AI summarySutton Environment and Sustainable Transport Committee approves a three year extension of the Highways Term Maintenance Contracts with R.J. Dance and F.M. Conway, alongside minor variations across three lots.
Money2025/26 spend shownRevenue £3,969,404; capital £7,917,504 across both contractors
What happens nextDeed of variation neededModifications to be finalised and recorded formally
Who it affectsTwo contractors and partner boroughR.J. Dance, F.M. Conway, and RB Kingston upon Thames
What was decided
The committee approved a three year extension of the Highways Term Maintenance Contracts covering Lot 1 (Reactive and Routine Maintenance), Lot 2 (Planned Improvements) and Lot 3 (Planned Maintenance), alongside minor variations set out in Appendices A and B. Report P29, P30
The extension is taken as a single three year period rather than three one-year increments, with changes to KPIs incorporated. Report P16, P17
Royal Borough of Kingston upon Thames, which already accesses the contracts, is to be kept informed of the variation. Report P21
Why
Officers cited value for money and continuity of highway services, and noted both contractors passed the council's financial health checks. Report P11
The contractors support climate goals through recycling up to 98% of highway waste, low-carbon asphalt with up to 90% recycled content, and use of Euro 6 compliant vehicles. Report P1
Legal review under regulation 72 of the Public Contracts Regulations 2015 concluded the risk of a procurement challenge is low because the original tender documents advertised the extension options. Report P15, P17, P24
What happens next
Negotiate and formalise the variation with the contractors and RB Kingston, then record it in a binding deed of variation. Report P21, P22
Continue annual indexation on contract rates as the standard framework clause, with negotiation on new rates where issues arise. Report P10
Manage all spending within existing Capital and Revenue budgets, using the call-off nature of the contract to scale work flexibly. Report P8, P9, P13
The money
1,971,760 R J Dance 2025/26 revenue, Sutton share Report P6
1,320,812 R J Dance 2025/26 revenue, Kingston share Report P6
3,292,572 R J Dance 2025/26 revenue total Report P6
4,319,688 2025/26 capital total, Kingston Report P7
7,917,504 2025/26 capital total, both boroughs Report P7
Options considered
Chosen: Approve three year extension of Lots 1, 2 and 3 with minor variations in Appendices A and B. Ensures value for money, continuity of service, and supports climate goals; legal challenge risk assessed as low. Report P1, P11, P24
Implications
Financial: As a call-off contract the council is only billed for instructed work, so spend can be flexed within annual Capital and Revenue budgets; no guarantee of volume applies. Report P8, P9, P13
Legal: Modifications must comply with regulation 72 of the Public Contracts Regulations 2015; the official risk of procurement challenge is rated low. Report P15, P17, P24
Climate: Climate Impact Assessment (Appendix C) judged the extension to have a positively improved impact on the council's climate goals and net-zero targets. Report P1, P31
Equalities: An Equalities Impact Assessment (Appendix D) is listed among the appendices. Report P32
Other: RB Kingston already accesses the contracts; variation must be negotiated with their knowledge to keep terms aligned across both boroughs. Report P21
Who and where
R.J. Dance, contractor for Lot 1 Reactive and Routine Maintenance Report P15
F.M. Conway, contractor for Lot 2 Planned Improvements and Lot 3 Planned Maintenance Report P15
Royal Borough of Kingston upon Thames, partner borough accessing the contracts Report P21
London Borough of Sutton residents receiving highways services Report P1
2026-06-25: Environment and Sustainable Transport Committee meeting where the extension was approved
Plain English for the jargon
Lot: A separate contract package within a procurement, here covering reactive, planned improvement, and planned maintenance work.
Call-off contract: A framework arrangement where the buyer instructs specific work as needed, with no guaranteed volume.
PCR 2015: Public Contracts Regulations 2015, the procurement rules that govern how these contracts can be modified.
Indexation: An annual adjustment to contract rates at the end of each financial year, applied the following year.
CIA: Climate Impact Assessment, completed for this extension and attached as Appendix C.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
To approve the Highways Term Maintenance Contracts extension, alongside minor variations as set out in Appendices A and B, for Lot 1 (Reactive and Routine Maintenance), Lot 2 (Planned Improvements) and Lot 3 (Planned Maintenance) for a further three years.
Word for word from the decision Sutton published for this meeting.Source: moderngov.sutton.gov.uk
Report to Environment and Sustainable Transport Committee
Page 23 Agenda Item 10 Highways Term Maintenance Contracts Extension
Report Title Highways Term Maintenance Contracts Extension
Committee Environment and Sustainable Transport Committee
Meeting Date 25 June 2026
Chair Councillor Christopher Woolmer
Report From Spencer Palmer, Strategic Director Environment Housing and Neighbourhoods
Report Author(s) Craig Adams, Head of Service Highways and Transport [phone removed]
Ward(s) Affected All Wards
Ambitious for Sutton Action on climate change priorities An inclusive place for everyone Strong and fair economic growth An efficient and well run Council
Open/Exempt Open
Signed Date 16 June 2026
1 Summary
1.1 The work delivered by the Highways Term Maintenance contracts support the delivery of several Ambitious for Sutton priorities including, action on climate change, an inclusive place for everyone, strong and fair economic growth and an efficient and well run council.
1.2 This report seeks approval to extend the current Highways Term Maintenance Contracts (Lots 1, 2, and 3) for a further 3 years, securing the continued delivery of essential reactive, routine, and planned highway works across the borough until 2030. This will support the delivery of the Ambitious for Sutton priorities; taking action on climate change, fostering an inclusive place for everyone, promoting strong and fair economic growth, and maintaining an efficient and well-run Council.
1.3 These contracts have been in place since April 2020. The contract was set up for 7 years with an option to extend for a further 3 years. This report seeks approval to implement the extension to ensure service continuity. Minor variations, as set out in Appendices A and B, have been agreed with the contractors as part of the extension to improve key performance indicators, amend operational rates, and enhance social value delivery.
2.1 To approve the Highways Term Maintenance Contracts extension, alongside minor variations as set out in Appendices A and B, for Lot 1 (Reactive and Routine Maintenance), Lot 2 (Planned Improvements) and Lot 3 (Planned Maintenance) for a further three years.
3 Background and Key Information
3.1 The Council has a duty to its residents to provide a safe, accessible, and well-maintained environment and a statutory duty under the Highways Act 1980 to maintain all publicly adopted highways and footways safely. Because the Council does not maintain a large, in-house construction workforce, it procures these services through a Term Maintenance Contract (TMC). This is a framework agreement that allows the Council to instruct awarded contractors to carry out repairs and improvements as required on the highway network.
3.2 The Council's current Highways Term Maintenance Contract commenced on 1 April 2020. The existing allocation for these services comprises: ● Lot 1 (RJ Dance Ltd): Reactive and minor maintenance (e.g., emergency repairs, out of hours response, repairing potholes, minor patching). ● Lots 2 and 3 (FM Conway Ltd): Planned improvements, gully cleaning, large-scale resurfacing, vehicle crossovers and schemes (e.g., new zebra crossings, cycle routes, raised junctions, lining and signing etc.).
3.3 The initial contract term expires in March 2027. The contract included the option to extend by up to three years. The contractor performance is measured using Key Performance Indicators (KPIs) to monitor and continually improve the impact of the service across critical areas, including customer satisfaction, the timely completion of works, achieving zero defects, environmental performance, and social value. Further detail on current contract performance is shown in appendix E
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Sustainable Transport Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.