North East Surrey Crematorium Board agreed this item on Tuesday 7 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved that: 1. the Management Agreement performance for the period 1 April 2021 to 31 March 2022, attached at Appendix A of the report be noted. 2. the Interim Accounts for the period 1 April 2021 to 31 March 2022, attached at Appendix B of the report be noted.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1This report is to provide an update to the Board on the performance against the Management Agreement Annual Budget as approved in December 2020 and to provide an update to the Board on the latest Interim Accounts.
Recommendations
The North East Surrey Crematorium Board is recommended to:
2.1Note the Management Agreement performance for the period 1 April 2021 to 31 March 2022, attached at Appendix A, for information.
2.2Note the Interim Accounts for the period 1 April 2021 to 31 March 2022, attached at Appendix B, for information.
3. Background / Update
3.1Management Agreement performance 1 April 2021 to 31 March 2022
3.3Transactions incurred under the Management Agreement are reflected in Appendix A attached and are compared with the Annual Budget approved by the Board in December 2020.
3.4These figures include costs incurred by Enable and invoiced to the Board for the period from 1 April 2021 to 31 July 2021 and costs incurred by Wandsworth Borough Council and recharged to the Board for the same period. Repairs costs have been extracted and are reported separately as part of the Surveyor’s report so not to distort the reported position.
3.5Overall, expenditure is broadly in line with approved budget. After 4 months of the year (33% of the year) expenditure stands at 33% of the total budget which demonstrates that there continues to be a good level of underlying cost control within the services delivered under the Management Agreement by operational staff. Agenda Item 6 Page 24
3.6Cost of Sales would appear to be overspent (53% of the total budget) but this is largely due to the annual cost of the Wesley Sound system which is paid early within the financial year.
3.7As experienced in recent years all energy costs, gas, electricity and now water, continue to be difficult to estimate with any accuracy. Previous changes to the Leisure and Cultural contract between Enable and Wandsworth Borough Council has passed the responsibility for energy usage for both gas and electricity monitoring and invoice verification back to the Council’s Energy Management Unit. This is to assist with aligning to the Council’s Environment and Sustainability Strategy and wider zero carbon initiatives which will be of benefit to the Board in the longer term as gas and electric are purchased as part of a Council wide procurement exercise and are therefore subject to economies of scale with the potential to move to greener energy sources. 3.8 It will be noted that the metered water budget is significantly underspent which is due to a backdated credit being applied to the bill by the supplier. The sharing of water costs within the crematorium grounds between the Board and Wandsworth Borough Council (for the cemetery areas) has been reviewed with revised arrangements now in place to split costs on an 80/20 basis (80% to the Board). 3.9 Costs incurred under the Management Agreement will continue to be reviewed on a regular basis with supporting documentation requested where expenditure is outside of expectations. Once transactions are confirmed, payments are made to Enable to reimburse the costs. Similar verification processes are in place for costs incurred by Wandsworth Borough Council and recharged to the Board.
3.10Interim Accounts for the period 1 April 2021 to 31 March 2022
3.11Appendix B attached shows transactions to date against the estimates approved by the Board in December 2020. It shows the actual income and expenditure incurred to date and a forecast for the full year.
Significant areas are as follows: -
● (Line 3) - Shows the progress on the maintenance of buildings and plant is the subject of the Surveyor's report elsewhere on this agenda. This area is forecast to be in line with budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.