Resolved
that 1. Officers procure an external provider for a one-year trial of a design review panel. 2. The outcome of the one-year trial be reported to a future meeting of the Housing, Economy and Business Committee.
Housing, Economy and Business Committee decided this item on Tuesday 25 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
that 1. Officers procure an external provider for a one-year trial of a design review panel. 2. The outcome of the one-year trial be reported to a future meeting of the Housing, Economy and Business Committee.
1.1This report considers whether a design review panel is suitable and feasible as part of the planning application process in Sutton. It recommends a one-year trial for a panel and proposes some parameters for the trial.
The Housing, Economy and Business Committee is recommended to:
2.1Agree that officers procure an external provider for a one-year trial of a design review panel.
2.2Agree that the outcome of the one-year trial be reported to a future meeting of the Housing, Economy and Business Committee. Agenda Item 9 Page 208
3.1What is a design review panel (Panel)? A panel is a group of planning and architectural professionals, most usually, who review planning applications and/or pre-applications from a design perspective. The aim is to provide an expert design critique of a proposed scheme.
3.2Who is on it? The composition of a Panel is at the discretion of the local planning authority (LPA) and can include nationally and regionally known planners and architects or those with local expertise. The best panels are considered to be those that are small in number but provide a balance between local expertise and those with national/regional standing and include a broad spread of expertise, e.g. urban designers, land use planners, transport planners and architects.
3.3What weight does it have? Panels act in an advisory capacity and will merely recommend to the LPA planning committee. A planning officer can go against the recommendation of a Panel and sometimes the Panel will not agree amongst itself. Generally though, it will act as a design assessor for the LPA.
3.4Which proposals does it consider? T he scope of a Panel varies between LPA’s. Some boroughs include all major developments (waste development; housing developments with 10 units or more or a site of 0.5ha or more; buildings creating a floorspace of 1,000sqm or more and, development on a site of 1ha or more). Others include smaller schemes which have a large impact, have design challenges, are likely to benefit from scrutiny and Council schemes.
3.5What exactly does it do? Most Panels follow a standard procedure: site visit; briefing by officer; presentation by applicant; comment and discussion; summary and advice; report; and presentation of report. The stages to the report usually take half a day. However, large schemes can have multiple reviews and can be linked to a pre-application service, while some Panels have meetings at the beginning, middle and end of the planning process.
3.6Who runs it? Of the 35 London planning authorities, 10 outsource their Panels to external providers, such as the Commission for Architecture and the Built Environment (CABE)/Design Council. 12 manage their Panels in house, some of which are free and some are formal and charged. 13 LPA’s (including LB Sutton) have no Panel, although Havering is in the process of establishing a trial.
3.7How much does it cost? Most LPA’s charge developers for the input of a Panel, with a view to covering costs, namely fees to Panel members and administrative costs. The average cost for a half-day Panel meeting in London is £3,670.
4. Issues
4.1The principal issue this report considers is whether Sutton Council should establish a Panel.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Establishing a Design Review Panel: ReportReport | 135 KB | DownloadRead as text |
Follow Housing, Economy and Business Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Minutes of the previous meetingthat the minutes of the meeting held on 9 June 2026 be agreed as an accurate record. | Agreed | Open |
| 15 Sep 2026 | Biannual Performance MonitoringThe Housing, Economy and Business Committee biannual performance monitoring report be noted | Noted | Open |
| 15 Sep 2026 | SHP Delivery Plan 26/27 UpdateSutton Housing Partnership’s Delivery Plan update, which includes the Service Improvement Plan 2026/27 and Performanc... | Approved | Open |
| 15 Sep 2026 | Beddington Farmlands UpdateThe progress made on the site over the last nine months be noted 2. The Breach of Condition Notice issued (5 Septembe... | Noted | Open |
| 9 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 14 January 2026 be agreed as an accurate record . | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.