New Road Industrial Estate - Claim for Dilapidations
AgreedExecutive1 paper
Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 2 December 2015. Below is the council's own wording, with the papers it was decided on.
(1) That a budget is allocated from the Council’s reserves to cover the settlement of the claim. (2) That the Head of Property Services, in conjunction with the Head of Finance and the Cabinet Member for Finance, be delegated to agree the final amount required.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.1Members will recall that the Council’s leases of Phase 1 and 2 of New Road Industrial Estate, Sheerness, expired on 10 August 2014 and 3 April 2015 respectively, and it was agreed by Cabinet at its meeting on 4 December 2013 that the Council would not enter into new leases. The Council continues to own the freehold interest in the land, and receives the ground rent under the two long term ground leases.
2.2As advised in the previous report, the Council was responsible under the terms of its leases for all repairs and maintenance during the period of these leases. At the end of the lease the landlord is entitled to claim for any financial loss they incur as a result of the tenant’s breach of its repairing liability. The claim is made by serving a schedule of dilapidations under the Law of Property Act 1925. 2.3 Claims for dilapidations have now been made by the landlord, and a specialist dilapidations surveyor has been engaged to deal with the claim on the Council’s behalf. This is to ensure that the amount of the claim is minimised in accordance with the law of dilapidations.
3 Proposals
3.1It is proposed that an in principle decision be made for use of reserves to cover the settlement of the claim. It is also proposed that the Head of Property Services, in conjunction with the Head of Finance and the Cabinet Member for Finance, be delegated to agree the final amount required. The final amount remains subject to ongoing discussion, and it is therefore inappropriate to report potential figures at this stage in order to preserve our negotiating position.
Alternative options
4.1The Council has a legal obligation to pay an agreed figure for dilapidations in accordance with the law. Given the nature of the claim the final figure will be one- off, and so the use of reserves is the most appropriate way to cover the claim. No other options would be sensible.
5 Consultation Undertaken or Proposed
5.1The Head of Finance and the Cabinet Member for Finance have been consulted on this proposal and support this action.
6 Implications
Issue Implications Corporate Plan This proposal supports the Council’s corporate priority of ‘a Council to be proud of’ through appropriate management of its financial resources to ensure that it complies with its legal and financial liabilities. Financial, A budget will be allocated from the Council’s reserves to cover the Resource and settlement of the claim. Agreement of the final amount required will Property be delegated to the Head of Property Services, in consultation with the Head of Finance and the Cabinet Member for Finance. Legal and The final claim is to be settled in accordance with the law of Statutory dilapidations, which is a combination of statute, contract and common law. Crime and None identified at this stage Disorder Sustainability None identified at this stage Health and None identified at this stage Wellbeing Risk Management None identified at this stage and Health and Safety Equality and None identified at this stage Diversity
Appendices
7.1None
Background papers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.