( i ) That consideration of the matter be deferred until the Committee’s next meeting, and NHS Property Services be asked to provide sufficient knowledgeable staff at that meeting to respond to the issues raised in the Healthwatch report. (ii) That clarification be sought regarding which organisations are responsible for which aspects of the building. 8:16 pm – the meeting adjourned until 8:26 pm.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1. The Wallington Local Care Centre (LCC), now known as Jubilee Health Centre, was the pilot scheme within the Better Healthcare Closer to Home (BHCH) programme. This Project Evaluation Report will allow lessons learned from the project to be transferred to the Nelson, Mitcham and other subsequent schemes.
2. This report forms part of the Post Project Evaluation process to be undertaken for the Jubilee Health Centre in Wallington and will be presented to the Jubilee Health Centre Programme Board and Sutton Clinical Commissioning Group (CCG).
3. The report covers two elements of the programme:
• Procurement, construction and fit out of the facilities; • Commissioning of the facilities into service.
4. This report does not cover procurement and mobilisation of clinical services which will be covered in other sections of the evaluation.
5. The Project Manager has maintained a “Lessons Learnt Log” which is attached at Appendix 3. The Log contains 16 issues which cover 3 areas of activity. This Executive Summary only highlights 7 key lessons:
Description Number of lessons 1 Organisation 9 2 Design 3 3 Project Administration 4
The project was complex with 6 clinical stakeholders including 2 GP practices and 4 service providers, the PCT and Practice Based Commissioners (PBC) who evolved into Sutton CCG and NHS England, Sutton Borough Council, Sutton LINk and Sutton Healthwatch and 2 building owners.
These lessons indicate that organisational issues within all the stakeholders have had a significant impact on the project. Design issues have been driven by organisational issues impacting on access to detailed knowledge, whilst Project Administration has been focused on construction programme risk management.
6. The report includes recommendations relating to the building specification made by Healthwatch Sutton following two site visits in 2013.
Version 1.0 Page 2 of 11 2014-01-28 Page 21 Agenda Item 5
7. The Jubilee Health Centre (JHC) was authorised in October 2009 as the Wallington Local Care Centre (WLCC) within the Better Healthcare Closer to Home (BHCH) programme. The programme has six objectives:
Version 1.0 Page 3 of 11 2014-01-28 Agenda Item 5 Page 22
• Providing more care locally; • Tackling health inequalities; • Meeting changing demographics and healthcare needs; • Using resources more efficiently; • Modernising estates; and, • Improving outcomes for patients.
The objectives below were met through the construction programme:
Objective Contribution to the Objective 1 Providing more The Development has provided the capacity to transfer in care locally outpatient appointments to a community setting at the heart of the eastern wards of Sutton. A diagnostic suite (including x-ray and ultrasound) has been installed and is in operation. All community mental health services and physiotherapy services were transferred from Sutton Hospital in 2012. Wallington is the centre of the east of the Borough of Sutton.
4 Using resources The forms of tenure between NHS Property Services who more efficiently are successor in title to Sutton and Merton Primary Care Trust (SMPCT) are intended to minimise unused space. Rooms are multifunctional.
5 Modernising The project has delivered a modern West Building and a estates fully refurbished East Building which both meet technical and clinical requirements for modern healthcare. Accommodation is compliant with all legislation, suitable for best clinical practice and in A1 condition. BREEAM Excellent was achieved for JHC West (the target for new accommodation). BREEAM Very Good was achieved for JHC East (the target for refurbished accommodation).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Scrutiny Committee Annual Report 2025/26The Annual Report 2025/26 (Appendix A of the report) be noted 2. The Annual Report 2025/26 be submitted to a future m...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.