Review and Establishment of the Design Review Panel
AgreedCommittee2 papers
Housing, Economy and Business Committee agreed this item on Tuesday 7 January 2020. Below is the council's own wording, with the papers it was decided on.
· To agree an extension of the existing Design Review Contract for six months in line with the terms of the contract; and · To agree that following the expiry of the current contract, officers commence procurement of an extended contract for a period of three years, subject to re-procurement.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1As part of the Ambitious for Sutton drive to improve the quality of the built and natural environment for all residents, this report sets out the outcome of the one year trial period, agreed at the Housing, Economy and Business Committee on 25 September 2018, for establishing a design review panel. Following a successful procurement process, a contract was awarded to Design South East (DSE), a not-for-profit organisation which provides independent advice to developers covering a wide range of design issues. The panel advising on each case is drawn from a highly experienced cohort of professionals from the field of architecture, urban design, landscape design, sustainability and transport.
1.2Since their formal appointment on 11 December 2018, DSE has provided independent advice on 11 schemes, including major mixed use developments in taller buildings in Sutton Town Centre, major mixed use schemes in Carshalton, and two proposals for schools. It is considered that DSE comments have been of significant value, enabling the Local Planning Authority to support high quality design in appropriate locations, while resisting poor quality development. This benefits the good place making principles set out in the Development Plan. Agenda Item 13 Page 346
Recommendations
2.1To agree an extension of the existing Design Review Contract for six months in line with the terms of the contract
2.2To agree that following the expiry of the current contract, officers commence procurement of an extended contract for a period of 3 years, subject to re-procurement
Background
3.1The Council has an ambitious approach to growth, and a vision for its delivery as set out within the Sutton Town Centre Masterplan and the London Cancer Hub Development Framework, all of which are embedded within Council policy as set out in the Local Plan adopted in February 2018. To preserve Sutton’s open spaces and suburban heartlands creates challenges to deliver the majority of our housing, employment and infrastructure needs within the town and district centres. A significant part of this challenge is to bring forward higher density development on relatively small sites whilst delivering high quality design. This requires greater challenge to the developer to come forward with policy compliant schemes of high design quality to enhance Sutton as a place to live, work and visit. There has been widespread acknowledgement that Local Authorities should use a variety of means to enhance the quality of its built and natural environment and one such tool is the use of Design Review Panels
3.2Design review is a process of independent, expert design advice provided by a multi-disciplinary and expert panel during the pre-application process. It benefits the applicant and the planning authority by providing an objective and clear assessment of the design merits of a development proposal, and offering constructive and considered recommendations.
3.3For many local authorities design review has become an integral part of the development management process in planning. It is identified in the National Planning Policy Framework as a key tool for local planning authorities to ensure design quality. Paragraph 62 of the NPPF states:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.