Beddington and Wallington Local Committee approved this item on Tuesday 2 December 2014. Below is the council's own wording, with the papers it was decided on.
i. To earmark a sum of £23,190 for planters and barrier baskets, as set out in Appendix A of the report, to be funded from 2015/16 Public Realm Capital (converted to revenue), subject to budgets being made available within the 2015/16 budget cycle that will be approved in March 2015. ii. To fund one bench on Beddington Gardens and to recycle the money for the second bench back into the Public Realm budget. iii. To amend the list of funded schemes from Elgin Road to Beddington Gardens. The Committee noted that the process for agreeing Public Realm projects was very fair and proposed projects were fully discussed at Public Realm Funding meetings.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Beddington and Wallington Local Committee
Summary
1.1This report provides an update on the progress of public realm projects since September 2014, new public realm schemes for the committee to consider and provides confirmation of the remaining budgets for 2014/15.
Recommendations
2.1To earmark a sum of £23,190 for planters and barrier baskets, as set out in Appendix A, to be funded from 2015/16 Public Realm Capital (Converted to Revenue), subject to budgets being made available within the 2015/16 budget cycle that will be approved in March 2015.
Background
3.1This Committee has been allocated £55,544 of Public Realm capital funding to invest in area improvements, an allocation of £22,218 for transport related schemes and £10,000 of revenue funding.
4. Issues
Schemes for Consideration of Funding
4.1Public realm schemes for consideration at this committee are detailed under Appendix A.
Current Public Realm Scheme Programme Agenda Item 9 Page 18
4.2Progress to date on current public realm schemes, funded by the committee, are detailed under Appendix A, Section 2.
Completed Public Realm Schemes
4.3Public realm schemes which have been completed since the last meeting of the committee are detailed under Appendix A, Section 3. These include:
Bandon Hill Cemetery signs Repositioning of Bench in Springfield Road / Replacement of Bench in Manor Road Survey to Assess Pavement Improvements in Manor Road
Options considered
5.1Public realm schemes can be proposed by ward councillors or community representatives. Consultation is then undertaken to agree which schemes should be proposed. These are then voted on at each meeting of the Local Committee.
6. Impacts and Implications
Financial
6.1The Beddington & Wallington Local Committee currently has a total available budget of £9,215 made up of £8,637 Public Realm Capital, £218 Transport for London funding and £360 direct revenue funding, if the proposals are agreed. This is detailed in Appendix A, Section 5.
Legal
6.2There are no specific legal implications arising from this report.
Other impacts and implications (Insert titles where appropriate – the guidance note suggests some implications which may be relevant)
6.3The schemes described in this report have been subject to consultation with local residents, councillors, community representative and partner organisations. Meetings are held in accessible venues and everyone is encouraged to take part and put forward their ideas.
6.4When public realm improvements are made as a result of decisions taken by the Local Committee, particular account is taken of the requirements under the Disability Discrimination Act and Equality Act 2010 with regard to access requirements.
6.5Many of the schemes that are approved have a positive effect by promoting community activity and improving shared spaces that everyone can enjoy.
6.6The work of the Local Committee and the public realm budget are a key part of Sutton Council’s response to the localism agenda, and actively promotes the engagement of local residents in decision making. Page 19 Agenda Item 9
7. Appendices and Background Documents
Appendix Letter Title A Area Improvements and Public Realm Programme B Progress on schemes being delivered C Completed scheme since the last meeting D Unfunded Public Realm Schemes for future consideration E Beddington and Wallington Local Committee Financial Update
Background Documents None
Audit Trail Version Date:
1.0Final 02/12/2014
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Beddington and Wallington Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.