CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Sutton
Sutton Shareholdings Board, Tuesday 10 March 2026 at 6.30pm

Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan

Approved Committee 3 papers

AI summarySutton Shareholdings Board approved Sutton Living Limited's business plan for 2026 to 2036 and its budget for 2026/27, and noted the company's risk register.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRisk register noted; exempt appendix
MoneyNot stated
What happens next1 April 2026Start of 2026/27 financial year covered by the budget
Who it affectsSutton Living LimitedCompany in which the Council has an ownership interest

What was decided

The Board approved Sutton Living Limited's updated business plan for the period 2026 to 2036, as set out at Appendix A. Report P1, P9

The Board approved Sutton Living Limited's proposed budget for the financial year 1 April 2026 to 31 March 2027, as set out at Appendix B. Report P1, P10

The Board noted Sutton Living Limited's Risk Register, as set out at Appendix C. Report P1, P11

Why

Legal advice said the Board must be satisfied that the initiatives are viable and that financial advice has been obtained before approving the business plan and budget. Report P1

Where grant funding or capital investment is provided by the Council to a company in which it has an ownership interest, the Subsidy Control Act 2022 must be considered to determine whether the measure is a subsidy. Report P3

What happens next

If any subsidy is provided, the Council must assess compliance with the subsidy control principles in Schedule 1 of the Subsidy Control Act 2022, and meet any applicable transparency obligations. Report P3, P4

The business plan covers 2026 to 2036 and the budget covers 1 April 2026 to 31 March 2027; no further background documents were listed beyond the appendices. Report P1, P9, P10, P14

Implications

  • Legal: If funding is given in a way that does not comply with the Subsidy Control Act 2022, an interested party may challenge the decision before the Competition Appeal Tribunal, which can quash the decision, prohibit further payments, and require recovery of the funding. Report P3
  • Legal: Where required, subsidy details must be recorded on the UK Subsidy Transparency Database within the applicable statutory time limits under sections 33 and 34 of the Subsidy Control Act 2022. Report P4
  • Financial: Financial advice should be obtained in respect of the updated business plan and proposed budget before the Board decides whether to approve them. Report P1

Who and where

  • Sutton Living Limited, a company in which the Council has an ownership interest Report P3

Timeline

  • 13/02/2026: Finance consultation by Victoria Goddard, Director of Finance Report P17
  • 26/02/2026: Legal consultation by James Fry, Senior Solicitor, SLLP Report P18
  • 2026-03-10: Sutton Shareholdings Board decision
  • 2026 to 2036: Period covered by the approved business plan Report P1, P9
  • 1 April 2026 to 31 March 2027: Financial year covered by the approved budget Report P1, P10

Plain English for the jargon

  • SLL: Sutton Living Limited, the subject company of this report
  • SCA: Subsidy Control Act 2022, governing public subsidies to companies
  • EQIA: Equalities Impact Assessment; no EQIA was carried out for this report
  • CIA: Climate Impact Assessment; no CIA was carried out for this report
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item35

Resolved

That Sutton Living Limited's updated business plan for the period 2026 to 2036 as set out at Appendix A, be approved. That Sutton Living Limited's proposed budget for the financial year 1 April 2026 to 31 March 2027 set out at Appendix B, be approved. That Sutton Living Limited’s Risk Register as set out at Appendix C, be noted.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Sutton Shareholdings Board

Page 121 Agenda Item 8 Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan

f

Report Title Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan

Committee Sutton Shareholdings Board

Meeting Date 10 March 2026

Chair Councillor Sunita Gordon

Report From Spencer Palmer, Strategic Director of Environment, Housing and Neighbourhoods

Report Author Firas Al-Sheikh, Managing Director (Sutton Living Ltd)

Ward(s) Affected Company Business

Ambitious for Sutton Quality and affordable housing priorities

Open/Exempt Open, with the exception of Appendix C, by virtue of paragraph 3 of Schedule 12A of the Local Government Act 1972

Signed Date 26 February 2026

1​ Summary​

1.1​ Developing and acquiring additional homes through the Council-owned company Sutton Living Limited (SLL) remains a key mechanism for delivering the Council’s Ambitious for Sutton priority of providing quality and affordable housing for residents.

