It was agreed that this would be followed up outside of the meeting. Members of the committee requested more information on the Levelling Up Fund project. It was agreed that this would be followed up outside of the meeting. Members of the committee questioned why there were no planned maintenance footway/carriageway schemes in the local committee area. It was agreed that this would be followed up outside of the meeting. Members discussed their concerns over the use of electric vehicle charging points by non-electric vehicles as parking spaces. Members of the committee requested information on how other London boroughs have tackled these challenges.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Sutton South, Cheam and Belmont Local Committee
Sutton South, Cheam and Belmont Local Committee 5 October 2023
Page 1 Highways and Transport - Programme update for 2023/24 and 2024/25
Agenda Item 7 Agenda Item 7 BACKGROUND In this presentation we will cover the following programmes of work and provide an update on petitions linked to those schemes: TfL funded programmes - LIP, Cycling and Walking, and Bus Priority schemes
Page 2 Petition items - HGVs in Crossways and HGV/traffic calling issues in Lumley Road area Levelling Up Fund - associated Cycling and Walking work; Drainage issues Footway and Carriageway Maintenance LED and Column Replacement Parking Strategy EV strategy and infrastructure delivery TfL Programmes 2023/24 - Update ● Cotswold Road/Downs Road - Improve safety at this junction. Informal consultation programmed to start in October 2023. ● Church Hill Road/Lumley Road area wide investigations - Allocation of £50k in 2023/24 to support the data collection, feasibility work. The project covers a significant area, so extensive surveys required to establish baseline data - due to be completed in October. Feasibility work considering a range of issues has commenced, which includes looking at HGV through traffic across the wider
Page 3 area, and specific issues relating to existing traffic calming in the Lumley Road area. Informal consultations planned for Nov/Dec 2023 ● Brighton Road/Langley Park Road/Crossways area - Allocation of £50k to investigate and deliver improved pedestrian facilities and consider cycling and safety scheme. Also consider issues of
Agenda Item 7 coach/hgv traffic - see next slide. ● Sandy Lane area - 20mph scheme. Data collection completed and consultation planned Oct/Nov ‘23 ● Downs Road - Bus stop accessibility (opp Royal Marsden) - design layout being drawn up. Agenda Item 7 TfL Programmes 2024/25 An indicative 2024/2025 programme was approved by the Environment and Sustainable Transport Committee in December 2022. The Borough 24/25 programme consists primarily of the delivery of two year schemes that started this year 23/24, and as such there are no new schemes proposed in your local committee area for 2024/25, with the key focus being on completing the development of the current list
Page 4 on the previous slide, through public and statutory Traffic Management Order (TMO) processes where required for legislation to be in place for measures such as 20mph speed limit changes.
The standard process is for schemes to go through informal consultation on the concept proposals, which are reviewed and agreed with ward councillors prior to any consultation starting. The results are then reviewed and any required changes made after discussions with ward councillors, before progressing to design and delivery stage.
There is a further round of formal consultation, which may include TMOs, and the results of this feedback are reviewed with ward councillors before the schemes are delivered on the ground. Petitions/other issues The HGV and 60 Seat Coach Ban on Crossways, The Gallop and Downsway petition - As previously to this Committee, officers will consider this petition as part of the TfL funded project that was discussed on the previous slide. It was originally anticipated that this work would start early in 2023, however delivery issues with other already committed schemes on the programme have meant the scheme was reprogrammed, as highlighted earlier, at the start of the 2023/24.
Page 5 HGVs on Lumley Road - The HGV concerns and effectiveness of the existing traffic calming features are being investigated as part of the wider area scheme discussed on the previous slide and included in the 2023/24 programme. Data collection is being arranged, as part of the wider scheme,to understand scale of HGV intrusion. These investigations are also assessing the
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Sutton South, Cheam and Belmont Local Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingthat the minutes of the meeting held on 5 February 2026 be agreed as an accurate record. On behalf of the Committee, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.