Award of Design and Build Contract for the Meads Community Centre
ApprovedExecutive1 paper
Cabinet - Decommissioned 18.05.2022 approved this item on Wednesday 29 April 2015. Below is the council's own wording, with the papers it was decided on.
(1) That the appointment of BMR Construction Ltd as design and build contractor for The Meads Community Centre with an approved budget of £400,000 be approved. (2) That delegated authority be given to the Director of Regeneration in consultation with the Cabinet Member for Localism, Sport, Heritage and Culture and Cabinet Member for Finance to increase the contract value if additional external funding becomes available for this project.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.1The Meads development within Sittingbourne is the subject of three Section 106 agreements. The Redrow Homes development provides a piece of land which has been designated for community use in the masterplan and a sum of £200,000 for the purpose of community facilities and/or a community building anywhere within the land. The Baradon Properties Limited Section 106 Agreement provides £210,000 for the purpose of a Community Hall. In addition a further £100,000 has been allocated to the community centre from the S.106 contributions from the residential development of the Watermark site.
2.2Work has been on-going to develop a Community Centre within The Meads development for a number of years. Originally the aim was to build an iconic building for the site which would cost in the region of £1.4million, due to changes in the economic climate and funding sources that are available, the project became untenable. To date £62,687 has been spent on the original project the majority of spend relating to architect fees and a public consultation exercise. This leaves a current balance of £447,313 held by Swale Borough Council.
2.3Since 2011 a range of options have been considered for the project including joint working with Bobbing Parish Council to collaborate in order to develop a bigger hall. However, this was deemed not feasible as significant funding would still need to be attracted and there are limited grants available for these types of projects currently for the demographic of this community. Due to lack of progress on the project a number of Trustees resigned and so it was decided to re- evaluate the project and the project was refocused at developing a centre within the existing budget and on the allocated site.
2.4The Meads Community Centre Trust (MCCT) was established in April 2011 to work with SBC to develop the design of the Community Centre, ensure resident’s views were included within the project and develop as a Trust to manage the Community Centre upon completion. MCCT currently comprises of five trustees all who reside at The Meads and recently successfully registered as a Charitable Incorporated Organisation (CIO) with the Charities Commission. MCCT has also produced and adopted a business plan and is in the process of developing all the relevant policies including health and safety, equalities and safeguarding.
2.5In order to ensure that the community centre was developed and met the community’s requirements, the MCCT obtained funding from the Big Lottery to carry out community consultation to inform the future requirements of the community centre. The MCCT ran a number of activities in 2013 to engage the local community and capture their views, which then informed the service specification for the design and build contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.