Housing, Economy and Business Committee noted this item on Tuesday 11 March 2025. Below is the council's own wording, with the papers it was decided on.
To note the latest update on the status of the restoration. 2. To take all necessary steps to secure the sum held by Valencia Waste Management in a cash collateral trust in lieu of a Bond to enable the Council to commence direct action to progress the (approved) restoration if required. 3. To review enforcement options in the light of the decision on the amended planning application by Planning Committee, including the option of drawing down from the sum held in lieu of the bond to complete the current restoration plan, should planning permission for the amended plan not be granted. 4. To reverse the decision to enter into an operating lease with Sutton Living Limited (SLL) and retain the homes as temporary accommodation in the HRA.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report Author ndy Webber, Head of Development Management and Strategic A Planning
Ward Affected Beddington
mbitious for Sutton A A ction on Climate Change priorities An Inclusive Place for Everyone
Open/Exempt Open
Signed Date 27 February 2025
1 Summary
1.1 The delivery of the restoration of Beddington Farmlands forms part of the Council’s Corporate Plan, and supports the Ambitious for Sutton plan priorities of taking Action on Climate Change and being An Inclusive Place for Everyone. The restoration, from its use as a landfill site to an important high quality nature reserve was a condition attached to the planning permissions for the landfill operations and the adjacent Energy Recovery Facility (ERF).
1.2 The committee has received regular updates on the progress with the restoration and is aware that there has been significant delays in delivering the agreed restoration plan in accordance with the planning obligations of the site owners. At the HEB meeting on 26 November 2024, the committee was updated on the poor progress made by the site owners, Valencia Waste Management, to implement the restoration plan according to schedules of work agreed with the Council. The committee was also updated on progress with the site owners planning application to vary the approved restoration plan.
1.3 At the meeting there was considerable discussion concerning the Council’s options for ensuring that the work is completed without further delay, which included taking enforcement action to require the site owner to comply. Alternatively, the option of drawing down from a Bond was discussed. The Bond is held as insurance in the event of the site owner defaulting on their obligations in the legal agreement(s) attached to the relevant
lanning permission and allowing the Council to to take direct action and deliver the p habitats and ongoing management.
1.4 It was agreed that a further report be presented to the committee in March 2025 setting out further progress and next steps to be agreed.
2 Recommendations
2.1 To note the latest update on the status of the restoration.
2.2 To take all necessary steps to secure the sum held by Valencia Waste Management in a cash collateral trust in lieu of a Bond to enable the Council to commence direct action to progress the (approved) restoration if required.
2.3 To review enforcement options in the light of the decision on the amended planning application by Planning Committee, including the option of drawing down from the sum held in lieu of the bond to complete the current restoration plan, should planning permission for the amended plan not be granted.
2.4 To bring a further update report to the Committee in June 2025.
3 Background and Key Information
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.