Approved Committee 6 papers

AI summaryNorth East Surrey Crematorium Board approves quarterly management findings, proceeds with footpath and fountain designs, and commissions a solar panel feasibility study.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSurveyor's findings and three project proposals agreed
MoneyNot statedNo sums given in the report
What happens nextDesign and tenderingFootpath Option 1 and two fountain scope options
Who it affectsCrematorium visitors and operationsPathways, garden, and Remembrance Building

What was decided

The Board approved the Surveyor's findings on crematorium management for September to November 2025. Report 2.1

Members agreed to take forward Option 1 of the main drive pedestrian pathway project (CNS 004) for design, planning and tendering. Report 2.2, 6.1

Members agreed to develop both a full scope and a reduced scope design for the tree of life fountain (CNS 007), and to appoint an electrical consultant to assess solar panels on the Remembrance Building. Report 2.3, 2.4

Why

The Surveyor's quarterly review found buildings, grounds, paperwork, safety files and emissions records to be in good order, with no reportable accidents in the period. Report 4.3, 4.4, 4.5, 4.6, 4.7, 4.10, 4.11

Officers judged PV panels on the Remembrance Building to be the only suitable energy improvement after reviewing heating, cremators and the Lodge. Report P13, P14

The financial year 2025/26 cremation target has been cut to 1,700 to match the trend in the first seven months. Report 4.2

What happens next

The pathway project (CNS 004) needs an agreement between Wandsworth Council and NESC before the works can proceed. Report 6.1

A new full-time gardener is to be recruited from April 2026 to allow handover before a current gardener retires and moves to a 2.5 day week pattern from October 2025. Report 4.13

Project updates are tracked in Appendix C and an Action Plan is in Appendix B; a Heat Decarbonisation Plan for Morden Cemetery is in Appendix D. Report 3.2, 4.14, 4.15, P48, P49, P50

Options considered

  • Chosen: Option 1 of main drive pedestrian pathway (CNS 004). Selected for design, planning and tendering Report 2.2
  • Chosen: Full scope design for tree of life fountain (CNS 007). To proceed alongside a reduced scope option Report 2.3
  • Chosen: Reduced scope design for tree of life fountain (CNS 007). To proceed alongside the full scope option Report 2.3
  • Rejected: Install electric cremators as a decarbonisation measure. Very expensive, significant carbon footprint, and existing cremators not at end of life Report P13
  • Rejected: PV panels on the Lodge. Lodge is owned and managed by Wandsworth Council, so out of NESC scope Report P13

Implications

  • Climate: Officers recommend PV panels on the Remembrance Building as the only suitable energy improvement after completing a Heat Decarbonisation Plan for Morden Cemetery. Report 3.2, P13, P14
  • Legal: The footpath project needs a formal agreement between Wandsworth Council and NESC before it can proceed. Report 6.1
  • Risk: Risk assessments, COSHH assessments and an emergency plan are on file and up to date, and no reportable accidents occurred in the quarter. Report 4.10, 4.11
  • Staffing: A gardener is moving to a 2.5 day week from October 2025, and a new full-time gardener is to start in April 2026 to allow handover. Report 4.13
  • Financial: The 2025/26 cremation target has been lowered to 1,700, with the budget adjusted accordingly. Report 4.2

Who and where

  • Visitors and bereaved families using North East Surrey Crematorium Report 4.4, 4.5
  • Crematorium staff, including gardeners Report 4.13
  • Wandsworth Council, which manages the site through Enable under a Management Agreement with NESC Report 1.1
  • Merton's Environmental Health Officer, who receives emissions reports Report 4.6

Timeline

  • September 2025 to November 2025: Quarter covered by the Surveyor's management review Report 2.1
  • From October 2025: A gardener's working pattern changes to 2.5 days per week Report 4.13
  • 05th November 2025: Date of the quarterly review of the crematorium and grounds Report 4.3
  • 18/11/2025: Final version date of the Surveyor's report Report P56
  • From April 2026: A new full-time gardener is to be employed for handover Report 4.13

Plain English for the jargon

  • NESCB / NESC: North East Surrey Crematorium Board, the joint committee that runs the crematorium
  • PV panels: Photovoltaic solar panels for generating electricity
  • CNS 004: Project reference for the main drive pedestrian pathway
  • CNS 007: Project reference for the tree of life fountain
  • COSHH: Control of Substances Hazardous to Health, a set of UK workplace safety regulations
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

The Surveyor’s findings for the management of the crematorium for the past three months (September 2025 - November 2025) be approved. 2. To proceed with the design of Option 1 for planning and tendering purposes for the main drive pedestrian pathway project (Appendix C – project CNS 004) be agreed. 3. To proceed with 2 options (full scope and reduced ... view the full minutes text for item 28.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to North East Surrey Crematorium Board

Summary

1.1This report is to provide an update on activities in the quarter to November 2025 relating to the Management Agreement between North East Surrey Crematorium Board (NESCB) and Wandsworth Council. The day-to-day management responsibilities and operation of the crematorium are carried out on behalf of Wandsworth Council by Enable.

