To note the Management Agreement performance for the period 1 April 2019 to 31 January 2020, attached at Appendix A, for information, 2. To note the Interim Accounts for the year ending 31 March 2020, attached at Appendix B, for information, 3. To authorise the Treasurer to sign the Rent Review Memorandum to acknowledge and accept the revised rent level payable from 21July 2015, and 4. To delegate the future signing of such Rent Review Memorandum documents to the Treasurer where amounts requested are calculated in line with the provisions contained within the lease and can be met from approved budget estimates.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report is to provide an update to the Board on the performance against the Management Agreement Annual Budget as approved in December 2019 and to provide an update to the Board on the latest Interim Accounts for the 2019/20 financial year and an estimate of the closing year-end balance.
1.2The report also includes information on the lease agreement between the Board and Wandsworth Borough Council in respect of the ongoing arrangements relating to the office premises within the crematorium grounds and seeks approval to sign the Rent Review Memorandum and delegate the future signing of such documents to the Treasurer.
Recommendations
2.1To note the Management Agreement performance for the period 1 April 2019 to 31 January 2020, attached at Appendix A, for information,
2.2To note the Interim Accounts for the year ending 31 March 2020, attached at Appendix B, for information,
2.3To authorise the Treasurer to sign the Rent Review Memorandum to acknowledge and accept the revised rent level payable from 21 July 2015, and
2.4To delegate the future signing of such Rent Review Memorandum documents to the Treasurer where amounts requested are calculated in line with the provisions contained within the lease and can be met from approved budget estimates.
Page 1 of 5 Agenda Item 5 Page 28
3. Background / Update
Management Agreement performance 1 April 2019 to 31 January 2020
3.1Transactions incurred under the Management Agreement are reflected in Appendix A attached and are compared with the Management Agreement Annual Budget approved by the Board in December 2019.
3.2These figures include costs incurred by Enable and invoiced to the Board for the period from 1 April 2019 to 31 January 2020.
3.3Total costs reimbursed by the Board to Enable to the period ending 31 January 2020 (10 months of the year) amount to £354,651 against budgeted expenditure of £466,200 (76% of the total annual budget after 83% of the year) which indicates that there might be a small underspend come year end. Total estimated full year costs of £435,000 have been included in the wider Interim Accounts forecast referred to in 3.2 below.
3.4In summary, Cost of Sales is marginally lower than could be expected with a uniform expenditure profile (75% of the total budget after 83% of the year) which is again mirrored within Administrative Costs (76% of the total budget after 83% of the year). This reflects the lower than expected activity level as referenced in the Surveyor’s report elsewhere on this agenda.
3.5Within Cost of Sales the actual costs incurred, when compared to approved budgets, show varying individual variances reflecting the current demand level for products within the range of memorials offered and reflect the market cost of the materials for the chosen options.
3.6Within Administrative Costs, Salaries are marginally underspent compared to the approved budgeted levels (79% of the total budget after 83% of the year) reflecting vacancy levels seen throughout the year to date and an ongoing reduction in overtime costs. The Energy Costs – Gas & Other budget is showing an underspend (60% of the total budget after 83% of the year) but this is likely to be due to the timing of the billing from the main gas supplier as the budget was significantly reduced as part of the budget setting exercise in December 2019 from £60,800 to £33,000 per annum to reflect current estimates rather than lower usage. Medical Reference Fees are showing an underspend (68% of the total budget after 83% of the year) which is due to profiling of the budget as the fees are paid quarterly in arrears but also again reflects the lower than expected demand in the year to date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.