Fire Safety in Council Flatted Blocks

Noted Committee 1 paper

Housing, Economy and Business Committee noted this item on Tuesday 26 September 2017. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

that the actions taken to date to ensure the fire safety of the Council’s flatted blocks be noted, the programme of further works and actions to be undertaken be endorsed and any recommendations coming from Dame Judith Hackitt's report concerning building regulations, be endorsed and acted upon within set timescales.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Housing, Economy and Business Committee

Summary

1.1This​ ​report​ ​provides​ ​the​ ​Committee​ ​with​ ​a​ ​summary​ ​of​ ​the​ ​actions​ ​carried​ ​out​ ​to​ ​date​ ​by Sutton​ ​Housing​ ​Partnership​ ​(SHP)​ ​to​ ​ensure​ ​the​ ​fire​ ​safety​ ​of​ ​the​ ​Council’s​ ​flatted​ ​blocks​ ​in the​ ​wake​ ​of​ ​the​ ​Grenfell​ ​Tower​ ​tragedy.​ ​ ​It​ ​also​ ​sets​ ​out​ ​the​ ​programme​ ​of​ ​works​ ​and​ ​further actions​ ​to​ ​be​ ​undertaken.

Recommendations

It​ ​is​ ​recommended​ ​that​ ​the​ ​Housing,​ ​Economy​ ​and​ ​Business​ ​Committee:

2.1Notes​ ​the​ ​actions​ ​taken​ ​to​ ​date​ ​to​ ​ensure​ ​the​ ​fire​ ​safety​ ​of​ ​the​ ​Council’s​ ​flatted​ ​blocks​ ​and endorses​ ​the​ ​programme​ ​of​ ​further​ ​works​ ​and​ ​actions​ ​to​ ​be​ ​undertaken.

Background

3.1Members​ ​will​ ​be​ ​well​ ​aware​ ​of​ ​the​ ​tragic​ ​fire​ ​that​ ​occurred​ ​at​ ​Grenfell​ ​House​ ​in​ ​west​ ​London on​ ​14​ ​June​ ​this​ ​year.​ ​ ​Since​ ​that​ ​time​ ​a​ ​considerable​ ​amount​ ​of​ ​work​ ​has​ ​been​ ​done​ ​locally to​ ​ensure​ ​the​ ​fire​ ​safety​ ​of​ ​Sutton’s​ ​high​ ​rise​ ​and​ ​other​ ​tall​ ​flatted​ ​blocks​ ​going​ ​forward,​ ​this including​ ​a​ ​number​ ​of​ ​responsive​ ​actions​ ​taken​ ​immediately​ ​or​ ​within​ ​a​ ​few​ ​days​ ​of​ ​the​ ​event. Agenda Item 6 Page 10

3.2This​ ​report​ ​provides​ ​a​ ​brief​ ​summary​ ​of​ ​the​ ​actions​ ​taken​ ​to​ ​date.​ ​ ​It​ ​also​ ​sets​ ​out​ ​a​ ​range​ ​of further​ ​actions,​ ​including​ ​a​ ​programme​ ​of​ ​proposed​ ​works,​ ​to​ ​ensure​ ​continuing​ ​fire​ ​safety​ ​of all​ ​the​ ​Council’s​ ​flatted​ ​blocks.​ ​These​ ​are​ ​now​ ​incorporated​ ​into​ ​SHP’s​ ​outline​ ​five​ ​year programme​ ​of​ ​major​ ​repairs​ ​and​ ​improvements.

4. Issues

4.1As​ ​would​ ​be​ ​expected,​ ​the​ ​immediate​ ​response​ ​of​ ​SHP,​ ​following​ ​the​ ​Grenfell​ ​Tower​ ​fire, was​ ​to​ ​focus​ ​on​ ​the​ ​Council’s​ ​two​ ​tower​ ​blocks​ ​-​ ​Chaucer​ ​House​ ​and​ ​Balaam​ ​House.​ ​ ​Both had​ ​recently​ ​been​ ​refurbished​ ​and​ ​re-clad,​ ​the​ ​former​ ​using​ ​aluminium​ ​composite​ ​material (ACM).​ ​ ​However,​ ​Chaucer​ ​House​ ​was​ ​also​ ​fitted​ ​with​ ​a​ ​sprinkler​ ​system,​ ​resourced​ ​by additional​ ​decent​ ​homes​ ​backlog​ ​funding​ ​from​ ​the​ ​Greater​ ​London​ ​Authority.

4.2The​ ​process​ ​of​ ​addressing​ ​fire​ ​safety​ ​has​ ​since​ ​been​ ​overseen​ ​by​ ​a​ ​project​ ​group​ ​of​ ​senior officers​ ​from​ ​both​ ​SHP​ ​and​ ​the​ ​Council,​ ​chaired​ ​by​ ​SHP’s​ ​Managing​ ​Director​ ​and​ ​meeting weekly;​ ​meetings​ ​have​ ​also​ ​included​ ​the​ ​Chair​ ​and​ ​Vice​ ​Chair​ ​of​ ​the​ ​HEB​ ​Committee.​ ​ ​At​ ​the same​ ​time,​ ​SHP​ ​and​ ​the​ ​Council​ ​have​ ​been​ ​working​ ​in​ ​close​ ​co-operation​ ​with​ ​the​ ​London Fire​ ​Brigade​ ​(LFB).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(6) Fire Safety in Council Flatted BlocksReport 167 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JM
Councillor Jayne McCoyChair, present
NE
Councillor Nick EmmersonVice-Chair, present
DB
Councillor David BartolucciCommittee Member, present
RC
Councillor Richard CliftonCommittee Member, present
TF
Councillor Trish FiveyCommittee Member, present
AH
Councillor Amy HaldaneCommittee Member, present
JM
Councillor Joyce MelicanCommittee Member, present
DS
Councillor Daniel SangsterCommittee Member, present
DH
Councillor David HicksCommittee Member, present
NG
Councillor Neil GarrattCommittee Member, present
RD
Councillor Ruth DombeyEx Officio, expected

On this subject at Sutton

Search all
  1. Fire Safety in Council Flatted BlocksThis decision
  2. Housing Revenue Account (HRA) Major Works - Fire SafetyApproved
  3. Fire SafetyNoted
  4. Award of contract for fire safety works at Chaucer HouseAgreed
  5. What the regulatory reform (fire safety) order 2005 means for disabled peopleDecided

More from Sutton Housing, Economy and Business Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the previous meetingthat the minutes of the meeting held on 9 June 2026 be agreed as an accurate record. Agreed Open
15 Sep 2026 Biannual Performance MonitoringThe Housing, Economy and Business Committee biannual performance monitoring report be noted Noted Open
15 Sep 2026 SHP Delivery Plan 26/27 UpdateSutton Housing Partnership’s Delivery Plan update, which includes the Service Improvement Plan 2026/27 and Performanc... Approved Open
15 Sep 2026 Beddington Farmlands UpdateThe progress made on the site over the last nine months be noted 2. The Breach of Condition Notice issued (5 Septembe... Noted Open