Recommendations

2.1To approve the Surveyor’s findings for the management of the crematorium for the past three months (September 2025 - November 2025).

2.2To agree to proceed with the design of Option 1 for planning and tendering purposes for the main drive pedestrian pathway project (Appendix C – project CNS 004).

2.3To agree to proceed with 2 options (full scope and reduced scope) for the design of the tree of life fountain (Appendix C – project CNS 007).

2.4To agree to appoint an electrical consultant to carry out a feasibility for the installation of PV panels on the roof of the garden of the Remembrance Building.

3 Matters arising from previous meetings

3.1The opening hours for the entire cemetery have changed over the past few years as detailed in the table below.

Report Page 1 Official Agenda Item 6 Page 10

Pre-2020 opening hours Current opening hours Gates open at: Gates open at: 8am Monday to Saturday 8am Monday to Saturday 10am Sunday & Bank Holidays 10am Sunday & Bank Holidays

Gates close at: Gates close at: 1pm Christmas Day 1pm Christmas day 4pm November to February 5pm April to October 5pm March and October 4pm November to March 6pm April and September 4pm Saturday, Sunday & Bank holidays (all year) 7pm May to August

3.2The Heat Decarbonisation Plan for Morden Cemetery has been completed and is included in Appendix D.

With regard to the recommendations in paragraph 1.3 (page 6):

• The building’s heating is currently supplied through heat exchangers, which are already an energy-efficient source. • Installing electric cremators would be very expensive and would involve a significant carbon footprint. Also, the existing cremators have not reached the end of their service life. • The Lodge is owned and managed by Wandsworth Council. • The Remembrance Building belongs to NESC, and PV panels can be installed.

In conclusion, the installation of PV panels on the Remembrance Building is the only suitable energy improvement, and it is recommended to proceed with this measure.

4 Background and Key Information

Business Level Activity

4.1Appendix A to this report provides information on cremation numbers up to November 2025.

4.2The target for the financial year 2025/26 has been reduced to 1,700 in line with the trend observed over the first seven months. The budget setting has been adapted accordingly - please refer to the treasurer’s report.

Report Page 2 Official Page 11 Agenda Item 6

Performance Monitoring

4.3The following is a summary of the services provided for the past quarter. The review of the crematorium and grounds took place on the 05th November 2025.

Exterior/Interior

4.4Adequate parking, directional signage, notice boards, CCTV, seating, and litter receptacles were reported to be in a good state of repair and free from graffiti. The exterior of the buildings including fencing, gates and lighting were also found to be in good repair.

4.5The remembrance building and crematory were found to be in good order. Similarly, the public toilets were found to be clean and available for use with adequate supplies of consumables. The Garden of Remembrance was found to be of a good horticultural standard.

4.6No issues have been found in the emissions reports to Merton’s Environmental Health Officer.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2512 Surveyor's report: Appendix AAppendix 270 KB Download
PDF
2512 Surveyor's report: Appendix BAppendix 226 KB Download
PDF
2512 Surveyor's report: Appendix CAppendix 223 KB Download
PDF
2512 Surveyor's report: Appendix DAppendix 2 MB Download
PDF
2512 Surveyor's report: Appendix EAppendix 20 MB Download
PDF
Item 6 Surveyor Report 202512Report 207 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 11 attended
JO
Councillor John OliverChair, present
CS
Councillor Cumar SahathevanVice-Chair, present
JS
Councillor Jake ShortCommittee Member, present
FA
Councillor Finna AyresCommittee Member, apologies
TB
Councillor Tony BeltonCommittee Member, apologies
RB
Councillor Rosemary BirchallCommittee Member, apologies
AC
Councillor Annamarie CritchardCommittee Member, apologies
AG
Councillor Angela GrahamCommittee Member, apologies
MB
Councillor Michael ButcherCommittee Member, absent
BH
Councillor Billy HayesCommittee Member, present
SM
Councillor Stephen MercerCommittee Member, present

On this subject at Sutton

Search all
  1. Report of the SurveyorThis decision
  2. Report of the SurveyorNoted
  3. Report of the SurveyorApproved
  4. Report of the SurveyorAgreed
  5. Extension of the appointment of the SurveyorAgreed
  6. Report of the SurveyorApproved

More from Sutton North East Surrey Crematorium Board

All decisions
MeetingDecisionOutcome
23 Jun 2026 Minutes of the last meetingThat the minutes of the previous meeting held on 10 March 2026 be agreed as an accurate record. Agreed Open
23 Jun 2026 Appointment of ChairCouncillor Cumar Sahathevan (Sutton Council) be appointed as Chair of the North East Surrey Crematorium Board for the... Decided Open
23 Jun 2026 Appointment of the Vice ChairCouncillor Robert Morritt (Wandsworth Council) be appointed as Vice Chair of the North East Surrey Crematorium Board ... Decided Open
23 Jun 2026 Report of the SurveyorThe Surveyor’s findings for the management of the crematorium for the past two months (March 2026 - April 2026) be ap... Approved Open
23 Jun 2026 Report of the TreasurerThe Annual Internal Audit Report by the South West London Audit Partnership and endorse the management actions propos... Noted Open