Resolved
RESOLVED : that 1. The progress of Public Realm schemes, as highlighted in Appendix A, be noted. 2. The sum of £4,374 Public Realm Capital for the installation of signage on Beddington Park as detailed, in Appendix A, be approved.
Beddington and Wallington Local Committee noted this item on Tuesday 11 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : that 1. The progress of Public Realm schemes, as highlighted in Appendix A, be noted. 2. The sum of £4,374 Public Realm Capital for the installation of signage on Beddington Park as detailed, in Appendix A, be approved.
1.1This report contains information on Public Realm spending since 16 May 2017, details any new requests for Public Realm funding and confirms available budgets for 2016/17.
The Beddington and Wallington Local Committee is recommended to:
2.1Note the progress of Public Realm schemes as highlighted in appendix A
2.2Approve the sum of £4,374 Public Realm Capital for the installation of signage in Beddington Park as detailed in Appendix A.
3.1This Committee has been allocated Public Realm funding to invest in area improvements. Agenda Item 11 Page 36
3.2The work of the Local Committees, including their management of the Public Realm budget, plays a pivotal role in the development of Sutton Council’s localism agenda and makes a significant contribution to resident engagement in locality decision making.
3.3The approved schemes have a positive effect on the local area by promoting community activity and improving shared spaces everyone can enjoy.
4. Issues
Schemes for Consideration of Funding
4.1Appendix A, Section 1 shows Public Realm schemes for consideration by the committee, at this meeting.
Current Public Realm Scheme Programme
4.2Appendix A, Section 2 shows all other current Public Realm schemes, within the Programme, previously agreed by the Committee and updates on progress.
Completed Public Realm Schemes
4.3Appendix A, Section 3 sets out Public Realm schemes completed since the last meeting of the Committee, including:
● BW/1617.13 - Woodcote Green bench ● BW/1617.7 - Woodcote Green information board ● BW/1617.15 -Traffic surveys for Tharp Road ● BW/1617.22 - Woodcote Road ● BW/1617.23 - Elgin Road ● BW/1617.24 - Boundary Road ● BW/1617.26 - Clyde Road - Traffic surveys
Unfunded Public Realm Schemes
4.4Appendix A, Section 4 sets out previously approved but not yet agreed, Public Realm schemes.
Annual Revenue Maintenance
4.5Appendix A, Section 5 sets out the ongoing revenue commitments for the maintenance of existing public realm schemes previously commissioned by this Committee.
Proposed Schemes to recycle or to clear over spend
4.6Appendix A, Section 6 sets out the proposed scheme(s) recommended to recycle. Page 37 Agenda Item 11
5.1Public Realm schemes can be proposed by ward councillors or community representatives. Proposals are taken through consultation to determine which schemes should be considered and voted on at each meeting of the Local Committee.
6. Impacts and Implications
Financial
6.1The 2017/18 total budget allocation is £104,953 made up of £55,544 Public Realm capital, £22,218 transport related schemes, £10,000 direct revenue funding and £3,858 Public Realm capital and £13,333 direct revenue funding carried forward from 2016/17 subject to approval by S & R Committee 17 July 2017.
6.2The committee has previously allocated funds of £42,912 Public Realm capital (converted to revenue), £0 transport related schemes, £1,220 direct revenue funding, and has recycled £15,505 Public Realm capital in 2017/18.
6.3The total cost of the proposed schemes in Appendix A, Section 1 is £4,374 Public Realm capital funding, £0 transport related schemes and £0 direct revenue funding.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(11) Public Realm Projects and Neighbourhood GrantsReport | 120 KB | DownloadRead as text |
PDF |
(11) Public Realm Projects and Neighbourhood Grants: Appendix AAppendix | 170 KB | Download |
PDF |
(11) Public Realm Projects and Neighbourhood Grants: PresentationReport | 536 KB | Download |
Follow Beddington and Wallington Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 20 January 2026 be agreed as an accurate record. | Agreed | Open |
| 7 Jul 2026 | Public questionsIt was agreed that local ward councillors would investigate the matter outside of the meeting. In response to a quest... | Agreed | Open |
| 20 Jan 2026 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 30 September 2025 be agreed as an accurate record. | Agreed | Open |
| 20 Jan 2026 | Public questionsIt was agreed that a response to these questions would be provided following the meeting. | Agreed | Open |
| 30 Sep 2025 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 10 June 2025 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.