Elm Grove Regeneration Developer Partner Procurement Outcome and Award
AgreedCommittee1 paper
Housing, Economy and Business Committee agreed this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.
To appoint Bidder C (refer to Executive Summary of exempt appendix A for bidder name) as the Council’s preferred bidder (development partner) for the Elm Grove regeneration and to enter into the preferred bidder stage of the competition, as provided for in the procurement process. 2. The Council enters into a contract with the preferred bidder through a Development Agreement, with the final terms of the Development Agreement to be agreed by the Strategic Director of Resources under delegated authority, with the proviso that should the proposed Development Agreement require any significant changes, the matter will be referred back to Committee be agreed. 3. To authorise the Strategic Director of Resources to enter into any ancillary contracts and agreements which may be necessary to deliver the above recommendations, within the scheme budget.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
1.1The Council is progressing the regeneration of Elm Grove to deliver on the Ambitious for Sutton Corporate Plan priority to provide quality and affordable housing. The regeneration of Elm Grove will also contribute to the Council’s ambitions to take action on climate change, create inclusive places for everyone and enable strong and fair economic growth in Sutton.
1.2To deliver the new homes and improvements to the area, the Council has sought to secure the services of a private sector development partner with the right level of skill, resource, experience and expertise to deliver what is a complex and multifaceted estate regeneration project. To facilitate this, the Council has undertaken a comprehensive partner procurement exercise, which has resulted in the selection of a preferred bidder for the scheme.
1.3This report provides a summary and the outcome of the procurement process. It also seeks approval to appoint the preferred bidder and to progress the necessary legal documentation through the preferred bidder stage into contract through a Development
Report Page 1 Agenda Item 12 Page 80 Elm Grove Regeneration Developer Partner Procurement Outcome and Award
Agreement. More details about the procurement process are contained in the Tender Report at exempt Appendix A and a summary of the legal documentation is contained in exempt Appendix B.
Recommendations
2.1To appoint Bidder C (refer to Executive Summary of exempt appendix A for bidder name) as the Council’s preferred bidder (development partner) for the Elm Grove regeneration and to enter into the preferred bidder stage of the competition, as provided for in the procurement process.
2.2To agree the Council enters into a contract with the preferred bidder through a Development Agreement, with the final terms of the Development Agreement to be agreed by the Strategic Director of Resources under delegated authority, with the proviso that should the proposed Development Agreement require any significant changes, the matter will be referred back to Committee.
2.3To authorise the Strategic Director of Resources to enter into any ancillary contracts and agreements which may be necessary to deliver the above recommendations, within the scheme budget.
3 Background and Key Information
3.1The regeneration of Elm Grove will see the creation of circa 290 new high quality homes incorporating Passivhaus sustainable principles. 50% of the homes will be affordable, including new homes for existing residents. The regeneration will also introduce new amenity space with access to play space on-site, alongside public realm improvements, including direct connections to Throwley Way and the High Street.
3.2The project is a strategic priority and part of the Council’s ambitions for Sutton town centre. The plans for Elm Grove have been subject to extensive consultation, and received the endorsement of residents through a ‘Yes’ vote in Sutton's first estate ballot in 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.