Resolved
- 1 To note the progress being made to minimise the impact of COVID-19 on the leisure contract. 2 To note the Council’s continued financial support for SLM, the leisure provider, up to the end of the financial year 2021/22.
Environment and Sustainable Transport Committee noted this item on Thursday 24 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
- 1 To note the progress being made to minimise the impact of COVID-19 on the leisure contract. 2 To note the Council’s continued financial support for SLM, the leisure provider, up to the end of the financial year 2021/22.
1.1This report details the impact of COVID-19 on the Council’s leisure provision, services which, in line with the Council’s priorities set out in Ambitious for Sutton, have played an important role in supporting residents to be active citizens.
2 Recommendation(s)
2.1To note the progress being made to minimise the impact of COVID-19 on the leisure contract.
2.2To note the Council’s continued financial support for SLM, the leisure provider, up to the end of the financial year 2021/22.
Report Page 1 Agenda Item 9 Page 12 Leisure Centre Contract - COVID-19 Indicative Timing: 20 minutes
3 Background and Key Information
3.1The Council entered into a 15 year contract with Sports and Leisure Management Ltd (SLM) in 2011, to provide non-statutory leisure services within the Borough. The Council’s four leisure centres have helped the Council to achieve the priority of supporting residents to be physically active. Additionally, the contract provides a net income to the Council.
3.2SLM manages and runs the Council’s four leisure centres: Westcroft Leisure Centre; Cheam Leisure Centre; David Weir Leisure Centre and the Phoenix Centre.
3.3During May 2020 SLM provided the Council with information setting out the impact of COVID-19 on their business, the financial support they were accessing and the operational measures they were taking to reduce costs.
3.4On 23 March 2020 England entered a national lockdown due to COVID-19 . The Government required all leisure centres to close, which constituted a change in law. Every local authority and every leisure provider faced the same situation. Essentially, leisure services had no option but to close down and those Councils that commissioned providers had to provide support to enable them to sustain their business during lockdown. The Council took the decision to temporarily take back responsibility for all four leisure centres in Sutton and to cover the costs associated with the sites, as part of the Council’s emergency response. This approach minimised the financial impact of the closure of the leisure centres both for the Council and for SLM.
3.5In July 2020 the Council agreed a deed of variation to the leisure contract to run from 1 July 2020 to 30 September 2020. This variation was agreed via a Delegated Decision Notice agreed on 17 July 2020. The aim of the variation was to ensure continuity of service, due to the serious impact COVID-19 would have on SLM’s potential to derive income from the leisure centres to and in order to meet their costs on reopening, on 25 July 2020.
3.6SLM provided a financial forecast of the impact of COVID-19 on their business for 2020/21, based on a breakeven position. This forecast was based on industry agreed forecasts for the return of members to leisure services. It took into account the reduced capacity due to social distancing requirements and the number of activities that SLM could deliver, in complying with government guidance. The Council capped its liability at 5% above these forecasts and an Open Book accounting approach was agreed, as recommended by the Government. Local authorities and leisure providers nationally took the same approach.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Leisure Centre Contract: Covid 19_ E&ST Committee _ 20210624Report | 169 KB | DownloadRead as text |
Follow Environment and Sustainable Transport Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 5 March 2026 be agreed as an accurate record. | Agreed | Open |
| 25 Jun 2026 | Environment and Sustainable Transport Committee: Policy and Strategy OverviewTo note the role and remit of the Environment and Sustainable Transport (E&ST) Committee as set out in the report. | Noted | Open |
| 25 Jun 2026 | Report on Petition to Extend Controlled Parking Hours on Grove Road (SM1) near Sutton High to 7:30 AM – 8:30 PM, Monday to FridayTo note the petition. 2. To approve a review of the parking arrangements currently in place giving due consideration ... | Noted | Open |
| 25 Jun 2026 | Report on Petition for a Pedestrian/Zebra Crossing in Thornton RoadTo note the petition. 2. To agree that a feasibility investigation is carried out on the proposal requested and the f... | Noted | Open |
| 25 Jun 2026 | Sutton Town Centre Public Realm and Placemaking PlanTo adopt the Sutton Town Centre Public Realm and Placemaking Plan as the Council’s strategic framework for guiding fu... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.