1.2​ The updated 10-year Business Plan (2026–2036) sets out SLL’s plans to build on its achievements to date, respond to current market conditions, and transition into a sustainably profit-making housing company. The plan reflects a deliberate shift in focus away from new build development towards the acquisition and long-term management of affordable rented homes, supporting the Council’s objectives to reduce homelessness, limit reliance on temporary accommodation, and achieve better value for money over the medium to long term.

1.3​ Since the previous business plan, SLL has significantly expanded its landlord portfolio and secured substantial additional funding through the Local Authority Housing Fund (LAHF) round 4. The company currently owns or manages 61 homes, with this expected to exceed 100 by the end of 2026/27 and to grow to over 300 homes by the end of the plan period. These homes are primarily let to households nominated by the Council, delivering both housing stability for residents and recurring savings to the Council’s homelessness budgets.

Report Page 1 Agenda Item 8 Page 122 Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan

1.4​ The Business Plan is transparent about short-term financial challenges, including the forecast loss arising from the completion of the Grove development and the requirement to grow rental income. These pressures are time-limited and are managed within an agreed framework of Council support. As the acquisition programme progresses and rental income grows, the plan demonstrates improving financial performance, with SLL forecast to generate cash surpluses from 2027/28 and to return to profitability from 2028/29.

1.5​ Over the longer term, the plan shows a strengthened financial position compared to previous forecasts, with earlier achievement of retained surpluses and improved value for money for the Council. The proposal to establish a Registered Provider of social housing is a key enabler of this strategy, unlocking access to additional grant funding, potential improvements to tax efficiency, and reducing reliance on Council funding over the longer term.

1.6​ Overall, the Business Plan demonstrates that SLL is operating as a disciplined, well-governed company that is aligned with the Council’s priorities, actively managing risk, and delivering tangible benefits for Sutton and its residents. Approval of the plan and associated budget will enable SLL to continue scaling its impact while progressing towards long-term financial sustainability.

2​ Recommendations​

2.1​ To approve Sutton Living Limited's updated business plan for the period 2026 to 2036 in Appendix A.

2.2​ To approve Sutton Living Limited's proposed budget for the financial year 1 April 2026 to 31 March 2027 in Appendix B.

2.3​ To note Sutton Living Limited’s Risk Register in Appendix C.

3​ Background and Key Information​

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan: Appendix AAppendix 742 KB Download
PDF
Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan: Appendix BAppendix 243 KB Download
PDF
Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business Plan: ReportReport 418 KB DownloadRead as text

At this meeting

Whole meeting
31MinutesAgreed 33Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetApproved 34Cognus Business Plan and BudgetNoted
35Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThis decision

Who was there

5 of 5 attended
SG
Councillor Sunita GordonChair, present
JS
Councillor Jake ShortVice-Chair, present
MJ
Councillor Marian JamesCommittee Member, present
TC
Councillor Tim CrowleyCommittee Member, present
MD
Councillor Mike DwyerCommittee Member, present

On this subject at Sutton

Search all
  1. Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanThis decision
  2. Sutton Living Ltd Mid-Year Performance and Finances 2025-26Noted
  3. Sutton Living Ltd Business Plan and BudgetApproved
  4. Sutton Living Ltd Mid-Year Performance and Finances 2024-25Noted
  5. Sutton Living Ltd 2024-29 Business Plan and BudgetApproved
  6. Sutton Living Ltd Mid-Year Performance and Finances 2023-24Approved

More from Sutton Sutton Shareholdings Board

All decisions
MeetingDecisionOutcome
10 Mar 2026 MinutesRESOLVED : that the minutes of the meeting held on 4 November 2025 be agreed as an accurate record. Agreed Open
10 Mar 2026 Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetThat the Sutton Decentralised Energy Network 2026-29 Business Plan and budget be approved. That the Sutton Decentrali... Approved Open
10 Mar 2026 Cognus Business Plan and BudgetThat the progress made by Cognus Limited against its 2025/28 Business Plan be noted. That the update on Cognus Limite... Noted Open
4 Nov 2025 MinutesRESOLVED : that the minutes of the meeting held on 25 March 2025 be agreed as an accurate record. Agreed Open
4 Nov 2025 Sutton Living Ltd Mid-Year Performance and Finances 2025-26That the public and press be excluded from the remainder of this meeting on the grounds that the remaining item on th... Noted Open