RESOLVED : 1. To note the measures in place and steps being taken to mitigate the cyber security risks to the Council. 2. To note that despite the measures set out in this paper it is impossible to fully mitigate the risk of a disruptive cyber attack on the Council given the evolving nature of the threat. Therefore, being prepared to manage and recover from an attack is a vital part of the risk mitigation.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1The Corporate risk register holds two risks that relate to cyber security. The first is CORP RR 07 Risk of Technology Failure and CORP RR 08 Breach of Information Governance or security.
1.2The paper sets out how the cyber security risks are managed. The paper provides an overview of the mitigations in place in respect to technology, policy and procedures and staff.
2 Recommendation(s)
2.1To note the measures in place and steps being taken to mitigate the cyber security risks to the Council.
2.2To note that despite the measures set out in this paper it is impossible to fully mitigate the risk of a disruptive cyber attack on the Council given the evolving nature of the threat. Therefore being prepared to manage and recover from an attack is a vital part of the risk mitigation.
3.1Cyber Security risks continue to evolve and grow and it is critical to the delivery of Council services in our communities that this risk is actively managed. The threat of an attack is high and malicious activity and code are in constant circulation and ever changing. The Council intercepts and blocks malicious activity everyday. Over recent months there have been a number of high profile cyber incidents that have been widely reported in the media, ranging from Manchester United through to an attack a lot closer to home in Hackney Council.
3.2The highly disruptive attack on Hackney Council in October 2020 has been reported as an example of a ransomware attack. This type of attack is increasingly common. Ransomware is malicious code that encrypts data making it unusable. The attacker will then offer the decryption keys for a ransom. This type of attack is increasingly common and highly disruptive.
3.3Recovering from an attack of this nature is complex and time consuming. To reduce further damage you need to effectively shut down your IT network and services. For systems that have been impacted by the ransomware they then need to be rebuilt from scratch using backups. This can take weeks. In some cases if the backups have been impacted or a system is not backed up it can be impossible to restore the service. In Hackney work continues 8 months after the attack to recover services, and this work will continue for some time. The impact of the attack has been felt across the Council.
3.4Cyber Security has been and continues to be a priority for the Digital and IT Shared Service. This paper sets out how Cyber Security risks are managed. It will cover: 3.4.1 Governance 3.4.2 Policy and procedure 3.4.3 Technology 3.4.4 Staff
3.5Governance: The Digital and IT Security Board, chaired by the AD for Digital and IT meets monthly to review the overall cyber security position. This Board is the operational Board overseeing the evolving risk position and the policies and procedures including the Acceptable Use Policy for all users of the Council’s IT services. The Security Board reports into the Information Security and Governance Board chaired by the Council’s Senior Information Risk Owner (SIRO), the Strategic Director of Resources.
3.6The Council has clearly defined roles managing the cyber risks. These include the Data Protection Officer, a technical Cyber team and an independent Cyber security expert and assessor who works with the Digital and IT Team and is part of the Digital and IT Security Board. This role provides expert advice and independent assessment of risk. The Council
Minutes of the previous meetingthat the minutes of the meeting held on 23 October 2025 be agreed as an accurate record. The independent member (Audi...
2024/25 Final Accounts and AuditTo note the 2024/25 Independent Auditors Report (Appendix A), 2024/25 Year End Report (Appendix B) and the 2024/25 Le...
Operation of the Code of ConductTo note the action taken by the Monitoring Officer in relation to code of conduct complaints. To agree that the Chair...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.