(i) To agree the needs assessment of schemes contained within the project mandates. (ii) To agree that the draft list of proposals contained within Appendix A should form the basis of the submission to Transport for London for Local Implementation Funding in 2015/16. (iii) To agree to incur capital expenditure for 2014/15 Planned Highway Maintenance Programmes as outlined in 2014-18 Capital Programme.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to: Environment and Neighbourhood Committee 4 September 2014
Report of: The Executive Head of Commissioning
Ward Author and Contact Phone Number: Location: Paul Blunt 0208 770 6445 Not Applicable Area Served: Chair of the Committee: Borough-wide Councillor Jill Whitehead
Report title: Local Implementation Plan Finding Bid 2015/16
Summary This report outlines Transport for London’s (TfL’s) transport related programmes for investment from 2011/12 to 2016/17. In order to obtain Local Implementation Plan (LIP) funding for 2015/16, the Council is required to submit a funding submission to TfL by 3rd October 2014. The process for selecting schemes is described in the report, together with the proposed list of schemes for submission. In addition, the report describes the Council’s Planned Highway Maintenance Programme 2014/15 which addresses the more important maintenance requirements of roads in the Borough and the prioritisation process.
Recommendations The Environment and Neighbourhoods Committee is asked to: a) Consider and agree the needs assessment of schemes contained within the project mandates (see Appendix A) b) Agree that the draft list of proposals contained in Appendix A should form the basis of the submission to TfL for LIP funding in 2015/16. c) Agree to incur capital expenditure for 2014/15 Planned Highway Maintenance Programmes as outlined in 2014-18 Capital Programme Background Documents and Previous Decisions
Local Improvement Plan 2011-2031(Amended Oct 2013) Commissioning and Financial Planning 2014/15 to 2016/17 (Appendix F)
Signed:
Strategic Director Agenda Item 5 Page 8
Date: 21st August 2014 1. Background 1.1 The Local Implementation Plan (LIP) is Sutton’s Transport Plan for the borough and covers detailed transport proposals for the financial years 2014/15 to 2016/17. It also sets out a longer term transport plan to 2031. The LIP is Sutton’s contribution to the Mayor’s overall Transport Plan for London. There are five main programmes: Programme 1 – Maintenance: Principal road renewal, bridge strengthening, highway structures & assessment. Programme 2 - Corridors, Neighbourhoods and Supporting Measures: Holistic schemes for key ‘Corridors and Neighbourhoods’ that address issues relating to the smoothing of traffic flow, bus reliability, safety, cycling (including cycle parking and cycle training), public realm, local area improvements, including controlled parking zones, 20 mph zones, ‘Legible London’ signage, walking, reduction of street clutter, electric charging points, travel plans, travel awareness initiatives, freight and delivery issues. Programme 3 – Local Transport Funding: TfL allocates £100k per borough for use on Local Transport Projects of our choice and there is no need to identify schemes as part of the submission for this funding. This has been allocated to Local Committees on a per capita basis since it was introduced. Programme 4 – Cycling Initiatives: TfL allocates funding for borough-wide cycling initiatives, such as cycle to school partnerships, cycle training, cycle parking and a contribution to staff resources. TfL has indicated that this could be in the region of £400k. (A bid was submitted in October 2013) Programme 5 - Major Schemes: Including shared space projects and public realm improvements. (Separate bid for schemes over £1m.) Discussions are in progress with TfL for a major scheme bid for improvements to the Beddington Lane area focussed on the Beddington Lane corridor. It is proposed to improve the carriageway to Beddington Lane, provide a continuous cycle track and footway/foot path along its entire length and provide complementary improvements to the roads, cycle routes and pedestrian links in, and serving, the Beddington strategic industrial location.
1.2Using a needs-based formula, TfL has allocated £1.283m to Sutton Council for corridors, neighbourhoods and supporting measures for 2015/16.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.