurement StrategyThis decision
  2. Collingwood Boiler House Renewal - Major Works Contract ApprovalApproved
  3. HRA Major Works Contract Approval - Kitchens & BathroomsApproved
  4. Housing Revenue Account (HRA) Major Works - Fire SafetyApproved
  5. Shanklin Village - Proposed Major WorksApproved
  6. Major Works planned for 45 Thicket Crescent and 22 Thicket RoadApproved

More from Sutton Housing, Economy and Business Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the previous meetingthat the minutes of the meeting held on 9 June 2026 be agreed as an accurate record. Agreed Open
15 Sep 2026 Biannual Performance MonitoringThe Housing, Economy and Business Committee biannual performance monitoring report be noted Noted Open
15 Sep 2026 SHP Delivery Plan 26/27 UpdateSutton Housing Partnership’s Delivery Plan update, which includes the Service Improvement Plan 2026/27 and Performanc... Approved Open
15 Sep 2026 Beddington Farmlands UpdateThe progress made on the site over the last nine months be noted 2. The Breach of Condition Notice issued (5 Septembe... Noted Open
9 Jun 2026 Minutes of the previous meetingThat the minutes of the meeting held on 14 January 2026 be agreed as an accurate record . Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies