Beddington and Wallington Local Committee agreed this item on Tuesday 28 June 2016. Below is the council's own wording, with the papers it was decided on.
2.1 The Committee agree to delegate the decision on the final schemes to Councillors in consultation with officers. 2.2 Recommend that the Environment and Neighbourhood Committee, as the Highways Authority for the London Borough of Sutton, include the list of schemes in Appendix A in its submission to TfL for LIP funding for 2017/18.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Beddington and Wallington Local Committee
Page 15 Agenda Item 10
Report to: Beddington and Wallington Local Date: 28 June 2016 Committee
Report title: Local Implementation Plan for the 17/18 Budget
Report from: Mary Morrissey, Strategic Director – Environment, Housing & Regeneration
Ward/Areas affected: Borough Wide
Chair of Committee: Councillor Joyce Mellican
Author(s)/Contact Ian Price, Team Leader Strategy and Commissioning, 020 8770 6461 Number(s): Corporate Plan Priorities: A Green Council
Open/Exempt: Open
Signed: Date: 17 June 2016
1. Summary.
The report outlines Transport for London’s (TfL’s) transport-related programmes for investment. At the time of writing this report TfL has not issued the guidance for bidding for the 2017/18 year as they are going through a transition year because of the election of a new London Mayor. TfL has suggested that the process will be the same as last year so in order to obtain Local Implementation Plan (LIP) funding for 2017/18, the Council is required to submit a funding submission to TfL in advance. The Council’s process for selecting schemes is described in the report together with the proposed list of schemes for submission.
2. Recommendations.
The Beddington and Wallington Local Committee is recommended to: 2.1 Consider and agree the proposed schemes as contained in Appendix A of this report.
2.2Recommend that the Environment and Neighbourhood Committee, as the Highways Authority for the London Borough of Sutton, include the list of schemes in Appendix A in its submission to TfL for LIP funding for 2017/18.
3. Background. Agenda Item 10 Page 16
3.1The Local Implementation Plan (LIP) is Sutton’s Transport Plan for the borough. As the Borough, along with the rest of London, is waiting for the new mayors transport strategy and bid guidance the Borough has worked on a 1 year programme to cover detailed transport proposals for the 2017/18 financial year. The LIP is Sutton’s contribution to the Mayor’s overall Transport Plan for London so will be working on a new 3 year programme from 2018/19 once TfL release more information. TfL has suggested extending the last 3 year programme for an extra year. Therefore there are five main programmes and TfL have listed the key outputs/outcomes of the programmes which should be achieved as follows: Programme 1 – Maintenance: Principal road renewal, bridge strengthening, highway structures and assessment. Programme 2 - Corridors, Neighbourhoods and Supporting Measures: Holistic schemes for key ‘Corridors and Neighbourhoods’ that address issues relating to the smoothing of traffic flow, bus reliability, safety, cycling (including cycle parking and cycle training), public realm, local area improvements, including controlled parking zones, 20 mph zones, ‘Legible London’ signage, walking, reduction of street clutter, electric charging points, travel plans, travel awareness initiatives, freight and delivery issues. Programme 3 – Local Transport Funding: TfL allocates £100,000 per borough for use on Local Transport Projects of our choice and there is no need to identify schemes as part of the submission for this funding. This has been allocated to Local Committees on a per capita basis since it was introduced. Programme 4 – Cycling Initiatives: TfL allocates funding for borough wide cycling initiatives, cycle training, cycle parking and a contribution to staff resources. Programme 5 - Major Schemes: Including shared space projects and public realm improvements.
3.2There is no preset allocation for maintenance and schemes in this category (programme 1) they are assessed by TfL on merit. Last year TfL indicated that the borough should bid for at least £200,000 for Principal Road Maintenance so this will be assumed for 2017/18 also.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Beddington and Wallington Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.