Housing, Economy and Business Committee noted this item on Tuesday 23 January 2018. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: Progress to date with the property acquisition programme be noted. It be agreed to authorise expenditure on property acquisitions in line with the projected resource availability as set out in the HRA Business Plan (September 2017 update).
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
The Housing Economy and Business Committee is recommended to:
2.1Note progress to date with the property acquisition programme;
2.2Authorise expenditure on property acquisitions in line with the projected resource availability as set out in the HRA Business Plan (September 2017 update).
Background
3.1At its meeting in March 2017 the Committee agreed in principle to the Council commencing a programme of property acquisitions, principally to provide a better and cheaper alternative to the use of expensive nightly paid temporary accommodation, the costs of which continue to escalate.
3.2A follow up report to the June meeting set out some initial financial modelling, which indicated that in combination with Right to Buy (RTB) receipts, there were both Housing Revenue Account (HRA) and General Fund resources available to fund the programme. The modelling also Agenda Item 11 Page 162
demonstrated the viability of the programme in terms of the rental income offset against future maintenance and borrowing costs, and savings in temporary accommodation costs.
3.3It was agreed that the programme would make use of two combined sources of funding: (i) a mix of General Fund borrowing via the Public Works Loan Board (PWLB) and net RTB receipts and (ii) a mix of HRA revenue funding and net RTB receipts - the former to be focussed primarily on purchases within the open market, the latter on ex-council stock. In both cases RTB receipts would fund the maximum allowable proportion of the total acquisition cost, ie 30%.
3.4The revised HRA Business Plan, considered by the Committee at its September 2017 meeting, confirmed that over five years (2017/18 to 2021/22), around £30m could be applied to the programme, subject to any further demands for resources to deal with existing stock investment. On an assumed average total acquisition cost per unit of £315k, this would yield approximately 96 acquisitions (averaging 19 per annum).
3.5It was agreed that a report on progress would be brought back to the Committee at regular intervals, commencing in January 2018. Progress to date is therefore set out below.
4. Issues
4.1The initial focus of the programme has been on ex-council stock sold under RTB, as these properties tend to be priced towards the lower end of the market and thus offer greater value for money. To date, funding deployed has been from the HRA (i.e. a combination of available HRA revenue, plus RTB net receipts) as a better option than using General Fund borrowing, which has the additional cost of interest. Also, units purchased with HRA funding become HRA assets and thus help to maintain the sustainability of the HRA.
4.2Set out in the table below is a summary of completed and ongoing purchases as at 10 January.
I bed 2 bed 3 bed Total
Offer accepted 6 16 4 26
Contracts exchanged 0 2 0 2
Purchase completed 1 2 2 5
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.