Housing, Economy and Business Committee noted this item on Tuesday 8 October 2019. Below is the council's own wording, with the papers it was decided on.
· to note that the relevant condition (42), subject to which planning permission was granted in May 2014, does not require the restoration of the land until 2023. As a consequence, there can be no breach of planning control until the period ... view the full minutes text for item 16.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Beddington Farmlands ERF & Landfill – site restoration and related matters. September 2019 Beddington ERF
The testing and reliability phase of the ERF continues, and successful operational take-over has seen formal hand-over of large parts of the ERF to the Viridor operations team. Viridor is providing the residual waste treatment service to the South London Waste Partnership with the ERF running consistently. Viridor, in partnership with the SLWP, is working to help inform and educate residents about putting the ‘right stuff in the right bin’, to maximise recycling and to avoid the wrong materials being sent to the ERF. The Virtual Visitor Centre, www.beddingtonerf.info, continues to host emissions monitoring data and has received >2000 visitors since April.
The administration building is nearing completion, and this will align with the education centre being available to host visits. Viridor’s education officer is working with the SLWP to develop a programme of visits focusing on schools and community groups in the immediate vicinity of the facility. The image right features the nearly completed administration building and installed electric charging points.
Swift boxes have now been installed to the Beddington ERF external cladding, these overlook the brown roof of the administration building. Viridor has committed to the Conservation and Access Management Committee – once its construction partners depart the site, that it will explore installing a barn owl nesting box in a secure location. A rainwater harvesting system is operational for flushing toilets in the administration building.
Viridor continues to meet regularly with the London Borough of Sutton planning department around ERF matters to ensure adherence to planning requirements.
Beddington Farmlands
Restoration work continues across the Beddington Farmlands with capping work to the closed landfill cells across the centre of the site continuing ahead of schedule (pictured right). The clay capping material has been recovered from stockpiles across the Beddington site, reducing the requirement to import material.
The area of capping completed to date is 56,350m2. This leaves circa 7,000m2 to be completed later in the year, and is on schedule. The remaining area is being left available for contingency tipping for any ERF maintenance outages (as agreed with LBS until 31st Dec 2019). Agenda Item 6 Page 20
BEDDINGTON BRIEFING
Viridor remains committed and confident that the Beddington restoration programme will be completed in accordance with its planning requirements by 2023, and will continue working with the London Borough of Sutton as this progresses. Viridor’s landfill restoration and aftercare teams have prioritised delivering and then supporting the habitats outlined in the Restoration Management Plan, allowing them to establish before focusing on broader access for the local community.
Over the summer Viridor has mobilised its specialist engineering team to lead the delivery of the Farmlands restoration project. This includes utilizing specialist contractors to deliver packages of work including the excavation of the wet grassland phases to the north and also finishing the capping to the landfill cells that have recently closed to active waste.
The wet grassland habitat to the north of the site, known as ‘south of pylons’ is progressing well with the first phase now excavated, the islets and gullies have been contoured and awaits seeding later in the year. One of the bird hides overlooks this habitat and herons have already been seen stalking in this area. The second phase (the area next to the first phase and running up to the ERF construction car park, known as ‘north of pylons’) is now undergoing its bulk excavation. The material is being used for capping and engineering works on site. Once the ERF construction carpark is removed work will take place to excavate this area too.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.