London Borough of Sutton
Audit and Governance Committee, Thursday 18 June 2020 at 7.00pm

Review of the Procurement of Main Contractors for Major Construction Projects

Decided Finance 1 paper

Audit and Governance Committee decided this item on Thursday 18 June 2020. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

that the council will continue the current ‘best fit’ approach, of choosing the optimum procurement route to suit each particular project. the council will consider an additional option of setting up a regional contractors framework again in 12 to 18 months, when the legislative and business context has stabilised post-Brexit and a report will be referred to the Strategy and Resources Committee for consideration.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

1.1A review of how the council currently procures major construction projects and whether there are other effective options that should also be considered.

Recommendations

2.1To note that following this review the council will​ ​continue the current ‘best fit’ approach, of choosing the optimum procurement route to suit each particular project.

2.2To note that the council​ ​will consider an additional option of setting up a regional contractors framework again in 12 to 18 months, when the legislative and business context has stabilised post-Brexit. This report will be referred to the Strategy and Resources Committee for consideration.

Background

3.1Following discussion at the Audit and Governance Committee in October 2019 covering an audit report relating to Hackbridge Primary School construction works, the Committee asked for a paper to be brought back on the use of Construction / Contractor Frameworks and available options going forward.

3.2Sutton set up a contractor framework based on use of the PPC2000 partnering contract (2009 - 2015), in conjunction with L B Merton. The call-off method was to select the most suitable Agenda Item 7 Page 32

contractor from the ‘panel’, applying their pre-tendered preliminaries, profit and overheads rates in an open-book partnering procurement process. This framework offered good value for money and fast contractor engagement to meet client timetables, and produced some notable projects for Sutton - eg Westcroft Leisure Centre; Middleton Circle Library, Whitehall Museum, in addition to many school expansions.

3.3In 2014, the council decided to participate in setting up the London Construction Programme Major Works framework, to influence its design to suit Sutton (however in the event the scale and universality of Haringey’s ambition resulted in an unwieldy system). Sutton used the LCP MW2014 framework for major projects (£9M and £38M; single-stage and two-stage respectively) and smaller projects (under £1M). Sutton have continued to use the replacement LCP framework - MW2019, which is only applicable to projects over £1M.

3.4Programme & Project Management (P&PM) experienced a long period from around 2008 during which the majority of projects were school expansions, plus other new-build and major refurbishment projects. The school expansion programme came to an end in 2019, and the current range of projects is more diverse, including new-build social housing, landscaping, infrastructure and urban/commercial regeneration.

4. Issues

4.1P&PM have experienced some problems with framework contractor procurement using LCP MW2014.

● One problem was that procedures obliged us to appoint the most competitively priced contractor in the appropriate Lot, despite having direct poor experience of this contractor. In the event this contractor failed and the contract had to be terminated, requiring significant additional funding to complete the project. While the council criticised LCP for not maintaining regular financial checks on the framework contractor it is not clear that later financial checks would have given us grounds for refusing to appoint them, as they continued to post good results. ● Another problem was a very poor level of interest from framework contractors to a recent tender enquiry for a £10M multi-site housing project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(7) Review of the procurement of main contractors for major construction projectsReport 161 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
SW
Councillor Sam WeatherlakeChair, present
DH
Councillor David HicksVice-Chair, present
RC
Councillor Richard CliftonCommittee Member, present
AM
Councillor Ali MirhashemCommittee Member, present
NP
Councillor Nali PatelCommittee Member, present
MS
Councillor Muhammad SadiqCommittee Member, present
CS
Councillor Colin StearsCommittee Member, present
JM
Councillor James McDermott-HillCommittee Member, present
PN
Councillor Param NandhaCommittee Member, present
NM
Councillor Nick MatteyCommittee Member, present
DP
David ParrettEx Officio, present
NA
Neil AstenEx Officio, present

All 13 on the meeting page

On this subject at Sutton

Search all
  1. Review of the Procurement of Main Contractors for Major Construction ProjectsThis decision
  2. A review of Council procurement spending and its impact on small and medium enterprisesDecided
  3. Medium Term Review Group on Procurement and CommissioningAgreed

More from Sutton Audit and Governance Committee

All decisions
MeetingDecisionOutcome
15 Jan 2026 Minutes of the previous meetingthat the minutes of the meeting held on 23 October 2025 be agreed as an accurate record. The independent member (Audi... Agreed Open
15 Jan 2026 2024/25 Final Accounts and AuditTo note the 2024/25 Independent Auditors Report (Appendix A), 2024/25 Year End Report (Appendix B) and the 2024/25 Le... Noted Open
15 Jan 2026 Internal Audit Progress ReportTo note the Internal Audit progress report. Noted Open
15 Jan 2026 Operation of the Code of ConductTo note the action taken by the Monitoring Officer in relation to code of conduct complaints. To agree that the Chair... Noted Open
15 Jan 2026 Member Development UpdateTo note the Member Development programme update. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies