Resolved
Resolved that: 1. The update on the Beech Tree Place Redevelopment scheme be noted.
Housing, Economy and Business Committee noted this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1. The update on the Beech Tree Place Redevelopment scheme be noted.
1.1The Ambitious for Sutton plan’s priorities include keeping residents safe, living well independently and being active citizens to enable Sutton to continue to be a great place to live, work and raise a family. The Council is committed to delivering these by maintaining and improving the physical environment and through the regeneration of its council estates to provide better homes and places for existing residents and Sutton’s growing community. The regeneration of Beech Tree Place is being delivered in accordance with these aims and priorities.
1.2The full redevelopment of Beech Tree Place is being undertaken because the existing accommodation does not meet national standards for older persons housing. The regeneration of the estate will deliver much needed new and affordable homes, that are built to a high quality, are larger, more accessible and energy efficient. As an allocated site in the Sutton Local Plan 2016 (STC11), Beech Tree Place will also contribute to the regeneration of Sutton Town Centre
1.3This report presents an update on the scheme to the Committee and outlines the next steps in the scheme progress.
Report Page 1 Agenda Item 14 Page 264 Beech Tree Place: Scheme Update
2 Recommendation(s)
2.1To note the update on the Beech Tree Place Redevelopment scheme.
3 Background and Key Information
3.1The Housing, Economy and Business (HEB) Committee on 15 June 2021 approved the redevelopment of Beech Tree Place (Appendix A). The approval was based on an estimated capital budget of £30m, but full details of the scheme had not been finalised at that time. The approval was for a notional scheme that was still subject to detailed design, statutory planning process and competitive tender returns.
3.2Following the return of tenders, the estimated budget for the scheme had increased significantly but could not be reported back to this meeting of the HEB committee for consideration because of time constraints attached to the GLA grant funding and contractor tendered prices. The Council therefore held an Urgency Committee on 25 August 2022, which considered a report (Appendix B) seeking approval to increase the budget to £44.2m, whilst seeking to further reduce costs through value engineering with the contractor and to seek additional grant funding from the GLA.
3.3The Urgency Committee on 25 August 2022 approved the recommendations. It also resolved that there should be a report on progress to the next meeting of the Housing, Economy and Business Committee and that the impact on the Housing Revenue Account Business plan should be considered.
3.4Since the decision of the Urgency Committee, the following progress has been made on the project:
3.4.1 Land assembly: The two privately owned properties on the site (Nos 33 and 35 West Street) have been acquired through private treaty negotiations. This completes the land assembly of the site.
3.4.2 Contract award: REAL LSE limited has been appointed as the contractor for the scheme. A building contract has been awarded.
3.4.3 GLA start on site: The contractor has commenced enabling works. This has enabled the Council to fulfil its commitment to the GLA to start on site by 30th September 2022, which has now been achieved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(13) Beech Tree Place_ Scheme Update: HEB Update ReportReport | 181 KB | DownloadRead as text |
PDF |
(13a) HEB BEECH TREE 15 JUNE 2021Report | 237 KB | Download |
PDF |
(13b) Beech Tree Place: Capital Budget Changes: URGENCY CommitteeReport | 317 KB | Download |
PDF |
(13biii) Urgency app C 20201013RFutureofBeechTreePlaceHEBCommitteeAppendix | 280 KB | Download |
Follow Housing, Economy and Business Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Minutes of the previous meetingthat the minutes of the meeting held on 9 June 2026 be agreed as an accurate record. | Agreed | Open |
| 15 Sep 2026 | Biannual Performance MonitoringThe Housing, Economy and Business Committee biannual performance monitoring report be noted | Noted | Open |
| 15 Sep 2026 | SHP Delivery Plan 26/27 UpdateSutton Housing Partnership’s Delivery Plan update, which includes the Service Improvement Plan 2026/27 and Performanc... | Approved | Open |
| 15 Sep 2026 | Beddington Farmlands UpdateThe progress made on the site over the last nine months be noted 2. The Breach of Condition Notice issued (5 Septembe... | Noted | Open |
| 9 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 14 January 2026 be agreed as an accurate record . | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.