To note the findings and implementation of the recommendations of the review. 2. To agree that officers will review member involvement in the governance arrangements for capital projects, and report back to a future meeting of the committee.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1The capital programme is key to delivering the Council’s priorities across the borough. Each year the capital programme spends in the range of £50m to £100m; it is therefore essential that there is proportionate, but effective governance and controls around the programme.
1.2Following the overspend on Beddington Lane capital programme and the subsequent internal audit, a review of the governance and controls of all capital programmes over £1m has been carried out.
1.3The review found that in general there was good governance and controls across the capital programme, although there were inconsistencies in how projects were agreed, overseen and delivered that needed to be addressed. This report provides an overview of the findings and outcomes of the review.
2 Recommendation(s)
2.1To note the findings and implementation of the recommendations of the review.
Report Page 1 Agenda Item 6 Page 2 Review of Governance Arrangements for Capital Projects
3 Background and Key Information
3.1PURPOSE OF THE REVIEW
In December 2020, the Programme Management Office (PMO) and Finance undertook a review of governance arrangements and financial controls on capital projects over a value of £1m. This review was prompted by the overspend on Beddington Lane capital programme and the subsequent internal audit review.
The purpose of this review was to understand governance arrangements and financial controls for other capital projects and to make recommendations accordingly.
All Sutton Council projects are expected to have appropriate, proportionate and robust governance arrangements in place from the outset of the project. Project governance arrangements should provide the Senior Responsible Officer (SRO), project manager, team and stakeholders with the structure, processes, decision-making models and tools to manage and provide oversight of the project effectively while supporting and controlling delivery across the life cycle of the project.
For all projects, it is expected that governance arrangements for the project have:
● A clear mandate and purpose ● Transparency of control and decision making ● Clear accountability of responsibilities ● A meaningful audit trail ● Rigorous risk and issue management
The projects within scope of the review were:
● Mandatory Disabled Facilities Grant ● Secondary Expansions ● Digital IT Programme ● Town Centre Masterplan Delivery ● Future High Streets Fund ● Sutton Works ● London Cancer Hub - Sutton Hospital Site ● Travellers Site (The Pastures) ● Phase 2 Housing ● Property Acquisitions ● HRA - programme management
Report Page 2 Page 3 Agenda Item 6 Review of Governance Arrangements for Capital Projects
The methodology used to undertake the review was as follows:
An initial information gathering meeting was organised between the PMO and the capital project lead to cover these four questions:
● Is there a clear project plan and milestones? ● Is there a Project Board/team meeting so issues can be raised? ● Is there clarity on roles and responsibilities? ● Is there detailed financial information held on commitments and forecasting?
During this meeting, capital project leads were also asked to share key documentation relating to the reporting and management of their project. The PMO also met with colleagues in Finance to discuss arrangements for financial reporting and management for capital projects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingthat the minutes of the meeting held on 23 October 2025 be agreed as an accurate record. The independent member (Audi...
2024/25 Final Accounts and AuditTo note the 2024/25 Independent Auditors Report (Appendix A), 2024/25 Year End Report (Appendix B) and the 2024/25 Le...
Operation of the Code of ConductTo note the action taken by the Monitoring Officer in relation to code of conduct complaints. To agree that the Chair...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.