Resolved
RESOLVED that : The Corporate Risk Register was reviewed, considered and commented on. 2. No new risks were highlighted to be added or escalated to the corporate risk register 3. The Council’s overall risk statement was considered.
Audit Committee decided this item on Thursday 29 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that : The Corporate Risk Register was reviewed, considered and commented on. 2. No new risks were highlighted to be added or escalated to the corporate risk register 3. The Council’s overall risk statement was considered.
1.1The Committee are asked to review and comment upon the latest corporate risk register shown as Appendix A. In order to ensure effective corporate oversight of key organisational risks the Council’s recently updated risk management strategy requires the corporate risk register to be reviewed at Audit Committee on a regular basis.
The Audit Committee is recommended to:
2.1Review, consider and comment on the corporate risk register
2.2Suggest any new risks to be added or escalated to the corporate risk register
2.3Consider the Council’s overall risk statement
3.1To ensure that there continues to be a Council-wide overview of key risks, the corporate risk register will be reviewed by audit committee on a regular basis. The review should focus on:
● Any new risks identified over the last three months to be added to the risk register Agenda Item 11 Page 100
● Any significant changes to risks, the reasons for this and the mitigation to be put in place ● Additional risks to be considered; or escalated to the corporate register, going forward.
3.2A risk statement, summarising the key risks; and dependencies between risks, has been produced.
4. Issues
New Risks
4.1There are currently 14 risks on the corporate risk register. The risk register was last updated in early March and was considered by CMT on 21 March. Since it was last reviewed by Audit Committee there have been no new risks added.
Significant Changes
4.2CORP RR 12 Alternative delivery models failure - Following the collapse of Carillion and profit warning regarding a number of other large outsourcing companies (including Capita) a review of the Council’s expopsure to these organisations has been completed. The review found that overall the Council’s exposure is relatively low with the facilities management contract with Mitie and also our payment processing software being provided by Capita. No change to current risk level.
4.3CORP RR 02 Breach of information governance or security - Project plan for GDPR is in place and the project team have begun implementation using a risk-based approached. Unlikely that the Council will be fully compliant but the ICO has confirmed that as long as Councils are paper compliant by 25 May 2018 there will be no sanctions. We are on course to meet at least this level of compliance, if not more. No change to current risk level.
4.4There have been no other significant changes in the level of risk for any of the risks currently on the corporate risk register.
Overall Risk Statement March 2018
4.5The Chief Executive and Corporate Management team (CMT) are ultimately accountable for ensuring that risk management is fully embedded in the Council’s business planning and monitoring processes as well as having overall accountability and responsibility for leading the delivery of the Council’s Risk Management Strategy and Framework. CMT take a leading and proactive role in ensuring that risks are managed effectively and that risk management is communicated, understood and implemented by Councillors, managers and staff.
4.6This statement from the Chief Executive summarises the key risks to the organisation and actions required to mitigate these1.
1 The statement is reported to members as part of the Risk report to Audit Committee and the Performance and Finance Report to Strategy and Resources Committee. Page 101 Agenda Item 11
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(11) Audit committee Risk Register Review March 2018Report | 145 KB | DownloadRead as text |
PDF |
(11a) Appendix A CorporateRiskRegister201718Appendix | 187 KB | Download |
Follow Audit Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Mar 2018 | Minutes of the last meetingthat the minutes of the meeting held on 11 January 2018 be agreed as a correct record. | Agreed | Open |
| 29 Mar 2018 | Treasury Management Quarterly reportRESOLVED that : The treasury management activity undertaken during the first nine months of the year was noted It be ... | Noted | Open |
| 29 Mar 2018 | Internal Audit Annual Plan 2018/19RESOLVED that : 1.The Internal Audit Plan, Charter and Strategy for 2018/19 was commented upon and it be approved. | Approved | Open |
| 29 Mar 2018 | SWLFP Anti Fraud and Investigations updateRESOLVED that : 1.The report was noted and commented upon . | Noted | Open |
| 11 Jan 2018 | Minutes of the last meetingthat the minutes of the meeting held on 21 September 2017 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.