Local Implementation Plan Funding Settlement 2019/20
AgreedCommittee4 papers
Environment and Neighbourhood Committee agreed this item on Thursday 7 March 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED : that: 1. The schemes and measures listed at table ST01 in Appendix A and also in the summary table at Appendix B, which provide the basis for the LIP work programme for 2019/20, be agreed. 2. It be agreed to incur capital expenditure of £890,400 for the capital schemes identified in the LIP for Corridors and Neighbourhoods, £100,000 for Local LIP funding and £815,000 for Beddington North Major Scheme so that the projects can proceed. A sum of £169,000 for various revenue initiatives identified in the Corridors and Neighbourhoods programme (approved for 2019/20) and is included in the revenue estimates. 3. The specific funding circumstances attached to the profiling of the Beddington Major Scheme, as set out in paragraphs 3.12 and 6.2, be noted. 4. Authority be delegated to the Assistant Director - Transport, Highways and Regulatory Services, to take all necessary steps to implement the schemes, including commencing any necessary statutory consultations.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report outlines Transport for London’s (TfL’s) funding settlement to the Council for Local Implementation Plan (LIP) funding in 2019/20 and notes the current status of the borough’s LIP3 Transport Strategy. A description of TfL’s transport-related programmes is given and how schemes were selected to be put forward for funding.
Recommendations
The Environment and Neighbourhood Committee is recommended to:
2.1Agree the schemes and measures listed at table ST01 in Appendix A and also in the summary table at Appendix B, which provide the basis for the LIP work programme for 2019/20.
2.2Agree to incur capital expenditure of £890,400 for the capital schemes identified in the LIP for Corridors and Neighbourhoods, £100,000 for Local LIP funding and £815,000 for Beddington North Major Scheme so that the projects can proceed. A sum of £169,000 for various revenue initiatives identified in the Corridors and Neighbourhoods programme (approved for 2019/20) and is included in the revenue estimates.
2.3Note the specific funding circumstances attached to the profiling of the Beddington Major Scheme, as set out in paragraph 3.12 and 6.2. Agenda Item 10 Page 2
2.4Authorise the Assistant Director Transport, Highways and Regulatory Services to take all necessary steps to implement the schemes, including commencing any necessary statutory consultations.
Background
3.1The LIP funding settlement reflects the amounts requested in the borough’s application to TfL under the specific funding stream for Corridors and Neighbourhood Schemes and Local Transport Funding, Principal Road Maintenance and Major Scheme award, and the level of funding for each stream is detailed in the report. Guidance on the allocations for Road Maintenance and Bridge Strengthening and Assessment is set out in paragraphs 3.16 and 3.17.
3.2TfL currently use a needs-based formulaic system to allocate funds to London boroughs to enable them to introduce highway improvements that are in line with the Mayor of London’s Transport Strategy (MTS). Boroughs are required to explain how they intend to do this through their LIPs, and set out in their LIP Delivery Plan what schemes will be introduced to achieve the MTS’s objectives.
3.3In May 2018, the Mayor of London published a new MTS covering the period to 2041, and a new document (LIP3) is required to set out how the borough will deliver the MTS outcomes over the life of that document. A draft LIP3 was endorsed by this committee on 20 September 2018, when delegated authority was also granted to the Director for EH&R to make non-material amendments post consultation in discussion with the Chair of this committee. The draft, with some minor amendments as discussed below, was submitted to TfL on 2 November 2018, and simultaneously published for statutory consultation until 21 December 2018.
3.4The consultation process included engagement with interested stakeholders such as the Emergency Services; disability groups; neighbouring local authorities; transport and environment groups and operators; business and community groups; and residents groups and assoications. A list of those groups can be found within the LIP3 at appendix A. At the same time a public consultation exercise was carried out between 2 November 2018 and 21 December 2018. The consultation appeared on the council’s website as well as the Citizenspace online consultation tool, and was available for any member of the public to respond.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.