Children, Family and Education Committee decided this item on Thursday 18 December 2014. Below is the council's own wording, with the papers it was decided on.
To ratify the feasibility work for two secondary school sites, namely Belmont (former site of Sutton Hospital) and the All Weather Pitch at Rosehill and adjacent land. 2. To give authority to incur expenditure totalling £500k (£100k per school) for the Phase 2 secondary expansion projects at the following schools in order for them to develop post feasibility to both planning and detailed design stages: · Greenshaw High School · Overton Grange High School · St Philomena’s Catholic High School for Girls · The John Fisher School · Wallington County Grammar School for Boys 3. To give authority to incur expenditure for the following expansion projects so that the construction phase can commence: · Up to a total of £2,337,041 for St Mary’s Junior School for Key Stage 2 expansion, of which £100k has already been authorised. · Up to a total of £2,330,000 for St Elphege’s Junior School for Key Stage 2 expansion, of which £100k has already been authorised. · Up to a total of £1,514,000 for Sherwood Park School for the Phase 2 expansion on the current site
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Children, Family and Education Committee
Summary
1.1This report updates on the delivery of school places in Sutton required due to demographic increase in the Borough. It seeks approval for capital expenditure and informs about the public consultation regarding the proposed expansion of Hackbridge Primary School.
Recommendations
2.1To ratify feasibility work for two secondary school sites, namely Belmont (former site of Sutton Hospital) and the All Weather Pitch at Rosehill and adjacent land.
2.2To give authority to incur expenditure totalling £500k (£100k per school) for the Phase 2 secondary expansion projects at the following schools in order for them to develop post feasibility to both planning and detailed design stages:
Greenshaw High School Overton Grange High School St Philomena’s Catholic High School for Girls The John Fisher School Wallington County Grammar School for Boys
2.3To give authority to incur expenditure for the following expansion projects so that the construction phase can commence:
Up to a total of £2,337,041 for St Mary’s Junior School for Key Stage 2 expansion, of which £100k has already been authorised. Up to a total of £2,330,000 for St Elphege’s Junior School for Key Stage 2 expansion, of which £100k has already been authorised. Up to a total of £1,514,000 for Sherwood Park School for the Phase 2 expansion on the current site Agenda Item 5 Page 10
Background
3.1As stated in previous reports, school expansions are required to meet the demographic increase in Sutton. Sutton’s expansion programme began in 2008 and has been ongoing. Expansions have been in the primary sector, but as from 2015, the secondary sector will be ready to take increasing numbers and schools are currently involved in building programmes to meet this need.
4. Issues
Secondary School Expansion Programme
4.1New Secondary Schools Due to the school population growth in Sutton, two new secondary schools will be required; the first in September 2017 and the second in September 2019. Two sites are currently being considered, one is the Belmont (former site of Sutton Hospital) site and the other is the All Weather Pitch and adjacent land in Rosehill. Feasibility work is being carried out on the Rosehill site and was due to be carried out at the same time on the Belmont site, however, unfortunately the Epsom St Helier Trust has not allowed Sutton Council to proceed with the surveys. The Council is expecting an update in mid-December from the ‘Trust’ as to how we proceed and an update will be given at the next Committee. The Rosehill feasibility study is due to be completed in January 2015 and we hope that the Belmont site will be completed soon after. If the feasibility studies are completed in accordance with the above timescales, this does allow sufficient time for a school to be built for September 2017. An update on both sites will be given to the Committee at the next meeting in March 2015.
4.2Expansion of Secondary Schools Phase 1 Schools are on schedule to deliver places for September 2015. Building programmes are being monitored appropriately.
Phase 2 Schools listed on Page 1 of this report have commissioned feasibility studies and will be developing the projects further to planning application stage in the coming months, hence the request for authorisation to incur expenditure for their projects.
Primary School Expansion Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.