Sutton South, Cheam and Belmont Local Committee approved this item on Thursday 2 July 2015. Below is the council's own wording, with the papers it was decided on.
That the Sutton South, Cheam and Belmont Local Committee approves the funding for Christmas lights for 2015 to the value of £16,140, funded from the public realm for 2015/16 in the following locations (subject to confirmation of costs from the contractor): · The Broadway, High Street, Station Way and Ewell Road, Cheam; · Upper Mulgrave Road, Cheam; · Station Road, Belmont.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Sutton South, Cheam and Belmont Local Committee
Summary
1.1This report asks for the Sutton South, Cheam and Belmont Local Committee’s approval of funds to implement Christmas lights in 2015 at Cheam and Belmont.
Recommendations
The Sutton South, Cheam and Belmont Local Committee is asked to:
2.1Approve the funding of Christmas lights for Christmas 2015 to the value of £16,140 (£13,520 plus a contingency of £2,620) funded from the Public Realm for 2015/16 in the following locations (subject to confirmed costs from the contractor):
The Broadway, High Street, Station Way and Ewell Road, Cheam Upper Mulgrave Road, Cheam Station Road, Belmont
Background
3.1Implementation of Christmas lighting in 2014 resulted in a number of issues and concerns. As a result a more detailed cost analysis for 2015 is provided that includes a contingency budget.
3.2A tender is currently being carried out for the procurement of a single provider for all Christmas lighting schemes throughout the borough.
3.3The procurement is being progressed by the Town and District Centre Manager, who will also support the co-ordination and installation of displays whilst promoting value for money. Agenda Item 8 Page 24
Procurement for 2015
3.4The current contract for Christmas lighting displays has expired. In order to prepare a tender for Christmas lighting displays required for the 2015 Christmas season, Local Committees are asked to commit budget and to approve the locations for displays.
3.5Following a paper taken to the Local Committees in 2013 a decision was made that in order to achieve best value for money, Christmas lights should be hired instead of purchased. This was based on there being no suitable Council owned storage facilities. In addition, lighting displays that are left in situ all year are subject to rapid deterioration and would require regular repair, resulting in additional costs. Hiring Christmas lights allows the Committee to benefit from a Christmas lighting scheme with the latest designs and lighting technology.
3.6In order to avoid damage to lamp columns and to ensure safety, only contractors approved by the London Borough of Sutton are permitted to erect displays on London Borough of Sutton lamp columns. Approved contractors undertake all activities in a safe manner through controls on suitably qualified staff, risk assessments and application of recognised standards.
3.7Where lighting displays are requested on private property, such as the Housing Association premises, permission must be sought from the landowner and the lamp columns tested for safety. For cases where displays are requested on Transport for London owned and operated Red Routes, permissions and licenses must be sought from Transport for London.
3.8LBS is tendering for the supply of Christmas Lights on a one year, plus one year, plus one year basis, i.e. a one year contract is placed but it can be extended for two years before the contract terminates. This will save operational resource in future years and achieve continuity for the local area. Financial commitment will be sought on a yearly basis.
4. Issues
4.1Any additional funding for new locations (over and above those stated in this report) will require approval at subsequent committee meeting. Approval of implementation of Christmas lights at new locations cannot be confirmed without a binding offer from the contracted supplier on costs and timescales.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Sutton South, Cheam and Belmont Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingthat the minutes of the meeting held on 5 February 2026 be agreed as an accurate record. On behalf of the Committee, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.